03 Developing the Project Plan Flashcards

(19 cards)

1
Q

The ___ for the project is an
early compilation of the significant work items that will have
associated cost or schedule considerations.

A

work breakdown structure (WBS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

is defined as a task-oriented, detailed breakdown of
activities that organizes, defines, and graphically displays the
total work to be accomplished to achieve the final objectives of
a project

A

work breakdown structure (WBS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A__ is a breakdown or
hierarchical representation of the various costs in a project.

A

cost breakdown structure (CBS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

is the determination of the timing and
sequence of operations in the project and their
assembly to give the overall completion time.

A

scheduling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

is the determination of the timing and
sequence of operations in the project and their
assembly to give the overall completion time

A

risk analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A project management
tool in which the stages of a project are graphically represented on a chart

A

Program Evaluation and Review Technique (PERT)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

A network analysis
technique that allows for conditional and probabilistic treatment of logical
relationships (that is, some activities may not be performed).

A

Graphical Evaluation and Review Technique (GERT)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

An event-oriented network analysis technique used to estimate project duration
when there is a high degree of uncertainty with individual activity duration
estimates.

A

Program Evaluation and Review Technique (PERT)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

applies the critical path method to a weighted average duration
estimate.

A

Program Evaluation and Review Technique (PERT)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

is considered a probabilistic method.

A

Program Evaluation and Review Technique (PERT)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

is incorrectly used in the construction industry sometimes to denote a Logic
Network

A

PERT Diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Is a modification of the
traditional GERT approach in that it recognizes special circumstances where
multiple numbers of the project teams or activities must be taken into
consideration simultaneously.

A

Queue-Graphical Evaluation and Review Technique

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

the simulation
language for alternative modelling, was the first simulation language which
allowed a modeler to formulate a system description using process, event, or
continuous world views or any combination of the 3.

A

Simulation Language for Alternative Modelling (SLAM)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

which has been
developed to help prepare a robust construction plan, focusing on construction
feedbacks in dealing with indirect and unanticipated events during construction

A

Dynamic Planning and Control Methodology (DPM)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

is a project
management methodology that helps you monitor essential resources and
prioritize dependent tasks within a project.

A

Critical chain project management (CCPM)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The extra time that’s placed between the final task and the end
of the project.

A

project buffers

17
Q

The extra time that’s placed between the feeding chain (also
known as the non-critical chain) and the critical chain.

A

feeding buffers

18
Q

These are literal resources you set aside in case the critical
chain is in need of extra supplies—like extra team members to have on hand,
additional equipment, or help from a third-party.

A

resource buffers

19
Q

is the full amount of assigned hours you
have tasked your team with divided by the number of hours you have to do the
work. You can view resource loading on a daily, weekly, monthly or project
basis.

A

resource loading