Self Study Cards Flashcards
Cards created by reading the Rita Mulcahy 9th Edition PMP Exam Prep book. (290 cards)
When are contingency reserves for schedule allocated?
For remaining identified risks after the plan risk responses process.
When should team building begin in the life of the project?
It should begin early on.
Forward pass path convergence must use which early finish value to calculate the float?
The later of them
I just completed a JAD Session, where am I?
Collect Requirements
What is 2 Sigma?
95.46%
What is the Triangular Distribution formula?
(P + M + O)/3
A PMO that provides policies, methodologies, templates, best practice training, and lessons learned from other projects is what type of PMO?
Supportive
What type of breakdown structure can be used to assign work packages to divisions or departments in the organization?
An Organizational Breakdown Structure
When is risk data quality assessment done?
During perform qualitative risk analysis.
Ambiuity (lack of understanding) and Variability (inability to predict changes) are categories of, what?
Non-event risks
Define the schedule compression technique fast tracking.
A technique used to compress a schedule where activities done in sequence are done in parallel.
The backward pass uses what duation value as the late finish of the last activity in the network?
Critical Path Duration
When, in quality, is root cause analysis used?
During the Manage Quality and Control Quality processes.
What creates a formal record of a project?
The Project Charger
What is the conflict resolution technique does not result in a permanent or complete resolution of a conflict?
Smoothing or accomodating.
Which type of organization is best for managing complex projects?
Matrix (Cross-disciplinary means the project covers more than one department or technical area of expertise. In such a case, a matrix organization is needed, with representatives from each department or discipline)
(Exam remembering) What is manage quality?
Are we following the policies as planned?
Name the categories of non-event risks.
Ambiuity (lack of understanding); and
Variability (inability to predict changes)
In terms of manage communications, what is an Earned Value Report?
A report that integrates scope, cost, and schedule measurements to assess project performance.
Legal restrictions is what kind of Enterprise Environmental Factor?
External
In a RACI, how many people or resources can be marked “A” (accountable)?
Only one; this helps avoid confusion about who is ultimately in charge or has authority for the work.
When does a Project Manager use/look at a work performance report?
The work performance report should be used when information is needed to make decisions, raise issues, initiate actions or gain awareness of the project status.
What are risk audits?
Assessments of the overall process of risk management on the project.
What are risk triggers?
Early warning signs that a risk event has occurred, or is about to occur. They letrisk owners know when to take action.



