Test Questions Flashcards
- A reason for having all normal power (non-emergency) branch circuits fed from a single distribution panel, at a particular patient bed location, it to minimize.
A. the occurrence of electrical fires.
B possible micro-shock to a patient
C. the number of outlets at the bedside
D. possible potential difference between outlet grounds
D. This requirement (NFPA 99-2005 paragraph 4.3.2.2.1.1) minimizes the difference in potential (voltage) between grounds on the normal branch circuits. If differenced in potential are substantial. There can be adverse effects on connected medical equipment. It also is easier to trace the circuits back toa single distribution panel rather than to multiple panels, which can be important when emergency conditions might require rapid restoration of power.
2. According to Guidelines for Design and Construction of Health Care Facilities (2010 edition), Which of the following medical gas systems are required in a typical medical/surgical patient room? A. vacuum and oxygen B. medical air and oxygen C. vacuum and medical air D. nitrous oxide and oxygen
A. This is the correct answer based on the Guidelines for Design and Construction of Health Care Facilities
- A piece of equipment must be delivered immediately for installation. It does not fit into the original logistics plan for primary product delivery. The only logical delivery site is next to the main entry where there is adequate area for the delivery vehicle. Which of the following modifications to the logistics plan needs to me implemented?
A. Notify the fire department
B. Schedule delivery for an off-hours installation
C. Coordinate with hospital security to maintain access
D. Require the driver to relocate and deliver to another location
C. Parking a large vehicle at the main entrance may obstruct patient and visitor access, requiring assistance in directing traffic and pedestrians during the delivery period.
- The owner of an outpatient diagnostic center is planning an expansion and considers adding several new imagining modalities. The owner asks for the construction manager’s input on when the medical imagining equipment selections should be made. Which of the following is construction manager’s BEST response?
A. Modalities and manufacturer of equipment can be decided at any point, as long as it is before the concrete foundations are poured.
B. the modalities should be determined before the end of Schematic Design and equipment manufactures considered for each modality should be arranged prior to completion of Design Development.
C. The MRI and CT scanner manufacturer and model need to be selected at Schematic Design, but the catherization lab equipment can be selected at any time prior to start of construction.
D. All of the medical imagining equipment decision should be made prior to starting Schematic design in order to properly size the rooms.
B. This response allows the design team to accommodate all the anticipated final equipment features into the project. A decision on a specific model can be made later, often well into the construction process depending on the structure and location of equipment.
5. A new hospital is being developed on a steep sloping site. Several level will have doors existing to grade from different levels of the building. Perimeter lengths of the building at each level are as follows. Level 8 all above ground Level 7 all above ground Level 6 5% of the perimeter is a grade Level 5 30% of the perimeter is a grade Level 4 20% of the perimeter is a grade Level 3 40% of the perimeter is a grade Level 2 5% of the perimeter is a grade Level 1 entirely below ground
According to NFPA 101-2000(Life Safety Code), which of the following levels of this building is the primary level of exit discharge?
A. Level 6 B. Level 5
C. Level 4 D. Level 3
C. Paragraphs 18.1.6.1 (for new buildings) and 19.1.6.1 (for existing buildings) of NFPA 101-2000 detail that “Primary level of exit discharge of a building shall be the lowest story whose floor is level with or above finished grade on the exterior wall for 50% or more of its perimeter.” In this case, there perimeter at grade for Level 4 and above is the sum of each of those levels. That is 5% at Level 6, 30% at Level 5, and 20% at Level 4 for a total of 55% at Level 4 or above. This is information may become important when deciding whether a new building will be considered a high rise building and there by requiring additional fire protection features under the code.
- Which of the following treatment areas requires lead as a shielding material?
A. Magnetic resonance imaging (MRI) suite
B. Electromyography (EMG) laboratory
C. Computerized tomography (CT) scanning suite
D. Ultrasound examination room
C. CT devices use ionizing radiation (x-ray) in their operation. Lead shielding blocks ionizing radiation and protects CT operators and other people in adjacent areas.
7. Which of the following departments of an acute care hospital must be staffed 24 hours a days, 7 days a week? A. Surgery B. Pharmacy C. Emergency D. Physical Therapy
C. Guidelines for the Design and Construction of Health Care Facilities (2010 edition) clause 2.2.3.1.1.1 define emergency services as the capacity to perform initial and definitive emergency care 24 hours a day , 7 days a week.
- During construction, it is likely that normal fire response plans will be inappropriate and staff will be required to use alternate evacuation routes and techniques. Which of the following BEST describes the Interim Life Safety Measures (ILSM) required?
A. Temporary exits should be designated and inspected daily, and at least two fire drills per quarter per shift should be performed.
B. Temporary exits should be designated and clearly marked, staff should be trained, and at least two fire drills per quarter per shift should be performed.
C. Have the local authority having jurisdiction approve temporary exits.
D. Provide additional firefighting equipment and train staff on usage.
B. This answer includes The Joint Commission requirements in the Life Safety Chapter at LS.01.02.01, EP2 regarding signage on temporary exits. Staff training and additional fire drills would also be appropriate in this situation.
- The electrical service to the medical air compressors must be shut down to relocate the electrical feed to a different distribution panel. Which of the following is MOST likely to be affected?
A. Critical care, NICU, HVAC controls, and surgery air-powered instruments
B. surgery air powered instruments, laboratory automated analyzer, physical therapy, and intensive cate
C. NICU, ability to calibrate respiratory therapy equipment, critical care, and coronary care.
D. HVAC controls, coronary care, ability to calibrate respiratory therapy equipment, and physical therapy
C. The Guidelines for the Design and Construction of Health Care Facilities (2010 edition) require medical air outlets be included in critical care, coronary critical cate, and newborn intensive care NICU). This information is contained in Table 2.1-6. NFPA 99 allows medical air to be used for the calibration of equipment used for respiration. According to NFPA 99-202 paragraph 5.1.3.5.2, medical air source shall be connected to the medical air distribution system only and shall be used only for air in the application of human respiration and calibration of medical devices for respirator application.
10. A radiology renovation project in an occupied hospital must be constructed in five phases. The department must remain in operation 8:00 am – 5:00 pm, M-Sat. Each phase of the renovation requires an 8-hour electrical shutdown in order to make the final electrical tie-in of the new panels. Electricians are paid $70/hr., $105/h. for time worked after 5:00pm and $140/hr. for weekend work. The BEST cost per electrician that can be achieved on the project is A. $1,600 B. $2,800 C. $4,200 D. $5,600
C. Phasing is commonly used to keep the radiology department in a position where they can continue to offer services, even though those services offering may be limited due to construction. The contractor will not be able to conduct the electrical system shutdown during the operating hours of the department, as it would render the department incapable of providing any service the work should be preformed off-hours. By performing the work in the evening and on weekends, the contractor will be required to pay electricians $105/hr., but can avoid the weekend rate. The BEST cost per electrician is:
(5 shutdowns) x (8 hours/shutdown) x ($105/hr.) = $4,200
- A hospital is building a new bed tower on its campus next to an existing facility, the new facility will eventually tie into the existing facility by a new bridge walkway connection. The project is separated from the exiting hospital until the final phase when the bridge will be added. When should the project manager request the Infection Control Risk Assessment (ICRA)?
A. It does not need to be provided since the project site is separated form the existing facility
B. It does not need to provided until they get ready to tie in the new bridge walkway.
C. It should be completed before any work begins on the project site.
D. It should be completed before any work begins with any hazardous demolition.
C. According to the Guidelines for Design and Construction of Health Care Facilities (2010 edition), clause 1.2-3.1.2 “ICRA shall be conducted during the early planning phase of a project, before construction begins, and continue through the project construction and commissioning.” Although there may be no need to implemented any mitigative measures at the stage, it is vital to plan the construction, identify the risks, and set a mitigative strategy in advance of any work. This often requires significant discussion between the contractor and the health care facility. The earlier the process starts, the smoother construction is likely to progress.
- A worker receives a cut to the wrist while removing demolition debris from a hospital renovation site. Which of the following is the MOST appropriate course of action?
A. Clean the wound site, apply and antibiotic ointment, and the cover with clean gauze.
B. Treat the wound, report the incident to the contractor safety officer, and then see a physician for follow-up
C. Treat the wound, report the incident to the contractor safety officer, and then apply an antibiotic ointment
D. Clean the wound site, report the hospital safety director, and then see a physician for follow-up.
B. A construction worker is responsible to the employer and must report through the employer’s safety system. The incident should be reported to the contractor safety officer, if available. While the contractor may opt to share this information with the hospital, it’s not the worker’s responsibility to do so. The contractor may also be required by legislation to report the incident to various government agencies; however, that responsibility lies with the contractor safety officer. It may also be requirement to see a physician for follow-up, depending on the nature of the injury.
- Under which of the following delivery methods does a design team have a contract with an owner?
- construction manager at risk
- design/build
- design/bid/build
- Integrated project delivery
A. 1, 2 and 3 only
B. 1, 2, and 4 only
C. 1, 3, and 4 only
D. 2, 3, and 4 only
C. 1, 3 & 4. True. All construction delivery methodologies involve a contractual relationship between the design team and the owner with the exception of design/build.
2. False. In design/build, the owner contracting with the deliver team and the design team is a subtractor
- Before an employee enters a permit-required confined space, the internal atmosphere shall be teste with a calibrated direct-reading instrument for oxygen content and which of the following?
A. hydrogen sulfide, and flammable gasses and vapors
B. Carbon monoxide, and flammable gasses and vapors
C. Carbon monoxide and potential toxic air contaminants
D. Potential toxic air contaminants, and flammable gasses and vapors.
D. The OSHA standard for permit required confined space requires that the atmosphere be tested for flammable gases and vapors; however there is no specific requirement for testing the atmosphere for hydrogen sulfide and carbon monoxide. Testing for hydrogen sulfide and carbon monoxide should only occur if the gas is expected to be present.
The OSHA standard for permit-required confined spaces (29 CFR 1910.146) requires that the atmosphere be tested for flammable gasses and vapors and potential toxic air contaminants.
- Which of the following are the key components in preventing water intrusion through the external shell of the building?
A. Weather barrier, air gap, and exterior finish
B. Thermal barrier, vapor barrier, and weather barrier
C. Vapor barrier, thermal barrier, and exterior sheathing
D. thermal barrier, weather barrier and exterior finish
A. it is most important to stop water intrusion at the outside of the building. Newer water shedding systems employ the elements listed in option A to accomplish this. The weather barrier reduced air pressure and prevents moisture from penetrating to the interior. The air ap provides a reduction of wind pressure, allowing wind-driven water to drop to the weep locations in the wall systems. The exterior finish is the first lien of stopping water from penetration to the interior of the building.
- Renovation work is planned on the main corridor that connects the general oncology unit with the bone marrow transplant unit. Which of the following conditions should exist before start work?
A. both patient care areas should have negative air pressure relative to the work site.
B. the work site should have negative air pressure relative to the oncology unit and positive air pressure relative to the bone marrow unit
C. Air pressure relationships for all areas should be neutral relative to each other.
D. Both patient care areas should have positive air pressure relative to the work site.
D. air flow would be away from the patient care areas and in to the work site, assuring that dust as well as fungal bacterial contaminants form the work site do not flow into either of the patient care areas.
17. A hospital plans to build a 125,000-sf ambulatory care center on a green field site. The project scheduled requires occupancy with in 12 months and a target budget is fixed. The design will be approximately 50% complete at the scheduled time of construction start. To achieve the given schedule and target budget, which of the following is the BEST delivery module for this project? A. lump Sum B. Design/Build GMP C. Cost plus stipulated fee D. Cost plus GMP at design completion
D. Cost plus GMP (Guaranteed Maximum Price) at design completion allows the owner to start the project early, price the project for work beginning, and budget the project as the design progresses. A final GMP can accurately be created on the design is completed and before much of the construction is started.
- An outpatient unit with a separate CMS provider number is being constructed as an addition to a hospital. How should the addition be separated from the hospital?
A. With non-rated construction as long as both building are fully sprinkled with no separation.
B. by a two-hour fire rated barrier when both building have the same construction type
C. by a two-hour fire barrier with both building have independent or metered utilities
D. no separation is required when both buildings have the same construction type.
C. the option features both the separation of buildings and utilities. The federal anti-kickback status, 42 U.S.C 1320a-7b(b) prohibits individuals or entities from knowingly and willfully offering, paying solicitating, or receiving remuneration to include referral of items or services covered by Medicare Medicaid or any other federal funded program (except that Federal Employees Health Benefits Program). Given this requirement, most hospitals have to interpret this to mean the las applies when physician -owned or operated facilities are not included under the hospital’s licenses. These physician-operated facilities must be freestanding building with not support form the hospital, including utilities.
- Which of the following techniques does the CDC recommend for evaluating the integrity of temporary construction barriers?
A. airborne sampling by microbiological techniques of occupied areas and construction work zones
B. surface swab sampling of construction barriers
C. Microbiological surface swab sampling of floors and countertops in occupied areas adjacent to construction work zones
D. Airborne particle counting of occupied areas.
D. Correct. The CDC Guidelines for Environmental Infection Control in Healthcare Facilities acknowledge that particle counter may be useful to evaluating integrity of construction barriers.
A. airborne sampling by microbiological is only used for few specific circumstances; outbreaks investigation, research, microbial abatement validation, and infection control procedure evaluation.
- A fire alarm system is being taken out of service for three months and a temporary fire alarm system will be put into place. According to the Interim Life Safety Measures (ILSM), is testing required of this system?
A. Yes, testing must be conducted weekly
B. Yes, testing must be conducted monthly
C. No, testing is not necessary since the system is temporary
D. No, testing is not necessary if the system is in place for three months of less.
B. TJC Life Safety Chapter, LS.01.02.01 EP 12 requires testing monthly
- Which of the following tools is used by a hospital in developing an emergency management plan?
A. Defend-in-Place Analysis
B. Hazard Vulnerability Analysis (HVA)
C. Interim Life Safety Measures (ILSM)
D. Infection Control Risk Mitigation Recommendation (ICRMR)
B. Correct- HVA is used by hospitals to assets events that could trigger the emergency operations plan for the organization and the likelihood of those events occurring.
A. Defend-in-Place is part of project design
22. A health care constructor provides the following value analysis for four buildings on a healthcare campus: Deferred Building FCI Maintenance Cancer Center 0.45 $3,000,000 Women’s Health 0.25 $1,000,000 Children’s Center 0.35 $2,000,00 Ambulatory Surgery Center 0.15 $8,000,000
Based on these data, which of the following buildings should be replaced?
A. Cancer Center B. Women’s Health
C. Children’s Care D. Ambulatory Surgery Center
A. The higher FCI indicates that is has a higher percentage of deferred maintenance or costs associated with renewal as compare to its capital value.
- which of the following conditions would MOST likely compromise the integrity of a smoke barrier?
A. non-functional smoke dampers
B. non-functional door latching hardware
C. drywall construction that has water damage
D. oversized kick plates on cross-corridor doors
A. the integrity of a smoke barrier may be compromised by a non-functional smoke damper in ductwork that passes through the smoke barrier.
24. Assuming all Interim Life Safety Measures (ILSM) listed below were put into place during a hospital renovation project, which of the following are required to be inspected on a daily basis? A. Temporary fire alarm systems B. Additional fire sprinkler heads C. Portable firefighting equipment D. Alternate exits in the affected areas
D. TJC standards (LS.01.02.01) require hospitals to evaluate the need to implement various ILSM when NFPA 101-2000 (Life Safety Code) deficiencies cannot be immediately corrected and during periods of construction. Of the various ILSM that might be implemented, only inspection of exits in the affected are is required on a daily basis by TJC.