Tutorial contracts Flashcards
summarise contracting
Contracting is the process of one party engaging another party to undertake specific work in return for remuneration of specified sums of money.
Contracting is the process of clearly defining the roles and responsibilities of each party in the project. clearly stating what is expected, courses of action for certain scenarios, how parties will be paid or reimbersed. The contract is a legal document which is enforeable by law.
Who is the principal
The principal is the party who needs the work done in the contracting process. therefore this will be the promoter for the main contract (but may be the contractor for sub contracts)
define a contract in 2 lines
A contract, in the simplest definition is a promise enforceable by law. the promise may be to do something or to refrain from doing something
A legal document enforceable by law which clearly states roles and responsibilities of the parties involved
explain why contract law is the product of a commercial civilisation
commericial civilisation developed trade which was not completed at the same time for both parties; the transaction was based on a promise of a future event and thus laws and courts needed to be established to enforce those promises.
3 main differences between formal and simple contracts in writing
1) to be enforceable a simple contract must be supported by consideration
2) concerns the limitation period (the time following a breach of contract in which the innocent party may take action on the other) This period is generally longer for formal contracts than it is for simple contracts
3) a formal contract creates an estoppol. this is a rule of law which precludes a party from later claiming that a statement expressed in the contract is incorrect
what are the 4 basic requirements that must e satisfied to form a valid contract
1) intention by both parties to form an enforceable contract must be demonstratable
2) consent of both parties must be genuine
3) legality of the agreement must be objective
4) both parties must have the legal capacity to form an agreement
in engineering terms, provide examples how a contract may be deemed illegal
an engineering contract would rarely be illegal through a criminal act. it is more likely that the contract indicates an action that is against a law of statute, for instance health and a safety at work act of 1974
What is a merger? how is it performed?
merger is the change between a simple and a formal contract. it is performed by creating a formal instrument of agreement
why is a conditional acceptance of an offer not a contract
a conditional acceptance is actually a counter offer
what is consideration? what is its significance ?
a contract is not necessarily yo undertake an action. if there is no material exchange between parties to a contract, its existence must be demonstrated by the transfer of something of value - this is consideration
suggest reasons why one party may perform an assignment
subcontracting is an assignment of the contractor’s duties; providing an agent or other party to provide payment is an assignment of the promoter’s duties
what is the principle of privity
privity indicates that the responsibilities of the contract parties that are established with the formation of a contract may not be transferred to a 3rd party, it also indicates that a 3rd party may not cause one of the contract parties to breach those responsibilities
what is the difference between a breach and a fundamental breach of contract
breach occurs if a party does not perform according to its responsibiltiies under contract
breach becomes fundamental if it causes a situation in which the other party is unable to perform their duties and responsibilities
suggest instances in which contracts are negotiated instead of competitively tendered
1) principal may know exactly what contractor is required for the work. could be simply bcause there is only one available or because they have worked with the contractor succesfully in the past
2) the promoter wants a specific contractor so is willing to negotiate with them to secure them rather than get a more competitive offer from another contractor perhaps of which there isn’t a proven relationship already
what are the differences between prices and costs
prices: sum of money contractor recieves in return for the work carried out
costs: sums of money the contractor incurs when carrying out the work
there are 4 main factors that influence the type of contract when classified by method of payment. list these factors and indicate which type of contract is suited to the differing levels of these factors
1) degree of certainty about final contract price desired at tender stage. If a high degree of certainty is known, a lump sum contract can be used, otherwise measure and value is suitable
2) flexibility required to cope with design changes likely to be encountered during contract. if high flexibility a measure and value contract is appropriate - a lump sum is particularly inappropriate. A cost based contract would also be suitable for such a project
3) contractors incentive for efficient performance, matched by the promoters incentive to provide the contractor with timely information and decisions. A target cost based contract will provide the greatest incentive to both parties. a simple cost reimbursement contract will not do this
4) extent of risk likely to be encountered during the contract and the most cost and time efficient way of allocating it. if a project is expected to contain a high level of risk many contractors would not accept anything but a cost reimbursement contract. for low levels of risk a lump sum contract would be adequate.
what is difference between an item and an activity? give example to illustrate point (try think of new ones)
item = process of work activity = discrete unit of project construction
difference between BoQ and scheduled rates
BoQ = has estimated quantities for each item, thus allowing an estimate of the total construction price to be made
A schedule of rates has no such quantities thus total estimates annot be made easily
how is cost efficiency achieved in price based contracts
if contractor recuses costs, more money will be made as price remains same. this is contractors incentive
how is cost efficiency achieved in cost based contracts
by providing a target cost for contractor to work to, cost savings are rewarded with a share of these savings - and penalty of a share of any cost over target
what are the differences between traditional contracts where the design and construction are separate and a design and construct contract
the main difference is that the designer os employed by the contractor, not the promoter. means promoter must employ a separate advisory engineer. it does allow for greater contractual freedom for innovation of design
in this contract the main contractor does not carry out the construction work
management contract
in this contract the promoter has little involvement with the design, construction and commissioning of the project
turnkey contract
this contract has a high degree of tender competition.however it is difficult to assess which submission may yield the lowest final price
schduled rates - dont think we need to know this stuff