Stages of a project Flashcards

(46 cards)

1
Q

The Architect proposes a fee for their services to the Client

A

Pre-Design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

The contractor proposes a cost or contract sum to the client to carry out
the contract works

A

Procurement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The contractor completes agreed deferred works and minor errors

A

DLP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Tenders are evaluated by the Architect

A

Procurement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A topographical survey is undertaken by a registered land surveyor

A

Pre-design (1 mark )
OR
Concept & Preliminary (1/2 mark)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The client takes over contract insurances from the contractor for a new
building

A

Practical Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Construction documentation is finalised by the Architect for Building
Consent

A

Detailed Design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Liquidated Damages are first charged to the contractor where the project
has not been completed according to the agreed programme

A

Contract Admin & Observation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The specification is completed by the architect

A

Detailed Design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Consultants’ requirements are first incorporated into the design prior to
their full coordination

A

Concept &Preliminary Design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Retentions are partially released for the first time

A

Practical Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The Architect considers the contract prices submitted by the contractors

A

Procurement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Variation Price Requests are costed

A

Contract Administration & Observation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The Client agrees the Architect’s proposed fee

A

Pre-design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The architect assists the client to expand and clarify the initial outline
brief

A

Concept and Preliminary Design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

The specification is completed by the consultant team

A

Detailed design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The ‘Contractor’s Performance Bond’ is released

A

At Practical Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

A Schedule of payment is prepared by either the Architect or the Quantitiy Surveyor

A

Contract Administration & Observation
OR
Pre-design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Door Schedules are produced and double checked

A

Detailed design

19
Q

The latest stage that a Resource Consent application should be made for a project that is not a Permitted Activity under the Auckland Unitary
Plan, so that the Client’s risk and expenditure is kept to a minimum

A

Developed design
OR
Concept design

20
Q

Consultants required for the project are identified for the project

A

Concept and preliminary design

21
Q

Minor defects are remedied to the satisfaction of the Architect

22
Q

the Architect first considers the approximate amount of documentation that might be required for a project

23
Q

An indicative cost for the project is prepared by the Quantity Surveyor to see if the project is viable with respect to costs and brief requirements

A

Concept and preliminary design
OR
Start of developed design

24
The ‘Principal’s Bond’ is released
At the Final account settlement
25
Variation Price Requests, if required, are issued and costed
Contract Administration & Observation
26
The Architect evaluates the tender prices received
Procurement
27
The specification is produced and double checked
Detailed Design
28
The Principal takes over the contract works insurance in a new build project
Practical Completion
29
The Architect first considers and estimates the amount of documentation that will be required for the project
Pre-design
30
The Principal and Architect can identify any newly discovered defects that require fixing under the contract to the satisfaction of the Architect
DLP
31
The structural consultant’s requirements are coordinated with the mechanical services drawings to identify any significant clashes
Developed Design
32
Retentions are collected
Contract Administration and Observation
33
The Architect assists the Client in developing and expanding the initial outline brief
Concept and Preliminary Design
34
Final preparation and compilation of the construction documentation occur to enable contract prices to be obtained
Detailed Design
35
The Architect issues Notices to Tenderers
Procurement
36
The most useful time to identify and locate existing underground services locations
Concept and Preliminary Design
37
A ‘Variation’ to the contract is issued
Contract Administration and Observation
38
A geotechnical survey is instructed for establishing the nature of the land beneath the proposed building footprint
Concept & Preliminary Design
39
A ‘Bonus for Early Completion’ of the project is paid out
At Practical Completion or start of DLP
40
The last stage where the amount of contract works insurance required for the project can be established
Start of Procurement; end of Detailed Design
41
The Client presents their design brief to the Architect for the first time
Pre-design
42
The earliest stage that a Resource Consent application can be made to establish the likelihood of consent success for a project typology that is not a Permitted activity under the Auckland Unitary Plan and to minimise the Client’s financial input into a project that may not proceed
Concept & Preliminary Design
43
Minor defects are remedied to the satisfaction of the Architect
DLP
44
The Quantity Surveyor can establish a reasonably accurate and comprehensive cost plan for the proposed project, incorporating all of the Consultants’ design requirements to meet the Client’s brief
Detailed Design
45
The Contractor issues a ‘Progress Payment’ claim (1 mark)
Contract Administration and Observation