Risk Management Flashcards

(17 cards)

1
Q

Can you tell me an example of something ‘Employer Other Risk’ is designed to cover?

A

Covid.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Can you run me through the Risk mitigation methods as outlined by RICS?

A

S - Sharing
T - Transfer
A - Avoidance
R - Reduction
R - Retention

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Can you give me an example of Risk Transfer, and an example of Risk Sharing?

A

Transfer = Design and Build contract transfer of design risk.

CDP = Sharing of design responsibility.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What would you expect to see on a risk register?

A
  • Reference
  • Description
  • Action / Owner
  • Status
  • RAG status
  • Cost impact
  • Probability
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the monte carlo simulation?

A

A computer based software used to generate potential outcomes.

It can identify risks that have the most impact on project outcome.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How would you make an allowance for risk in a Stage 4 Cost Plan?

A

Priced risk register

If this information is not available, then % driven.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

You say you informed the CA of the commercial impact - how did you price risk?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Can you tell me any other methods of pricing risk?

A
  • Simple
  • Probabilistic
  • Percentage
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the simple method for pricing risk?

A

A likely cost multiplied by the probability of occurrence.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the probabilistic method for pricing risk?

A

A more in-depth version of simple method. It assigns the probability of best, likely and worst case scenario’s to generate an expected value per assumption.

The total of three probabilities should be 1 or 100%.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

On what basis do you think risks should be allocated to each party at post contract stages - can you give me an example?

A

Risks should be allocated based on who would be best to mitigate the risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the differences between the risk allowances in a D&B and Traditional procurement route?

A

The Contractor takes more risk on a D&B as they are in control of the Design as well as the Build, whereas Traditional the Contractor doesn’t take risk of the design.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How would the risk in a D&B procurement compared to Traditional affect cost plans?

A

In a D&B you would have D&B risks and D&B fees.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Who takes the time risk on a D&B?

A

Contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

On a traditional procurement who takes design risk?

A

Client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

On a traditional procurement who takes build risk?

17
Q

On the PWI project, why are you producing the risk register rather than the PM?

A

I did not produce a risk register, the PM did.