What schedule 2 quotations were put forward (BP)
A
For steel work to lightwell. options to get around a discovered structural piece
2
Q
How long was the period to issue schedule 2 quotations? (BP)
A
Amended from 21 to 14 days unless agreed otherwise
3
Q
How much was it to break through the meter thick wall? (BP)
A
c. £10k
4
Q
What did you allow for when demolishing the meter thick wall? (BP)
A
2 men for one week @ £35/hr
temporary propping
4nr lintels
making good
supervision
5
Q
Who was part of the discussion when reviewing the structural wall demo variation requirements? (BP)
A
Architect
Structural engineer