The Richter magnitude of the 1906 San Francisco earthquake is estimated to have 8.3. The 1989 “World Series” earthquake in San Francisco had a magnitude of 7.1 on the Richter scale. How much greater was the intensity of the 1906 earthquake than that of the 1989 earthquake?
A. 16 times
B. 12 times
C. 20 times
D. 14 times
A. 16 times
It is the process where a load is prepared for lifting using a lifting machine. The main part of this process is the tying up of the load with sling and other connecting devices so that the load could be hooked onto a crane.
A. Lifting
B. Rigging
C. Loading
D. Handling
B. Rigging
Complete or partial dismantling of a building or structure by pre-planned and controlled methods or procedures.
A. Demolition
B. Clearing
C. Breaking
D. Grubbing
A. Demolition
It is capable of spreading, consolidating, and finishing a concrete slab without the use of conventional forms.
A. dust palliative
B. fog seal
C. tack coat
D. slipform paver
D. slipform paver
It is a very versatile machine that has the longest reach for digging and dumping of any member of the crane shovel family.
A. dragline
B. crane
C. backhoe
D. excavator
A. dragline
The bucket volume contained within the bucket when following the outline of the bucket sides is called:
A. Struck capacity
B. Bucket capacity
C. Plate line capacity
D. Waterline capacity
C. Plate line capacity
The bucket assumes a level of material flush with the lowest edge of the bucket.
A. Struck capacity
B. Bucket capacity
C. Plate line capacity
D. Waterline capacity
D. Waterline capacity
The bucket capacity when the load is struck off flush with the bucket sides.
A. Struck capacity
B. Bucket capacity
C. Plate line capacity
D. Waterline capacity
A. Struck capacity
It represents those components of cycle time other than travel time.
A. Time
B. Stop time
C. Waiting time
D. Fixed time
D. Fixed time
This represents the travel time required for a unit to
haul material to the unloading site and return.
A. Different time
B. Travel time
C. Variable time
D. Changing time
C. Variable time
This should be done during the first seven days in order that the expected development of strength will be obtained and the occurrence of plastic cracks
will be prevented or minimized.
A. Testing
B. Curing
C. Sprinkling
D. Brooming
B. Curing
A mixture of cementitious materials and water, with or without aggregate, proportioned to produce a creamy consistency.
A. Filler
B. White cement
C. Primer
D. Grout
D. Grout
Joints placed in concrete pavements, which are usually placed transversely, at regular intervals, to provide adequate expansion space for the slab to expand when the pavement is subjected to an increase in temperature.
A. Hinge Joint
B. Contraction Joint
C. Construction Joint
D. Expansion Joint
D. Expansion Joint
Joints placed in concrete pavements, which are usually placed transversely regular intervals across the width of the pavement to release some of the tensile stresses that are due to a decrease in temperature.
A. Hinge Joint
B. Contraction Joint
C. Construction Joint
D. Expansion Joint
B. Contraction Joint
Joints placed in concrete pavements, which are usually placed transversely across the pavement width to provide suitable transition between concrete placed at different times or on different days.
A. Hinge Joint
B. Contraction Joint
C. Construction Joint
D. Expansion Joint
C. Construction Joint
Joints placed in concrete pavements at right angles to the center line of the
pavement is called:
A. Transverse Joint
B. Longitudinal Joint
C. Construction Joint
D. Expansion Joint
A. Transverse Joint
It is a type of thermoplastic lane marking designed to aid and provide motorist with visual, audio, and warning on the road.
A. Chevron markings
B. Painted median
C. Rumble strips
D. Diagonal markings
C. Rumble strips
Which of the following is NOT an objective for traffic barriers?
A. Increasing capacity
B. Separating opposing flow
C. Channeling various modes of traffic flow
D. Work zone safety
A. Increasing capacity
Which of the following duties normally NOT be a responsibility of the estimating department within a general contractor’s organization?
A. obtaining bid documents
B. securing subcontractor/material quotations
C. project cost accounting
D. delivering competitive or negotiated proposals
C. project cost accounting
In competitive bidding, when the bids are all opened, the owner will normally award the contract to the lowest _______.
A. available bidder
B. qualified bidder
C. responsible bidder
D. bonded bidder
C. responsible bidder
What is the accepted normal limit of peripheral vision?
A. 45°
B. 80°
C. 160°
D. 180°
C. 160°
According to NSCP, the slope of cut surfaces shall be no steeper than:
A. 1H:1V
B. 1.5H:1V
C. 2H:1V
D. 3H:1V
C. 2H:1V
According to NSCP, the slope of fill surfaces shall be no steeper than:
A. 1H:1V
B. 1.5H:1V
C. 2H:1V
D. 3H:1V
C. 2H:1V
Any temporary elevated platform used for supporting employees or materials or both in the course of any construction works
A. Formworks
B. Scaffold
C. Framing
D. Bracing