1
Q

True or False:
A work center can take credit for a PMS check if 80% of the check can be completed?

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Who reviews, and approves via signature, the 13-week report?

A

DIVO, WCS, and LCPO

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The LOEP contains all of the following information except?

A

The periodicity code for each maintenance requirement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

True or False:
An OPNAV 4790/CK is used to report discrepancies/deficiencies in the PMS system?

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

If more than one piece of equipment will be maintained by an MRC, the location Block will read?

A

See Location Guide List Below

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Who is the functional manager of 3M on the ship?

A

3MC (3M System Coordinator)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

To request a replacement for a lost or damaged MRC that is classified, the WCS should fill out a?

A

OPNAV 4790/7B (Category A)
*PMS FBR Non-Technical

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

An MRC card with a SYSCOM MRC Control Number A7 4ABG N has a production (birth) date of?

A

October 2017

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Which of the following is NOT an example of an IEM MRC?

A

U-1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Equipment is placed in IEM Status I whenever?

A

The equipment will not be operated for 30 days or more, but is NOT scheduled for corrective maintenance or overhaul.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Which document provides instructions and references required for use in the 3M System?

A

OPNAVINST 4790.4 (series)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Which form is used to document installation of new equipment?

A

OPNAV form 4790/CK

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Equipment should be placed in IEM Status II when?

A

Is inactive for 30 days or more AND is scheduled for corrective maintenance, overhaul, or removal for safe storage/placement.
*Refers to equipment that is repaired off ship.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Danger and Caution Tagout Audits are conducted how often?

A

Weekly

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What does an “C” beside a MIP number on the LOEP mean?

A

A Change to the MIP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

In SKED or on the 13-week report, M-1(#R-1) signifies what?

A

Monthly one has Mandatory Related Maintenance of R-1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

The ships underway schedule can be viewed on which of the following tabs in SKED 3.2?

A

Events tab

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

How many weeks are in a quarter?

A

13 mostly, but sometimes 14

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

A semi-annual MR can be scheduled at what interval?

A

4-8 months

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

An annual MR can be scheduled at what interval?

A

3-5 Quarters

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

When a maintenance action cannot be fully accomplished, what must be submitted with your weekly 3M report, reflecting the non-accomplished maintenance?

A

A check note

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

The acronym PAR stands for what?

A

Periodic Accomplishment Rating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

In SKED 3.2, hat will happen when attempting to mark a check complete, if no MP is assigned?

A

A pop-up window will appear, forcing you to assign at least one crew member, prior to marking the check complete.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

SNAP II was replaced by?

A

OMMS-NG

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
When using HAZMAT, information on proper PPE can be found where?
Both A and C *MSDS/SDS and HMUG
26
In OMMS-NG, a JSN is created by?
Opening a work candidate
27
When entering a 2K in OMMS-NG, what minimum information is required?
All items with a red check by them
28
True or False: As a WCS, you can share your OMMS-NG access with someone else without giving them your LAN password?
True
29
In OMMS-NG, a job priority of Highly Desirable will require what category CASREP?
Cat 2
30
In OMMS-NG, a job priority of Essential will require what category CASREP?
Cat 3
31
In OMMS-NG, a job priority of Mandatory will require what CASREP?
Cat 4
32
When submitting a 2K in OMMS-NG that is assigned a priority of Highly Desirable, Essential, or Mandatory, where should the CASREP DTG and Serial be documented?
On the MISC tab
33
What will happen to regularly scheduled maintenance, when equipment is in IEM?
It will not appear on the boards, only PM checks will show up, if applicable.
34
An Advance Change Notice (ACN) would be received when?
Whenever a change has been implemented to an existing maintenance requirement.
35
Who is the Authorizing Officer for an equipment tagout for Engineering while underway?
COW *Chief of the Watch
36
What symbol indicates mandatory maintenance is required and must be accomplished concurrently?
#
37
What does the acronym IEM stand for?
Inactive Equipment Maintenance
38
True or False: In the “Procedure” block, WCS may line out the non-applicable line items (Alternate procedures) that do no pertain to current equipment/configuration when the step is followed with the words “if applicable” or a Note identifying steps to be omitted?
True
39
PMS schedules are produced using what computer program?
SKED 3.2
40
What should be done (if anything) before the WCS, LCPO, and DIVO sign the completed 13-week report (accountability log)?
Log in to SKED, verify that the correct maintenance was done and checked off by the person signing, and that it is marked complete in SKED the same day that it was signed for.
41
True or False: The Department Head signature on Quarterly and Cycle boards has been replaced in SKED 3.2 with an electronic approval process for revisions.
True
42
Submitting a 4790/CK for a newly installed piece of equipment will initiate support to include?
-PMS, Tech Manuals, COSAL **All of the above
43
Shipboard divisions may have E7 and senior who are responsible for multiple Work Centers. These CPOs are designated by the CO as?
Group Supervisors
44
While reviewing your PMS schedule in SKED 3.2, you notice that the line item is highlighted in yellow. What does this signify?
The MR is nearing the end of its maximum range (within a week)
45
True or False: Maintaining a Work Center RPPO log is optional?
False
46
What is the maximum periodicity of a 2W MRC?
2 weeks
47
What is the maximum periodicity of a 3W MRC?
3 weeks
48
What is the maximum of a weekly (W) MRC?
Every week
49
What does the word CASEEP mean?
Casualty Report
50
How many types of CASREPs are there?
4
51
What type of CASREP report is submitted when a system has been restored to full operational status?
Correct
52
When ordering using an Open Purchase request, what is the maximum dollar amount allowed for one request?
$10k
53
Who is the final approving authority, by signature, for the RIP chit?
CO
54
What would be an example of a Consumable Item that is to be ordered using the “Non-Maint Supplies” menu in OMMS?
Hand tools
55
What must you bring when you are trying to order a DLR?
DLR (or RIP chit), RPPO log, 2K
56
If you turn-in a Circuit Card assembly or a Power Supply, what additional report must be provided to Supply?
2MTR
57
Who is responsible for providing the quote for open purchase requests?
-the divisions RPPO; the request originator **Either A or C
58
What is a 5-digit code used to identify the manufacturer of a part?
CAGE code
59
What publication is the MILSTRIP/MILSTRAP desktop guide?
NAVSUP P-409
60
An “URGENT” TFBR leaves the ship….?
By message
61
What are the 3 general purpose APL’s?
X-SYSTEMITEM, X-SERVICEITM, X-COMPARTMNT
62
What Command is used to finalize a deferral, completed, or change work candidate?
Apply
63
True or False: The intent of the PMS Spot Check program if for Quality Assurance of equipment and 3M training of PMS procedures and documentation.
True
64
What is used today in place of an OPNAV 4790/2K?
Work candidate
65
What color ink will be used on the Quarterly schedule to indicate lay-up maintenance?
Green
66
Under “Lead/Assist” tab in OMMS, what work center would be selected to respond to potable water trouble calls?
EA02 (Steam & Heat shop)
67
What are the 5 common tool bar functions in OMMS-NG window?
Exit New Open Print server New list
68
True or False: Login and password are required to access OMMS-NG?
False
69
An MRC with a periodicity code of “2W-12” is required to be completed?
Every 2 weeks
70
What Assist work center would you select to defer maintenance for repairs on a Departmental Wooden Picture board?
ER02 (Carpentry Shop)
71
What type of citation warrants the submission of an “Urgent” feedback report?
When the subject matter involves a Safety Hazard
72
Your work candidate requires assistance to complete the task other than the OWC. What tab would the user select to assign an assist work center?
MA Planning
73
True or False: 3M weekly reports are due to the 3M office by 1130 on Tuesday.
True
74
True or False: Requests for work package additions can be done using the ships OMMS-NG maintenance module (i.e. MA Planning)
True
75
The purpose of internal work processing is to….?
Provide all functions necessary for documenting deficiencies noted and repaired onboard the ship
76
The computer SERVER providing support for functions specifically related to Supply and Financial Management is?
R Supply
77
Reviewing MRC’s and promptly submitting PMS feedback reports is the responsibility of the?
WCS
78
How often is an equipment validation conducted IAW LINCOLNINST 3120.1D?
Weekly
79
Which of the following is used to verify an MRC?
MRC to MIP, MIP to LOEP, LOEP to Record of Change Page (also called FR)
80
A blue flag on a master tagout line item indicates the tagout?
Is authorized to be removed
81
The JSN is 4-digit number used to?
Identify the WC submitting a maintenance action. Report parts/material that are not on hand. Reports uncorrected deficiencies reported by INSURV. **All of the above
82
What does EIC mean?
Equipment Identification Code
83
In the OMMS-NG system, printed CSMP summary reports are a function of the?
Reports Tool Bar Option
84
How long are quarterly close-outs kept on file and by whom?
1 year; Dept 3MA