Section 1 Terms Flashcards

1
Q

Professional services agreement

A

A contract between an owner and consultant for a task or set period of time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Work Breakdown Structure

A

A visual hierarchical deconstruction of all work to be done for a project that shows deliverable tasks and relation to other tasks. Used to create a schedule. Outlines overall work plan including finance/budget, feedback, monitoring, and tasks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

field order

A

change to plans issued by the Landscape Architect that requires no cost or schedule changes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

“At risk” construction management

A

CM services are provided as an independent contractor rather than as an owner agent. CM must deliver project that meets GMP requirement or compensate the owner/be penalized

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Post construction evaluation

A

evaluation done after final completion determining if the design meets the needs of the owner and users

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Change Order

A

a change made within the general scope of a contract. Usually means additional pay or time for contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Active interference

A

owner caused problems that prevent the contractor from staying on schedule. For example: not providing drawings on time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Stop Notice

A

an order to stop work until being paid in public projects. Generally not used in private contracts (liens used instead)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

0% Completion

A

item not started (CD Phase)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

25% Completion

A

item started, still in progress

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

50% Completion

A

drawing started, not labeled

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

90% Completion

A

item is complete but has not been reviewed for QC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Punch list

A

List following substantial completion. Largely small items required to reach final completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

GMP

A

Guaranteed Maximum Price. This is the maximum price for a construction project created by the contractor using design documentation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Maximum-not-to-exceed

A

Maximum price for design services.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Schedule of values

A

Comprehensive list of items on a project representing the entire project and contract price. Can be used as a basis for submitting and reviewing progress payments. Incidental items are not listed but included in larger elements. For example: re-bar is included in concrete.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Record Drawings

A

Final set of drawings created by the architect that include all reported changes that happened during construction. Not considered the same as as-built drawings, which are created by the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Notice of award

A

Given to the contractor as a notice they have been awarded a contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Notice to proceed

A

Notice that a contractor can begin construction process. GC will generally not begin ordering or any other processes until given this notice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Overhead

A

non-labor costs associated with operating an office

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Bid Bond forfeiture

A

GC backs out after being awarded a contract. Must forfeit value of surety bond (5% of contract amount) up to price of the next highest bid to compensate owner. May also be required to forfeit bond value outright

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Contingency

A

Wiggle room allotting extra budget for unforeseen issues. Generally 5-10% when estimated by an LA.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Bid rejection

A

Bid is thrown out & not considered. In public work this can be for lateness, not being a regular bid, or not meeting bond requirements. Private work can reject any and all bids for any reason, but this will create bad relationships between owners & contractors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

opinion of probable cost

A

cost estimate from designer based on takeoffs, details, and specifications. Not intended to be authoritative

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Public work: Drawing ownership
In public work, drawings generally belong to the owner unless otherwise specified in the contract
26
Private work: Drawing ownership
In private work, drawings generally belong to the designer unless otherwise specified in the contract
27
"Or equal" & "Or approved equal" specification
This is a modification to a proprietary specification. "Approved" equal requires approval from the designer
28
Specification parts
Pt. 1: General; Pt 2. Product; Pt. 3 Execution
29
CSI Division 1
General Requirements
30
CSI Division 2
Existing Conditions
31
CSI Division 3
Concrete
32
CSI Division 4
Masonry
33
CSI Division 9
Finishes
34
CSI Division 31
Earthwork
35
CSI Division 32
Exterior Improvements
36
CSI Division 12
Furnishings
37
Statement of Interest
Given in response to a pre-project RFI
38
Errors & Omissions Insurance
professional liability insurance purchased to protect a firm from mistakes, claims of negligence, or failure to perform duties
39
Clerk of Works
Responsible for verifying quantities of delivered materials & confirming work is carried out properly and safely. Also responsible for ensuring quality of workmanship and safety is proper, and reports back to clients.
40
General Statute of Limitations
6-10 years for contracts, less for torts
41
Project work plan
Scheduling tool. Organizational framework to plan how and when project will occur
42
Binding arbitration
Arbitration that is court-enforceable but does not set legal precedent.
43
Work Plans
Plan for completing work put together by contractor before construction
44
Shop drawings
Drawings, diagrams, or illustrations clarifying exactly how something will be fabricated. Used for custom items as well.
45
Certificate of occupancy
Certificate issued by government building authority confirming a building/project is safe to occupy. Typically occurs around same time as substantial completion, but is not related.
46
Notice of Substantial completion
Notice given to contractor after approval from owner that project is largely complete & is followed by a punch list. Owner can no longer assess liquidated damages (lateness) and can only withhold costs for repair or punch list items.
47
Gantt Chart/Bar Chart
method of project scheduling for medium sized projects with limited deadlines, deliverables, and consultants
48
Critical Path Method
project scheduling process flow diagram superimposed over a timeline with deadlines. Handles large complex projects.
49
Milestone List
simplistic scheduling tool often used to convey schedule status without going into major detail
50
Construction Contract Documents
contains all documents for a project including correspondence & addendums. Completed when project is closed out, and thereby does not contain bid requirements which are no longer relevant.
51
Project Profit Goal
15-20%
52
Project Related Expenses
Non-labor costs like printing, messenger services, etc. Charged to client with 10% markup.
53
ALTA Survey
American Land Title Association Survey. Detailed land parcel map showing improvements, utilites, and other significant observations
54
Five Project Phases
start, planning, design, production, closeout
55
Architects Supplemental Instruction (ASI)
Issued by architect to contractor as a response to an RFI. Used to clarify drawings or make corrections to a drawing after it has been issued. Generally does not affect budget or timeline.
56
Request for Information (RFI)
Issued by contractor to architect asking for clarification on plans or details
57
Project Manual
All project documents except for CD's. Includes specifications. Basically everything written in text before a project has begun.
58
Bidding Documents
All project documents needed for a contractor to create a bid. Does not include project modifications.
59
Alternative Dispute Resolution (ADR)
Methods to resolve conflict outside of the legal system. Main methods are arbitration, mediation, & partnering
60
Partnering
Method of dispute resolution where two groups solve an issue among themselves
61
Goals
Universal principles applied at all projects that do not change
62
Comprehensive General Liability Insurance
protects from lawsuits related to injury sustained by the general public, and from third party lawsuits
63
Separate Contracts Method
owner contracts all disciplines themselves. Also referred to as Multiple Prime contract method
64
Backcharging
provision in a contract allowing one party to recover expenses covering work from another when the other fails to perform. Not to be confused with acceleration.
65
Primary cause of cost overruns
Performing work outside of the project scope
66
Site Maintenance plan
holistic document taking current and future needs into account for a site. Addresses a variety of resource issues like maintenance budget, energy and water use, and user needs.
67
Submittals
written or physical information provided by a responsible contractor submitted to the owner or architect
68
Umbrella Excess Liability Insurance
Picks up coverage at the limit of a basic liability policy. Uses liability policy maximum coverage as deductible amount.
69
Contingent Liability
an injured third party is able to sue a responsible party regardless of any contracts responsible party may have with anyone else.
70
Construction closeout
primary purpose is to ensure the quality of the fully completed project