Risk Management Flashcards

(42 cards)

1
Q

Primary Risk Management Processes

A
  • Plan Risk Management
  • Identify Risks
  • Perform Qualitative Risk Analysis
  • Perform Quantitative Risk Analysis
  • Plan Risk Responses
  • Control Risks
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Known Risks

A
  • have been identified and analyzed
  • possible to plan responses
  • Knwon risk that cannot be proactively managed should be assigned contingency reserves
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Unknown Risks

A
  • cannot be managed proactively
  • Should be assigned a management reserve
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Risk Appetite

A
  • degree of uncertainty an entity is willing to take on in anticiaption of a reward
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Risk Tolerance

A
  • Degree, amount, or volume of risk that an organization or individual will withstand
    *
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Risk Threshold

A
  • measures along the level of uncertainty ir the level of impact at which a stakeholdr may have a specific interest
  • Below the threshold, they will accept the risk
  • Above the threshold, they will not tolerate the risk
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Risk Management Plan Components

A
  • Methodology
  • Roles and Responsibilities
  • Budgeting
  • Timing
  • Risk Categories
  • Definitions of risk probability and impact
  • Probability and Impact Matrix
  • Revised Stakeholder tolerances
  • Reporting formats
  • Tracking
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Risk Information Gathering Techniques

A
  • Brainstorming
  • Delphi Technique
  • Interviewing
  • Root Cause Analysis
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Brainstorming

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Delphi Technique

A
  • Way to reach a concensus of experts
  • Participate anonymously
  • Use a quesitionairre to solicit ideasabout important risks
  • ideas are consolidated then recirculated to the experts
  • Helps to redues bias in the data
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Root-Cause Analysis

A
  • USed to identify a problem or to discover the underlying cause that lead to it, and develop preventative action
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Risk Diagramming Techniques

A
  • Cause and Effect Diagrams
  • System or process flow charts
  • influence diagrams
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Checklist Analsysis

A
  • Use of a checklist for risks from historical information
  • Should not be used in place or proper risk management
  • Would likely be used for very repeatable projects and processes
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Risk Cause and Effect Diagrams

A
  • Also known as fishbone diagrams
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Risk System or process flow charts

A
  • how various elements of a system interrelate and the mechanism of causation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Influence Diagrams

A
  • Graphical representations of situations showing causal influences, time ordering of events, and other relationships aming variables and outcomes
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

SWOT Analysis

18
Q

Qualitative Risk Assessment Tools and Techniques

A
  • Risk proabability and Impact Assessment
  • Probability and Impact Matrix
  • Risk Data Quality Assessment
  • Risk Categorization
  • Risk Urgency Assessment
19
Q

Risk probability and impact assessment

A
  • looking at the prbability and impact on each risk
  • Think of the traditional risk log
20
Q

Probability and impact matrix

A
  • Risk rating rules usually pre-defined
  • matrix to score each risk based on probability and impact
  • Color scales may be used to identify high, medium, low risk based on organizational rules
  • Risk Scores help to determine priority of action and response
22
Q

Risk Data Quality Assessment

A
  • Determining the degree to which riskl data is useful in managing those risks
  • For example, do you have adequate information to understand and rsspond to the risk
23
Q

Risk Categorization

24
Q

Risk Urgency Assessment

A
  • Considers indicators of priority
  • risks requiring near-term responses
25
Quantitative Risk Analysis
* Risk evaluation based on numerical analysis * May or may not be possible depdning on data available for the project * Almost always follows the qualitative analysis process
26
Qualitative Risk Analysis Techniques
* Data Gathering and Representation Techniques * Interviewing * Probability Distributions * Modeling Techniques * Sensitivity Analysis * Expected Monetary Value (EMV) Analysis * Modeling and Simulation
27
Data Gathering: Interviwewing
* drawing on historical data * Estimasting risk based on low, most likely, and high estaimtes
28
Probability Distributions
* represent uncertsinty in values * Think bell curve * Shape of curves may be determined by data or by risk policies
29
Sensitivity Analysis
* Used to determine which risks have the most potential impact on the project * Investigates the extent to which uncertainty or each proejct element affects the objecitves when all other uncertain elements are held constant * Common representation of this is the Tornado Diagram * Y-Axis contains each type of uncertainty * X-Axis contains the spread or correlation of the uncertainty at base values
30
Expected Montetary Value Analysis
* Calculates the average outcome when future includes scenarios that may or may not occur * Used for analysis under uncertainty * Opportunities generally expressed as positive values * Threats usually expressed as negative values * Requires a risk-neutral assumption (neither risk averse, nor risk seeking) * Typically uses decision tree analysis * EMV is calculated by multiplying the value of each posible outcome by its probability of occurence and adding the products together
31
Modelling and Simulation
* translates the specificed uncertainties into their potential impact on project objectives * Typically performed using the Monte Carlo technique
32
Negative (Threat) risk response techniques
* Avoid * Transfer * Mitigate * Accept
33
Positive (Opportunity) Risk Response Techniques
* Exploit * Enhance * Share * Accept
34
Avoid
* Negative Risk Repsonse strategy where project team acts to eliminate the threat or protect the team from its impact * Usually changes the project's objectives, including changing scope, or to the extreme of shutting down the project
35
Transfer
* Negative risk response strategy in which the proejct team transfers the impact of the threat to a third party, along with the ownership of the response * Does not eliminate risk * Typically includes payment of a risk premium to the owning party (higher rates, etc) * Contracts might be used to transfer liability * Reason for companies hiring vendors for example
36
Mitigate
* Negative risk response sterategy in which the project team acts to minimize the probability of occurance or impact of a risk * Examples include: * adopting less complex processes * conducting more tests * choosing a more stable supplier * designing redundancy into a system
37
Accept
* Negative risk response strategy in which the project team decides to acknowledge the risk and not take any action unless the risk occurs * Usually used when there is no way to address a risk in any other way
38
Exploit
* Positive risk response strategy in which the organization wants to ensure that the opportunity is realized * Esnuring the opportunity definitely happens
39
Enhance
* Positive risk response strategy used to increase pobabilityand/or positive impacts of an opportunity * Example: is adding more resources to an activity to finish early
40
Share
* Positive risk response in allocating some or all of the ownership to a third party that is more capable of capturing the opporunity * Example might include outsourcing for a specialized task
41
Accept
* Positive risk strategy in which the team is willing to take advantage of the opportunity if it arises, but does not actively pursue it
42
Contingent Response Plan
* Risk response plan that will only be executed if certain conditions occur