Systems 3 Tech Specs Flashcards
(38 cards)
Tech Spec 3.7.9 SSI Requirements
→maintain max expected inlet temp ≤102°F
→level maintained ≥770’, restore within 7 days or shutdown (required level based on 30 days for accident unit and safe shutdown of other unit)
→if SSI inoperable for reasons other than level (e.g. temp >102° or dam degraded), be in mode 3 in 6 hrs, mode 5 in 36 hrs
Modes 1-4
TR 13.7.33 SSI Sediment
→average sediment depth shall be ≤1.5 ft; if not, take immediate action to reduce sediment level
→dam shall have no abnormal degradation or erosion; if not, immediately enter TS 3.7.9 for SSI inop
Tech Spec 3.7.8 Station Service Water System (SSWS)
Two trains and an SSW Pump on the opposite unit with its associated cross-connects shall be operable (Modes 1-4).
TR 13.7.34 Flood Protection
→flood protection shall be provided for all safety-related systems, components, and structures when SCR exceeds 777.5 ft
→applicable at all times
→initiate action to be in lower mode in 1 hr, mode 3 in 7 hrs (only applies if flood protection not in place)
Tech Spec 3.7.7 CCW Operability
Both trains of CCW must be operable in Modes 1-4
→one train inoperable: restore within 72 hrs (or RICT)
→can’t restore: mode 3 in 6 hrs, mode 5 in 36 hrs
Note: if any RHR train is made inoperable by CCW inoperability, must enter LCO 3.4.6
RWST Tech Spec Requirements
Modes 1-4
→Temp: 40°F to 120°F, fix within 8 hrs
→Boron: 2400-2600 ppm, fix within 8 hrs
→Level: 473,731 ( >95% per TS Bases), fix within 1 hour
Note: If low temp alarm comes in (≈45°), recirc through containment spray pumps to warm it up.
Tech Spec 3.5.2 ECCS - Operating
Two trains shall be operable in MODES 1‐3
→exception allowed to isolate both SI flowpaths for 2 hours for valve testing in MODE 3
When coming up to NOP/NOT from shutdown:
→both SI pumps required to be inoperable below 350°F for LTOP
→therefore, SI pumps must be inoperable while changing from Mode 4 to Mode 3
→allowed for 4 hours OR before RCS temp >375°F, whichever comes first
→one train of CCP inop - 7 days to restore
→one or more train inoperable other than CCP but you can still guarantee 100% ECCS flow - 72 hours
Tech Spec 3.5.3 ECCS - Shutdown
One ECCS train shall be operable in MODE 4
→an RHR train in SDC can be considered operable for this spec
→assumes train can be realigned to the injection flowpath
→concerned with RHR suction temperature and voiding when realigned to the RWST
→cannot consider RHR in shutdown cooling for this spec when temperature is >200F
→SIPs are not required in this spec due to requirements of LTOP
→one train RHR inop - immediately take action to restore to operable
→one CCP OOS - restore within 1 hour
Tech Spec 3.5.5 Seal Injection Flow
Seal injection flow shall be <40gpm when RCS pressure is between 2215 psig and 2255 psig
→applicable in Modes 1‐3
→restore in 4 hours or shutdown
→concerned with adequate ECCS flow on an SI
TR 13.1.31 Boration Injection Systems - Operating
Two flowpaths required operable in Modes 1‐4
→required to be manually aligned in 15 minutes
→administratively controlled if field actions required for alignment
TS 3.6.7 Chem Add Tank requirements
→NaOH concentration must be between 28% - 30% by weight
→Level must be maintained 91% - 94%.
→1-4 psig N2 overpressure
TS 3.6.6 CS System MODE requirements
2 trains required in modes 1 - 4
TS 3.5.4 RWST
→Boron 2400-2600 ppm (restore in 8 hrs)
→Level > 95% or 473,731 gallons (restore in 1 hr)
→Temp 40 -120˚F (restore in 8 hrs; if too cold, heat by recirc through CSPs)
TS 3.9.5 RHR High Water Level (Mode 6)
One RHR loop shall be OPERABLE and in operation in MODE 6 with the water level ≥ 23 feet above the top of the reactor vessel.
TS 3.9.6 RHR Low Water Level (Mode 6)
Two RHR loops shall be OPERABLE and one RHR loop shall be in operation in MODE 6 with the water level < 23 feet above the top of the reactor vessel flange
Tech Specs
3.4.6 RCS Loops - Mode 4
3.4.7 RCS Loops - Mode 5, Loops Filled
3.4.8 RCS Loops - Mode 5, Loops Not Filled
Tech Spec 3.4.12 requirements for LTOP
→2 RHR suction reliefs (lift @ 450 psig ± 3%), or
→2 PORVs, or
→1 of each
→0 SI pumps capable of injecting
→2 charging pumps capable of injecting
→0 accumulators capable of injecting
If these requirements are not met, then the RCS must be depressurized and a 2.98 sq in vent path must be made in the RCS pressure boundary.
Per Tech Spec 3.4.12, LTOP applies Mode 4, 5, and 6 (when RV head on), but does not apply when all RCS CL temperatures > 320°F and all of the following are met:
- at least 1 RCP operating
- PZR level ≤ 92%
- Plant heatup rate is limited to 60°F per hour
Note: LTOP will still arm ≤350°F
Tech Spec 3.5.2 ECCS - Operating
Two ECCS trains shall be operable (Modes 1-3)
→ECCS trains are CCPs, SIPs, RHRPs and piping
→SI Accumulators and RWST not considered part of the LCO
→all ECCS subsystems credited for LOCA
Note: operation in Mode 3 with ECCS pumps made incapable of injecting per LTOP (LCO 3.4.12) is allowed for up to 4 hrs or until temp of all 4 cold legs >375° F, whichever comes first.
Tech Spec 3.5.3 ECCS - Shutdown
One ECCS train shall be operable (Mode 4)
→an operable train is CCP and RHR (doesn’t include SIP) capable of taking suction from RWST and swapping to sump
→an RHR train is operable when aligned for shutdown cooling if capable of being manually realigned to ECCS
→if RHR subsystem inoperable, take action to restore immediately
→if CCP subsystem inoperable, restore within 1 hr
TS LCO 3.7.20, UPS HVAC System
Two UPS HVAC System Trains shall be OPERABLE (Modes 1-4)
1 hour or less, actions
LCO 3.7.20.A one UPS HVAC System train inoperable
→A.1: Verify the affected UPS & Distribution Room is supported by an OPERABLE UPS A/C Train immediately AND
→A.2: Restore the inoperable UPS HVAC train to OPERABLE status within 30 days
TR 13.7.36 “Area Temperature Monitoring”
One or more areas exceeds the normal temperature for more than 8 hours then restore according to CAP and complete analysis immediately.
13.7.37 - Safety Chilled Water System
Electrical Switchgear Area Emergency Fan Coil Units shall be OPERABLE in MODES 1-4. If one or more is inoperable, the LCO allows you to either:
- Declare Safety Chilled Water train(s) inoperable and enter TS LCO 3.7.19 (Immediately), or
- Declare affected fan coil unit(s) and their support equipment inoperable (Immediately)
Tech Spec 3.7.19
Two safety chilled water trains shall be operable in Modes 1-4
→one train inoperable, restore within 72 hrs or RICT; if not, Mode 3 in 6 hrs, Mode 5 in 36 hrs
→two trains inoperable, LCO 3.0.3 immediately