The Rise and Fall of the Chaos Report Figures Flashcards

1
Q

What are the main criticisms of the original Chaos report?

A

The original data from which the conclusions were drawn was not published with the report.

Incompleteness - The classifications of the project were incomplete

Lack of Context - Some projects could overrun by 25% and could still be considered a success, but some could overrun by 5% and be considered a failure, it’s all about the context of the project which the report fails to understand.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Define the classification of projects in the Chaos report

A

Type 1 - Project success, Completed on time and within budget, offering all the features and functions specified.

Type 2 - Project Challenged, Project has been completed and is operational but over budget and the time estimate and additionally offers fewer features and functions than originally specified.

Type 3 - Project Impaired - The project is cancelled at some point during the development cycle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why is the classification of the projects incomplete in the chaos report?

A

It is incomplete as a project which is within budget and time, but that has less functionality doesn’t fit any category.
A project such as this is common in Software development but is not categorised in this report.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the meaning of the term f/a?

A

f/a is the forecast over actual ratio for a given project aspect.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How does f/a relate to project failure or success?

A

> 1 would be an under-run, i.e. a project completed before time. The project has delivered more than was expected.

< 1 would be an over-run, i.e. a project completed after time. The project has undelivered.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly