Visual Sprint Planning Process Flashcards
-Handling Project Risks and Identifying Improvement Ideas | Project Reflection and Learning
What is an essential input needed to plan the sprints and deliver effect continuously throughout the project?
A. Impact case
B. The stakeholder map
C. The Impact Solution Design
D. The pulse check measuring effect experienced by the key stakeholders
C. The Impact Solution Design
What is the procedure described by the efficiency paradigm?
A.
Sense the situation
Categorize the problem
Analyze possible improvements
Respond
B.
Confirm
Clear
Cordon
Control
C.
Situation
Complication
Questions
Answer
D.
Know
Can
Choose
Execute
A.
Sense the situation
Categorize the problem
Analyze possible improvements
Respond
How many steps does the pulse checks process have?
A. 4
B. 5
C. 6
D. 10
C. 6
1) identifying and grouping key stakeholders
2) adapting the standard questions to the organizational culture
3) designing the pulse check process to align with the project heartbeat and key events
4) obtaining buy-in and communicating the purpose, tool, and processes to key
stakeholders
5) initiating the process, and continuously enforcing the process
6) following up on people’s engagement
Why is it essential that the project owner is actively involved in the project?
A. The project owner needs to be able to intervene in multiple departments, negotiate with mid-level managers, and eliminate impediments along the way
B. Only they have the formal power to change the project organization’s direction
C. They have the mandate to make critical decisions regarding the focus and the intended impact of the project
D. All of the above
D. All of the above
Which of the following statements about the Local Translation is true?
Statement 1: The local translation tools are
Governance customization
Half Double reflective tool
Adaption of mindset
Statement 2: The local translations tools should be used to facilitate dialogues with key stakeholders.
Statement 2: The local translations tools should be used to facilitate dialogues with key stakeholders.
Which of the following are NOT an impact tool?
A. Work breakdown structure (WBS)
B. Impact case & Impact tracking
C. Impact Solution Design
D. Pulse check
A. Work breakdown structure (WBS)
In cases where the project sponsor and the project owner are two different people, where should the roles be placed?
A. Both project sponsor and project owner should be in the executive level
B. Both project sponsor and project owner should be in the upper- or mid-management level
C. Individuals who have been in the organization for a long duration and are considered senior people
D. The project sponsor should be on the executive level and the project owner should be in upper- or mid-management level. In these cases, the project sponsor should delegate the real power to the project owner.
B. Both project sponsor and project owner should be in the upper- or mid-management level
Which of the following are considered Flow methods?
1) Allocate core team +50% and assure co-location. Reduce complexity in time and space to free up time to solve complex problems.
2) Define a fixed project heartbeat for stakeholder interaction to progress the project in sprints.
3) Design your project to deliver impact as soon as possible with end users close to the solution.
4) Increase insight and commitment using visual tools and plans to support progression.
A. 1, 2, 3
B. 1, 2, 4
C. 2, 3, 4
D. 1, 3, 4
B. 1, 2, 4
1) Allocate core team +50% and assure co-location. Reduce complexity in time and space to free up time to solve complex problems.
2) Define a fixed project heartbeat for stakeholder interaction to progress the project in sprints.
4) Increase insight and commitment using visual tools and plans to support progression.
What should the collaborative project leader do on the PROJECT level?
A. Leading the impact, being hard on the impact, and flexible on deliverables
B. Facilitating and energizing interactions
C. Be present, find a way and motivate stakeholders
D. Putting people first, creating purpose, autonomy, and mastery for the team and key stakeholders
A. Leading the impact, being hard on the impact, and flexible on deliverables
What is a benefit of co-locating the project team in close proximity?
A. Questions are answered quickly
B. Ideas can be shared and qualified quickly
C. It increases motivation of the project team members
D. All of the above
D. All of the above
The Impact Solution Design must create a core idea that visualizes the project’s value creation for the entire duration of the project.
To identify the core idea for reducing the time to impact, Half Double suggest you refer to the areas of Product, Process and People.
Which of the questions below fits the Process area?
A. Could we deliver part of or half of the process for each release?
B. Could we release the core version of the product as a minimum viable product and then build on it?
C. What is the core use of the product/service/system/process?
D. Can we limit the first release to only focus on a specific group to reduce time to impact?
A. Could we deliver part of or half of the process for each release?
Half Double recommends a four-step process for customizing governance. What is the correct order of the process?
1) Consider what these adjustment requirements mean in the context that the project is to be implemented in
2) Anchor with key people and involve key stakeholders and management to handle rigid rules that prevent project progress
3) Draw up a plan for how concrete changes are made in the most important governance areas
4) Analyze the project and assess where it is important to adjust the existing governance routines to promote success
A. 1, 2, 3, 4
B. 2, 3, 1, 4
C. 3, 4, 2, 1
D. 4, 1, 2, 3
D. 4, 1, 2, 3
How should the project team members be regarded?
A. As a Full-time Equivalent this is required to deliver according to the project plan
B. As a replaceable resource that is allocated to the project for an agreed upon amount of hours per week
C. As a key resource in the project that needs the optimal conditions to do his or her best work
D. A and B
C. As a key resource in the project that needs the optimal conditions to do his or her best work
What is likely to demotivate the project’s key stakeholders?
A. Getting attention from the project leader and project owner
B. Answering a pulse check but not hearing how their answers are used
C. Being able to affect the project
D. A and B
B. Answering a pulse check but not hearing how their answers are used
Working with project visuals addresses certain motivational factors. Which factors does it address?
A. Purpose – the yearning to do something for a reason greater than yourself and your own work on the project.
B. Mastery – the desire to get better and be better at something that matters.
C. Autonomy – the urge to direct our own work and effort.
D. All of the above
D. All of the above