rule 2 Flashcards
(73 cards)
Rule 2
Procurement Planning
Section 7
Procurement Planning and Budgeting Linkage
7.1 All the procurement shall be within the ABC of the procuring entity and should be meticulously and judiciously planned by the procuring entity
true na true
7.2 no procurement shall be undertaken unless it is in the accordance with the approved ________ (APP) of the procuring entity
Annual Procuring Plan
7.3 the APP shall be formulated sand revised only in accordance with the guidelines
okayyy
7.4 Updating of the individual project Procurement management plan (PPMPs) and the consolidated APP for each procuring entity shall be undertaken every ___ or as often as may be required by the Head of the Procuring Entity.
6 months
7.5 The ABC as reflected in the APP or PPMP shall be at all times ______ with the appropriations for the project authorized in the General Appropriations Act (GAA), continuing, and automatic appropriations, the corporate budget, and the appropriation ordinance, as the case may be.
consistent
RULE 3
Procurement by Electronic Means
Procurement by Electronic Means and the Philippine Government Electronic System (PhilGEPS)
Section 8
8.1.1 To promote transparency and efficiency, information and communications technology shall be utilized in the conduct of procurement procedures. Accordingly, there should be a _____ portal that shall serve as the primary source of information on all government procurement.
single
______ shall serve as the primary and definitive source of information on government procurement
PhilGEPS
8.2 Features of PhilGEPS
a. electronic bulletin board
b. registry of manufacturers, suppliers, distributors, contractors, and consultants
c. electronic catalogue of common and non-common use goods, supplies, materials and equipment
8.3.1All procuring entities are mandated to fully use the PhilGEPS in accordance with the polices, rules, regulations, and procedures adopted by the GPPB and embodied in this IRR.
Procuring Entities shall register with the PhilGEPS and shall undertake measures to ensure their access to an on-line network to facilitate the open, speedy and efficient on-line transmission, conveyance and use of electronic data messages or electronic documents.
8.4.1 Procuring Entities with videoconferencing capabilities that have manufacturers, suppliers, distributors, contractors and/or consultants that also have videoconferencing capabilities may conduct their pre-bidding conferences electronically
8.4 Pre-bid Conferences and Notices under the PhilGEPS
8.4.2 Requests for clarification from bidders may be sent _______ to the ABC
Electronically
RULE 4
Competitive Bidding
All procurement shall be done through competitive bidding, except as provided in Rule XVI of this IRR
true
the procurement process from the opening of bids up to the award of contract should not exceed ____ or a shorter period to be determined by the Procuring Entity concerned. (IRR-A Section 38)
3 months
STEPS/PROCEDURE:
q. Advertise and post IAEB
accept letter of intent
b. Issue the bidding document
c. Call a pre-bid conference
d. Receive and open the technical and financial envelopes
e. Evaluate the bids
post-qualify
f. award the contract
g. have the contract signed and approved
h. issue the notice to proceed
RULE 5
Bids and Awards Committee
Section 11
The BAC and its Composition
The head of the procuring entity shall designate at least ____ but not more than ___ members to the BAC of unquestionable integrity and procurement proficiency
5 to 7
Section 12
Functions of the BAC
a. advise and/or post the invitation to bid/request for expressions of interest
b. conduct pre-procurement and pre-bid conferences
c. determine the eligibility of bidders
d. undertake post-qualification proceedings
e. resolve motions for reconsideration
f. recommend award of contracts to the head of procuring entity
g. recommend the imposition of sanctions in accordance with RULE XXIII
h. performs such other related functions as may be necessary
RULE 6
Preparation of BIdding Documents