Materials price sub-variance
Actual quantity x (Standard price per unit – Actual price per unit)
Materials usage sub-variance
Standard price x (Standard quantity – Actual quantity)
Overall materials variance
Materials price sub-variance + Materials usage sub-variance
Labour rate sub-variance
Actual labour hours x (Standard hourly rate – Actual hourly rate)
Labour efficiency sub-variance
Standard rate x (Standard hours – Actual hours)
Overall labour variance
Labour rate sub-variance + Labour efficiency sub-variance
Sales price sub-variance
Actual quantity x (Standard selling price– Actual selling price)
Sales volume sub-variance
Standard price x (Standard quantity – Actual quantity)
Overall sales variance
Sales price sub-variance + Sales volume sub-variance