03 Developing the Project Plan Flashcards
(19 cards)
The ___ for the project is an
early compilation of the significant work items that will have
associated cost or schedule considerations.
work breakdown structure (WBS)
is defined as a task-oriented, detailed breakdown of
activities that organizes, defines, and graphically displays the
total work to be accomplished to achieve the final objectives of
a project
work breakdown structure (WBS)
A__ is a breakdown or
hierarchical representation of the various costs in a project.
cost breakdown structure (CBS)
is the determination of the timing and
sequence of operations in the project and their
assembly to give the overall completion time.
scheduling
is the determination of the timing and
sequence of operations in the project and their
assembly to give the overall completion time
risk analysis
A project management
tool in which the stages of a project are graphically represented on a chart
Program Evaluation and Review Technique (PERT)
A network analysis
technique that allows for conditional and probabilistic treatment of logical
relationships (that is, some activities may not be performed).
Graphical Evaluation and Review Technique (GERT)
An event-oriented network analysis technique used to estimate project duration
when there is a high degree of uncertainty with individual activity duration
estimates.
Program Evaluation and Review Technique (PERT)
applies the critical path method to a weighted average duration
estimate.
Program Evaluation and Review Technique (PERT)
is considered a probabilistic method.
Program Evaluation and Review Technique (PERT)
is incorrectly used in the construction industry sometimes to denote a Logic
Network
PERT Diagram
Is a modification of the
traditional GERT approach in that it recognizes special circumstances where
multiple numbers of the project teams or activities must be taken into
consideration simultaneously.
Queue-Graphical Evaluation and Review Technique
the simulation
language for alternative modelling, was the first simulation language which
allowed a modeler to formulate a system description using process, event, or
continuous world views or any combination of the 3.
Simulation Language for Alternative Modelling (SLAM)
which has been
developed to help prepare a robust construction plan, focusing on construction
feedbacks in dealing with indirect and unanticipated events during construction
Dynamic Planning and Control Methodology (DPM)
is a project
management methodology that helps you monitor essential resources and
prioritize dependent tasks within a project.
Critical chain project management (CCPM)
The extra time that’s placed between the final task and the end
of the project.
project buffers
The extra time that’s placed between the feeding chain (also
known as the non-critical chain) and the critical chain.
feeding buffers
These are literal resources you set aside in case the critical
chain is in need of extra supplies—like extra team members to have on hand,
additional equipment, or help from a third-party.
resource buffers
is the full amount of assigned hours you
have tasked your team with divided by the number of hours you have to do the
work. You can view resource loading on a daily, weekly, monthly or project
basis.
resource loading