System Restoration Flashcards
(19 cards)
Dynamic Reserves
- 50% OR less allowed to be LOAD SHED.
- MUST be sufficient to support frequency deviations due to loss of largest contingency.
- Load pickup factors: max load generation can take without frequency decline:
a. 5% fossil
b. 15% hydro
c. 25% combustion turbines
Synch/Spinning
- Load shed counts as synch reserves ONLY during restoration.
Frequency:
a. 59.75HZ - 61HZ
b. Regulation to maintain frequency is 2% of area Load.
c. Shedding approximately 6% of load to raise frequency 1HZ.
Priorities during restoration
a. Cranking power to hot units that can be RTS
b. providing AUX to nuclear plants
c. Critical loads
d. Non-critical loads
e. Communications between GO and TSO
Voltage control
Capacitors:
a. generates VARS
b. removed from service until approx. 40% load has been re-energized.
Reactors:
a. Reduces system voltages.
b. Absorbs VARS.
Goal is to maintain approx. 90% to 105%
Manual Control
a. When there is insufficient data for automatic control
b. PJM replaces frequency control
Flat frequency control
a. Initiated when ACE signal is developed using frequency value in interconnected area.
b. used when PJM BA is islanding, or isolated from eastern interconnection.
c. frequency bias is 1% of interconnected area’s load
Flat Frequency Control utilizes only power system frequency
as the controlling parameter. This mode of control only responds to frequency deviations
and does not adjust operations for any interconnection tie line schedule deviations. This
mode is applicable only to those instances when the PJM Balancing Authority Area
becomes isolated from the Eastern Interconnection.
Tie Line bias control
a. Develops ACE signal when tie lines in service
b. Normal control mode.
Black Start Units
a. TOs manage and deploy black start units.
b. TO review annual restoration plan.
c. TOs have authority/responsibility for restoration
d. 2 black starts per TO zone
General Guidelines
approx. 1.7MVAR/Mile on 500 KILOVOLT lines
600 MW connected at 230 Kilovolt lines / higher
Level one cross zonal coordination
- black start unit supplies outside zone
- eliminates black start shortage in a given zone
Level two cross zonal coordination
- Single black start serving load pockets in multiple TO Zones
- example: 1 BS unit supplies its own geographical zone and another.
Level three cross zonal coordination
a. combines multiple TO restoration plans into a newly defined region.
b. Example: Merging 2 or more TO zones or create a new larger region with 1 plan
Black Start Criteria & Requirements
a. 110% critical load requirement
b. 2 black start units per zone redundancy
c. maintain fuel for 16 hour routine
d. less than 3 hour start time (breaker close to dead bus)
e. Equipment tested manually
Flat tie line control
Flat tie Line Control utilizes only interconnection tie line flow as
the controlling parameter. This mode of control only responds to net tie flow deviations
and does not adjust operation for any frequency deviations. This mode is limited to
special circumstances when the PJM Balancing Authority desires to maintain a given
net interchange flow, and the power system frequency is stable and being controlled by
other Balancing Areas