Standard Costing Flashcards

(17 cards)

1
Q

How do you calculate Sales Volume Variance?

A

(Actual Sales Units - Budgeted Sales Units) * Budgeted Sales Price

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How do you calculate Sales Price Variance?

A

(Actual Sales Price - Budgeted Sales Price) * Actual Units

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How do you calculate Sales Variance?

A

(Actual Sales - Budgeted Sales)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How do you calculate Direct Material Variance?

A

(Actual Direct Materials Cost - Budgeted Direct Materials Cost)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How do you calculate Direct Materials Price Variance?

A

(Budgeted Price - Actual Price) * Actual Total Quantity

Actual Quantity : Actual Units * Actual Kilos of Direct Materials

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How do you calculate Actual price?

A

Total Direct Materials Cost / Actual Quantity of Direct Materials

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How do you calculate Direct Materials Usage Variance?

A

(Standard Quantity per unit - Actual Quantity per unit) * Standard Price * Actual Units

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How do you calculate the Direct Labour Variance?

A

(Budgeted Direct Labour Cost - Actual Direct Labour Cost)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How do you calculate the Direct Labour Rate Variance?

A

(Standard Wage Rate - Actual Wage Rate) * Actual Total Hours

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How do you calculate Actual Hours?

A

Total Actual Cost / Actual Direct Labour Rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How do you calculate Labour Efficiency Variance?

A

(Standard Hours per unit - Actual Hours per unit) * Standard Rate * Actual Units

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How do you calculate Overhead Absorption Rate? [OAR]

A

Fixed Overheads / Basis [ex. labour hours]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How do you calculate the Fixed Overhead Expenditure Variance based on Direct Labour Hours?

A

(Budgeted Fixed Overheads - Actual Fixed Overheads]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How do you calculate the Fixed Overhead Volume Variance based on Direct Labour Hours?

A

(Budgeted Hours for Actual Output - Budgeted Hours for Budgeted Output) * OAR

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How do you calculate the Fixed Overhead Capacity Variance based on Direct Labour Hours?

A

(Actual Labour Hours Worked - Budgeted Labour Hours Worked) * OAR

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How do you calculate the Fixed Overhead Efficiency Variance based on Direct Labour Hours?

A

(Budgeted Hours for Actual Output - Actual Hours for Actual Output) * OAR

17
Q

How do you