Technical - Construction Technology and Environmental Services Flashcards
What are the RIBA stages?
Royal Institute of British Architects Plan of Work. Gateways to take a construction project from inception through to design, construction and handover.
0 – Strategic Definition
1 – Preparation and Briefing
2 – Concept Design
3 – Spatial Coordination
4 – Technical Design
5 – Manufacturing and Construction
6 – Handover
7 – Use
What is buildability?
The extent to which the design of the building facilitates the ease of constructing it.
What are the benefits of off-site construction over in-situ?
Modular products can be made, reducing waste.
Not hampered by the weather.
Speed – components built off site at the same time can be transported to site and erected at a faster pace.
What are temporary works?
Temporary works that facilitate the permanent works being completed, such as scaffold, propping, formwork, excavation support, access roads and temp lighting.
What are hoists?
Mechanisms that lift materials or people vertically.
What is substructure?
Lower portion of the building situated in the ground. Transmits the load of the building to the ground. Examples are foundations, retaining walls and basements.
What is ground heave?
Usually clay soil that swells when wet and forces the ground upward.
What techniques can be used to improve the ground?
Vibro compaction and vibro stone columns.
Vertical drains and vacuum consolidation.
Soil mixing.
Dynamic compaction or dynamic replacement.
Name some different forms of excavation.
Site clearance.
Stripping topsoil.
Reduced level dig.
Cut and fill.
Foundations.
What must be considered before excavating?
The soil type and ground moisture.
Method of excavation.
Whether ground support systems are required.
How close are neighbouring buildings.
Depth of excavations.
If there are any buried services or drainage.
How can you waterproof a sub-terranean area?
Tanking – waterproof material such as bitumen is applied to provide a continuous membrane down the walls and to the base.
Drained cavity – water enters but it trapped behind a waterproof cavity. The moisture then seeps to the floor and must be drained or pumped away.
What is SUDS?
Sustainable Urban Drainage Systems. Designed to manage surface water drainage and to mimic natural drainage. Stops the fast release of water into out capacitated sewer systems.
What is a typical road build up?
Compacted sub-base (250mm)
Base course (150mm)
Binder course (100mm)
Surface course (40mm)
What is a typical lime floor build up?
Geotextile
Foamed Glass Gravel
Clip rails for underfloor heating
Geogrid
Geotextile
Lime Screed
What is the purpose of foundations?
To spread the load of the building to the ground and bear the load of the superstructure.
What must be considered when selecting what foundations to use?
Ground/ soil conditions.
The total load of the building.
Type of structure.
Construction constraints.
Cost.
What are the different types of foundations?
Strip, Pad, Raft and Piled.
What is a raft foundation?
A continuous slab that extends over the entire footprint of the building. Spreads the load over a wider area than the other foundations so the stress on the ground below is reduced.
What are pad foundations?
Pads of concrete, or reinforced concrete, that support columns.
What are strip foundations?
Linear foundations usually used to support masonry.
What are pile foundations?
A column that is driven deep into the ground in areas where ground conditions are poor or the loads are very heavy.
Two types:
1. End bearing
2. Friction
Piles can either be bored or driven concrete.
When would a pile foundation be most suitable for a project?
When the structure is heavy and the ground is weak.
If there are settlement problems.
If the water table is high.
If the load distribution of the superstructure is not even.
If there are horizontal forces.
What are end bearing piles?
Bottom of the pile is driven down until it rests on a strong layer such as rock. The load then transfers through the pile and onto the rock.
What are friction piles?
Do not rest on a strong layer, instead there are shear stresses along the side of the pile that transfer the forces to the soil.