UNIT 6 : ENERGY AND ATMOSPHERE Flashcards
(86 cards)
_________ allows utilities to call on buildings to decrease their electricity use during peak times, reducing the strain on the grid and the need to operate more power plants, thus potentially avoiding the costs of constructing new plants.
Demand response
Requirements for _____ enclosures are limited to inclusion in the owner’s project requirements (OPR) and basis of design (BOD) during the commissioning process.
exterior
By the end of the ______ phase, engage a commissioning authority with the following qualifications.
Design development
The CxA must have documented commissioning process experience on at least ___ building projects with a similar scope of work
two
In all cases,the CxA must report his or her findings directly to the _____
owner
The owner, with the help of the design team and other stakeholders, should develop the initial owner’s project requirements (OPR) in the \_\_\_\_\_\_ stage
predesign
The ____ must include all systems to be commissioned plus the building envelope, even if full envelope commissioning is not pursued.
OPR
The ____ is the project team’s interpretation of the OPR.
BOD
Create a basis of design (BOD) to provide clear technical guidance for the project in the
______ design phase
schematic
The ____ is a living document that is updated throughout the life of the project and will become the
basis for the final commissioning report.
Cx plan
____ is a central energy conversion plant and transmission and distribution system that
provides thermal energy to a group of buildings (e.g., a central cooling plant on a university campus).
district energy system (DES)
______ is the heating and cooling systems, equipment, and controls located in the project building or on the project site and associated with transporting the thermal energy of the district energy system (DES) into heated and cooled spaces.
downstream equipment
____is a heating or cooling system or control associated with the district energy system (DES) but
not part of the thermal connection or interface with the DES.
upstream equipment
______ equipment includes the thermal connection or interface with the DES, secondary distribution systems in the building, and terminal units
Downstream
_____ equipment includes the thermal energy
conversion plant and all the transmission and distribution equipment associated with transporting the thermal energy to the project building or site.
Upstream
Buildings consume an estimated __% of the total energy consumed in the world
40%
For EA Prerequisite Minimum Energy Performance, Option 3, the energy performance target must be
established using ENERGY STAR’s Target Finder and must be greater than a score of ____
90
ASHRAE 90.1–2010 defines___ climate zones and
three climate types: A (moist), B (dry), and C (marine)
eight
Power Usage Effectiveness ( PUE ) =
PUE = total data center energy
consumption or power/
IT energy consumption
or power
In the 1987 ______established an international agreement to phase out use of the most harmful ozone-depleting substances, including
CFCs.
Montreal Protocol
Cx Plan includes the following when pursuing EA-C Demand Response?
One performance test of full demand-response plan.
Proves that all equipment responds as planned and all parties understand their roles.
Carbon Offset?
Reduction in emissions of carbon dioxide or green house gases made to compensate for/offset an emission made elsewhere.
To meet EA-C Optimize Energy project team will address nonregulated load savings by?
Using exceptional calculation method (ECM) in a whole-building energy simulation.
Green-e energy certification applies to which EA-C?
EA-C Green Power and Carbon Offsets