Plan Schedule Management - Inputs/T&T/Outputs

A
Inputs
.1 Project charter
.2 Project management plan
.3 Enterprise environmental factors
.4 Organizational process assets

Tools & Techniques
.1 Expert judgment
.2 Data analysis
.3 Meetings

Outputs
.1 Schedule management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Define Activities - Inputs/T&T/Outputs

A

Inputs
.1 Project management plan
.2 Enterprise environmental factors
.3 Organizational process assets

Tools & Techniques
.1 Expert judgment
.2 Decomposition
.3 Rolling wave planning
.4 Meetings
Outputs
.1 Activity list
.2 Activity attributes
.3 Milestone list
.4 Change requests
.5 Project management plan updates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Sequence Activities - Inputs/T&T/Outputs

A
Inputs
.1 Project management plan
.2 Project documents
.3 Enterprise environmental factors
.4 Organizational process assets
Tools & Techniques
.1 Precedence diagramming method
.2 Dependency determination and integration
.3 Leads and lags
.4 Project management information system

Outputs
.1 Project schedule network diagrams
.2 Project documents updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Estimate Activity Durations - Inputs/T&T/Outputs

A
Inputs
.1 Project management plan
.2 Project documents
.3 Enterprise environmental factors
.4 Organizational process assets
Tools & Techniques
.1 Expert judgment
.2 Analogous estimating
.3 Parametric estimating
.4 Three-point estimating
.5 Bottom-up estimating
.6 Data analysis
.7 Decision making
.8 Meetings

Outputs
.1 Duration estimates
.2 Basis of estimates
.3 Project documents updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Develop Schedule - Inputs/T&T/Outputs

A
Inputs
.1 Project management plan
.2 Project documents
.3 Agreements
.4 Enterprise environmental factors
.5 Organizational process assets
Tools & Techniques
.1 Schedule network analysis
.2 Critical path method
.3 Resource optimization
.4 Data analysis
.5 Leads and lags
.6 Schedule compression
.7 Project management information system
.8 Agile release planning
Outputs
.1 Schedule baseline
.2 Project schedule
.3 Schedule data
.4 Project calendars
.5 Change requests
.6 Project management plan updates
.7 Project documents updates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Control Schedule - Inputs/T&T/Outputs

A
Inputs
.1 Project management plan
.2 Project documents
.3 Work performance data
.4 Organizational process assets
Tools & Techniques
.1 Data analysis
.2 Critical path method
.3 Project management information system
.4 Resource optimization
.5 Leads and lags
.6 Schedule compression
Outputs
.1 Work performance information
.2 Schedule forecasts
.3 Change requests
.4 Project management plan updates
.5 Project documents updates