1° Full-Length Test Flashcards
(180 cards)
Which of the following is NOT a characteristic of a project?
A) Temporary
B) Unique product, service, or result
C) Ongoing operation
D) Progressive elaboration
Correct Answer: C
The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and creating a staffing management plan is known as:
A) Develop Project Team
B) Plan Human Resource Management
C) Acquire Project Team
D) Manage Project Team
Correct Answer: B
What is the primary purpose of ‘Earned Value Analysis’ (EVA) in project management?
- A) To measure the project team’s performance and progress.
- B) To assess the project’s risk exposure.
- C) To evaluate the accuracy of the project schedule.
- D) To determine the project’s communication effectiveness.
Correct Answer: A
‘Stakeholder Engagement’ levels are categorized into which of the following groups?
- A) Unaware, Resistant, Neutral, Supportive, Leading
- B) Informed, Uninformed, Supportive, Neutral, Resistant
- C) Unaware, Aware, Interested, Supportive, Active
- D) Aware, Unaware, Supportive, Neutral, Opposed
Correct Answer: A
Which process is responsible for tracking team member performance, providing feedback, resolving issues, and managing team changes?
- A) Develop Project Team
- B) Manage Project Team
- C) Acquire Project Team
- D) Plan Human Resource Management
Correct Answer: B
The ‘Critical Path Method’ (CPM) is used to:
- A) Identify the shortest path and longest duration to complete the project.
- B) Calculate the baseline budget for the project.
- C) Determine the most cost-effective use of resources.
- D) Assess the risk impact on project timelines.
Correct Answer: A
‘Qualitative Risk Analysis’ should be performed:
- A) Only at the beginning of the project.
- B) Periodically throughout the project lifecycle.
- C) Only when new risks are identified.
- D) At the closure of the project.
Correct Answer: B
What is the main goal of ‘Integrated Change Control’?
- A) To ensure that all changes are documented.
- B) To facilitate decision making on requested changes.
- C) To prevent any changes to the project scope.
- D) To monitor the project performance.
Correct Answer: B
‘Resource Leveling’ will most likely result in:
- A) A shorter project duration.
- B) Increased project costs.
- C) An unchanged project scope.
- D) An extension of the project schedule.
Correct Answer: D
The ‘Schedule Performance Index’ (SPI) is:
- A) A measure of schedule efficiency on a project.
- B) A projection of future project schedule performance.
- C) The ratio of earned value to planned value.
- D) The ratio of actual cost to planned cost.
Correct Answer: A
‘Procurement Management Plan’ includes:
- A) Selection criteria for sellers.
- B) Work performance data.
- C) Project team members’ roles and responsibilities.
- D) Change request forms.
Correct Answer: A
What does a ‘Risk Breakdown Structure’ (RBS) provide?
- A) A hierarchical decomposition of risks by category.
- B) An estimation of the probability and impact of risks.
- C) A schedule for risk management activities.
- D) A detailed plan for risk response strategies.
Correct Answer: A
‘Cost Aggregation’ is used in which process?
- A) Estimate Costs
- B) Determine Budget
- C) Control Costs
- D) Plan Cost Management
Correct Answer: B
The primary purpose of ‘Project Scope Management’ is to:
- A) Ensure the project includes all the work required, and only the work required, to complete the project successfully.
- B) Control the costs associated with the project.
- C) Manage the timeline and schedule of the project.
- D) Define the roles and responsibilities of the project team.
Correct Answer: A
In ‘Plan Communications Management,’ which factor is the most critical to consider?
- A) The project’s organizational structure.
- B) The urgency of the project.
- C) Stakeholder information needs and requirements.
- D) The budget allocated for communications.
Correct Answer: C
What is the ‘Project Management Plan’?
- A) A document that describes how the project will be executed, monitored, and controlled.
- B) A formal agreement between the project team and the customer.
- C) A detailed schedule of all project activities.
- D) A chart that shows team members and their responsibilities.
Correct Answer: A
‘Variance at Completion’ (VAC) is:
- A) The difference between the budget at completion and the earned value.
- B) The difference between the budget at completion and the actual cost.
- C) A forecast of the total cost variance compared to the budget at the end of the project.
- D) The amount of budget deficit or surplus at the end of the project.
Correct Answer: C
The ‘Perform Qualitative Risk Analysis’ process primarily:
- A) Assesses the impact of identified risks on project objectives.
- B) Quantifies the effects of risks on project outcomes.
- C) Prioritizes risks based on their probability and impact.
- D) Develops responses to high-priority risks.
Correct Answer: C
Which of the following best describes ‘Fast Tracking’?
- A) Performing activities sequentially.
- B) Adding more resources to critical activities.
- C) Performing activities in parallel that were originally planned in sequence.
- D) Reducing the project scope to speed up completion.
Correct Answer: C
A ‘Bidder Conference’ is used in:
- A) Plan Risk Management
- B) Estimate Activity Durations
- C) Conduct Procurements
- D) Control Stakeholder Engagement
Correct Answer: C
The purpose of ‘Control Schedule’ is to:
- A) Develop the project schedule.
- B) Shorten the project duration without changing the project scope.
- C) Update project progress and manage changes to the schedule baseline.
- D) Ensure that project activities are completed on time.
Correct Answer: C
‘Scope Baseline’ includes all of the following EXCEPT:
- A) Project scope statement.
- B) Work Breakdown Structure (WBS).
- C) WBS Dictionary.
- D) Change Log.
Correct Answer: D
What is the main advantage of ‘Decomposition’ in project management?
- A) It allows for more accurate cost and duration estimates.
- B) It speeds up the process of developing the project schedule.
- C) It eliminates the need for a project management plan.
- D) It reduces the complexity of the project scope.
Correct Answer: A
The ‘Manage Quality’ process is characterized by:
- A) Ensuring the project’s deliverables meet the agreed-upon standards and stakeholder expectations.
- B) Identifying quality requirements and standards for the project and its deliverables.
- C) Implementing the quality management plan to ensure that work is being performed effectively.
- D) Monitoring and recording the results of quality activities to assess performance and recommend necessary changes.
Correct Answer: C