West Section Flashcards

(5 cards)

1
Q

What schedule 2 quotations were put forward (BP)

A

For steel work to lightwell. options to get around a discovered structural piece

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How long was the period to issue schedule 2 quotations? (BP)

A

Amended from 21 to 14 days unless agreed otherwise

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How much was it to break through the meter thick wall? (BP)

A

c. £10k

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What did you allow for when demolishing the meter thick wall? (BP)

A

2 men for one week @ £35/hr
temporary propping
4nr lintels
making good
supervision

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Who was part of the discussion when reviewing the structural wall demo variation requirements? (BP)

A

Architect
Structural engineer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly