Systems 3 Tech Specs Flashcards

(38 cards)

1
Q

Tech Spec 3.7.9 SSI Requirements

A

→maintain max expected inlet temp ≤102°F
→level maintained ≥770’, restore within 7 days or shutdown (required level based on 30 days for accident unit and safe shutdown of other unit)
→if SSI inoperable for reasons other than level (e.g. temp >102° or dam degraded), be in mode 3 in 6 hrs, mode 5 in 36 hrs

Modes 1-4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

TR 13.7.33 SSI Sediment

A

→average sediment depth shall be ≤1.5 ft; if not, take immediate action to reduce sediment level
→dam shall have no abnormal degradation or erosion; if not, immediately enter TS 3.7.9 for SSI inop

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Tech Spec 3.7.8 Station Service Water System (SSWS)

A

Two trains and an SSW Pump on the opposite unit with its associated cross-connects shall be operable (Modes 1-4).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

TR 13.7.34 Flood Protection

A

→flood protection shall be provided for all safety-related systems, components, and structures when SCR exceeds 777.5 ft
→applicable at all times
→initiate action to be in lower mode in 1 hr, mode 3 in 7 hrs (only applies if flood protection not in place)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Tech Spec 3.7.7 CCW Operability

A

Both trains of CCW must be operable in Modes 1-4
→one train inoperable: restore within 72 hrs (or RICT)
→can’t restore: mode 3 in 6 hrs, mode 5 in 36 hrs

Note: if any RHR train is made inoperable by CCW inoperability, must enter LCO 3.4.6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

RWST Tech Spec Requirements

A

Modes 1-4
→Temp: 40°F to 120°F, fix within 8 hrs
→Boron: 2400-2600 ppm, fix within 8 hrs
→Level: 473,731 ( >95% per TS Bases), fix within 1 hour

Note: If low temp alarm comes in (≈45°), recirc through containment spray pumps to warm it up.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Tech Spec 3.5.2 ECCS - Operating

A

Two trains shall be operable in MODES 1‐3
→exception allowed to isolate both SI flowpaths for 2 hours for valve testing in MODE 3

When coming up to NOP/NOT from shutdown:
→both SI pumps required to be inoperable below 350°F for LTOP
→therefore, SI pumps must be inoperable while changing from Mode 4 to Mode 3
→allowed for 4 hours OR before RCS temp >375°F, whichever comes first
→one train of CCP inop - 7 days to restore
→one or more train inoperable other than CCP but you can still guarantee 100% ECCS flow - 72 hours

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Tech Spec 3.5.3 ECCS - Shutdown

A

One ECCS train shall be operable in MODE 4
→an RHR train in SDC can be considered operable for this spec
→assumes train can be realigned to the injection flowpath
→concerned with RHR suction temperature and voiding when realigned to the RWST
→cannot consider RHR in shutdown cooling for this spec when temperature is >200F
→SIPs are not required in this spec due to requirements of LTOP
→one train RHR inop - immediately take action to restore to operable
→one CCP OOS - restore within 1 hour

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Tech Spec 3.5.5 Seal Injection Flow

A

Seal injection flow shall be <40gpm when RCS pressure is between 2215 psig and 2255 psig
→applicable in Modes 1‐3
→restore in 4 hours or shutdown
→concerned with adequate ECCS flow on an SI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

TR 13.1.31 Boration Injection Systems - Operating

A

Two flowpaths required operable in Modes 1‐4
→required to be manually aligned in 15 minutes
→administratively controlled if field actions required for alignment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

TS 3.6.7 Chem Add Tank requirements

A

→NaOH concentration must be between 28% - 30% by weight
→Level must be maintained 91% - 94%.
→1-4 psig N2 overpressure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

TS 3.6.6 CS System MODE requirements

A

2 trains required in modes 1 - 4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

TS 3.5.4 RWST

A

→Boron 2400-2600 ppm (restore in 8 hrs)
→Level > 95% or 473,731 gallons (restore in 1 hr)
→Temp 40 -120˚F (restore in 8 hrs; if too cold, heat by recirc through CSPs)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

TS 3.9.5 RHR High Water Level (Mode 6)

A

One RHR loop shall be OPERABLE and in operation in MODE 6 with the water level ≥ 23 feet above the top of the reactor vessel.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

TS 3.9.6 RHR Low Water Level (Mode 6)

A

Two RHR loops shall be OPERABLE and one RHR loop shall be in operation in MODE 6 with the water level < 23 feet above the top of the reactor vessel flange

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Tech Specs

3.4.6 RCS Loops - Mode 4
3.4.7 RCS Loops - Mode 5, Loops Filled
3.4.8 RCS Loops - Mode 5, Loops Not Filled

17
Q

Tech Spec 3.4.12 requirements for LTOP

A

→2 RHR suction reliefs (lift @ 450 psig ± 3%), or
→2 PORVs, or
→1 of each
→0 SI pumps capable of injecting
→2 charging pumps capable of injecting
→0 accumulators capable of injecting

If these requirements are not met, then the RCS must be depressurized and a 2.98 sq in vent path must be made in the RCS pressure boundary.

18
Q

Per Tech Spec 3.4.12, LTOP applies Mode 4, 5, and 6 (when RV head on), but does not apply when all RCS CL temperatures > 320°F and all of the following are met:

A
  1. at least 1 RCP operating
  2. PZR level ≤ 92%
  3. Plant heatup rate is limited to 60°F per hour

Note: LTOP will still arm ≤350°F

19
Q

Tech Spec 3.5.2 ECCS - Operating

A

Two ECCS trains shall be operable (Modes 1-3)
→ECCS trains are CCPs, SIPs, RHRPs and piping
→SI Accumulators and RWST not considered part of the LCO
→all ECCS subsystems credited for LOCA

Note: operation in Mode 3 with ECCS pumps made incapable of injecting per LTOP (LCO 3.4.12) is allowed for up to 4 hrs or until temp of all 4 cold legs >375° F, whichever comes first.

20
Q

Tech Spec 3.5.3 ECCS - Shutdown

A

One ECCS train shall be operable (Mode 4)
→an operable train is CCP and RHR (doesn’t include SIP) capable of taking suction from RWST and swapping to sump
→an RHR train is operable when aligned for shutdown cooling if capable of being manually realigned to ECCS
→if RHR subsystem inoperable, take action to restore immediately
→if CCP subsystem inoperable, restore within 1 hr

21
Q

TS LCO 3.7.20, UPS HVAC System

A

Two UPS HVAC System Trains shall be OPERABLE (Modes 1-4)
1 hour or less, actions

LCO 3.7.20.A one UPS HVAC System train inoperable

→A.1: Verify the affected UPS & Distribution Room is supported by an OPERABLE UPS A/C Train immediately AND
→A.2: Restore the inoperable UPS HVAC train to OPERABLE status within 30 days

22
Q

TR 13.7.36 “Area Temperature Monitoring”

A

One or more areas exceeds the normal temperature for more than 8 hours then restore according to CAP and complete analysis immediately.

23
Q

13.7.37 - Safety Chilled Water System

A

Electrical Switchgear Area Emergency Fan Coil Units shall be OPERABLE in MODES 1-4. If one or more is inoperable, the LCO allows you to either:

  1. Declare Safety Chilled Water train(s) inoperable and enter TS LCO 3.7.19 (Immediately), or
  2. Declare affected fan coil unit(s) and their support equipment inoperable (Immediately)
24
Q

Tech Spec 3.7.19

A

Two safety chilled water trains shall be operable in Modes 1-4

→one train inoperable, restore within 72 hrs or RICT; if not, Mode 3 in 6 hrs, Mode 5 in 36 hrs

→two trains inoperable, LCO 3.0.3 immediately

25
Tech Spec 3.1.4 Rod Group Alignment Limits
Modes 1 and 2 All shutdown and control rods shall be OPERABLE AND Individual indicated rod positions shall be within 12 steps of their group step counter demand position. Note: the operability (i.e. trippability) of the shutdown and control rods is an initial assumption in all safety analyses that assume rod insertion upon reactor trip. One or More Rods Inoperable: →verify SDM within COLR limits within 1 hr OR →initiate boration to restore SDM within 1 hr AND →Mode 3 in 6 hrs One Rod Not Within Alignment Limits: →verify SDM within COLR limits within 1 hr OR →initiate boration to restore SDM within 1 hr AND →reduce thermal power to ≤75% RTP within 2 hrs More Than One Rod Not Within Alignment Limits: →verify SDM within COLR limits within 1 hr OR →initiate boration to restore SDM within 1 hr AND →Mode 3 in 6 hrs
26
Tech Spec 3.1.5 Shutdown Bank Insertion Limits
Each shutdown bank shall be within insertion limits specified in the COLR (Modes 1 and 2 with any control bank not fully inserted) . Each shutdown bank shall be within 218 and 231 steps withdrawn in MODE 1, and in MODE 2 with any control bank not fully withdrawn. This LCO is not applicable during the performance of OPT-106A/B (SR 3.1.4.2) One or More Shutdown Banks Not Within Limits: →verify SDM within COLR limits within 1 hr OR →initiate boration to restore SDM within 1 hr AND →restore shutdown banks to within limits within 2 hrs
27
Tech Spec 3.1.6 Control Bank Insertion Limits
Control banks shall be within the insertion, sequence, and overlap limits specified in the COLR (Modes 1 and 2 with keff ≥1.0). This LCO is not applicable while performing SR 3.1.4.2
28
TR 13.1.37 Rod Group Alignment Limits and Rod Position Indicator
The Rod Position Deviation Monitor (u-ALB-6D/3.5, DRPI ROD DEV alarm and inputs) shall be operable in Modes 1 and 2. If the DRPI ROD DEV alarm becomes inoperable, rod group alignment, and the operability of the Demand Position Indication System and the DRPI System must be verified every 4 hours. Applicable conditions of LCOs 3.1.4, Rod Group Alignment Limits, and 3.1.7, Rod Position Indication, shall be immediately entered upon discovery of one or more rod position indications inoperable.
29
TR 13.1.38 Control Bank Insertion Limits
The Control Bank Insertion Limit Monitor shall be operable in Mode 1 and in Mode 2 with the reactor critical. The Control Bank Insertion Limit Monitor inputs annunciators u-ALB-6D/1.7, ANY CONTROL BANK AT LO LMT, and u-ALB-6D/2.7, ANY CONTROL BANK AT LO-LO LMT, and CONTROL ROD INSERTION LIMIT & POSITION recorders u-ZR-0412 & 0412A. If these indications become inoperable, the position of each control bank must be verified to be within the limits of the COLR every 4 hours. Applicable conditions of LCO 3.1.6, Control Bank Insertion Limits shall be immediately entered upon discovery of control bank insertion limits not met.
30
ODCM Section 3.3.3.5 - Radioactive Gaseous Effluent Control
→specifies requirements for Radioactive Gaseous Effluent Monitoring I & C →WRGM flow rate and sample points →if WRGM is OOS, flow rate is estimated every 4 hrs OR sample every 24 hrs, depending on which aspect of WRGM is OOS
31
Tech Spec 5.5.4 Administrative Requirement for Control of Radioactive Effluents
→ALARA to the public →monitor releases
32
Tech Spec 3.3.2 ESF Instrumentation
→containment pressure instruments operable →Modes 1-3 →trip or bypass in 72 hrs or Mode 3 in 78 hrs, Mode 4 in 84 hrs
33
Tech Spec 3.3.3 PAM Instrumentation
→Modes 1-3 →PAM instruments must be operable
34
Tech Spec 3.3.1 & 3.9.3 Source Range:
→Source Range Instrumentation is required in Mode 2 (below P6) through Mode 6 →in Mode 6, only visual count rate indication is required in the Control Room →in Mode 3-5 the T.S. only applies if the Rod Control System is capable of withdrawal and one or more rods not fully inserted.
35
Tech Spec 3.3.1 Intermediate Range:
The Intermediate Range Instrumentation is required in Mode 1 (below P-10) and Mode 2 (above P-6) 1 IR Channel inoperable, Mode 1 (P-6): →reduce THERMAL POWER to P-10 in 24 hours →Mode 2 (P-6): →suspend operations involving positive reactivity additions immediately, and →reduce power to
36
Tech Spec 3.3.1 Power Range:
2 PR Channels Inoperable, enter LCO 3.0.3
37
Tech Spec 3.2.4 Quadrant Power Tilt Ratio (QPTR)
→action required once ≥1.02 →applicable in Mode 1, >50% →For each 1% QPTR above 1.00, reduce power 3% →verify QPTR every 12 hrs →perform evaluation to allow continued operation →if completion time not met, reduce power to <50% Note: this one is tricky. Action isn't required until 1.02, but you must take the action based on the amount above 1.00
38
Tech Spec 3.2.3 Axial Flux Difference
→applicable in Mode 1 >50% →Spec not met when **two or more** PR NIs indicate out of spec →30 minutes to be <50% - no time for correction Background Info: →AFD = ΔI →inside the doghouse = acceptable; outside the doghouse = unacceptable "Half power, half an hour"