2° Full-Length Test Flashcards
(180 cards)
Which of the following is a primary output of ‘Develop Project Charter’?
- A) Project scope statement
- B) Project management plan
- C) Project charter
- D) Stakeholder register
Correct Answer: C
The ‘Buyer-Conducted Performance Review’ is an activity within which process?
- A) Control Procurements
- B) Plan Procurement Management
- C) Conduct Procurements
- D) Close Procurements
Correct Answer: A
‘Project Scope Management’ includes:
- A) Defining and controlling what is included and what is not included in the project.
- B) Identifying the project outcomes beneficial to stakeholders.
- C) Managing the project team.
- D) Ensuring the project is completed within the approved budget.
Correct Answer: A
‘Earned Value Analysis’ (EVA) is utilized to:
- A) Estimate the required budget at completion of the project.
- B) Measure the project performance against the scope, schedule, and cost baselines.
- C) Define the total scope of the project.
- D) Allocate the project resources efficiently.
Correct Answer: B
The main purpose of ‘Control Schedule’ is to:
- A) Develop the project schedule.
- B) Ensure that project activities are completed on time.
- C) Monitor the status of project activities to update project progress and manage changes to the schedule baseline.
- D) Allocate sufficient time for project tasks.
Correct Answer: C
Which process involves reviewing all change requests, approving changes, and updating the project management plan and project documents?
- A) Direct and Manage Project Work
- B) Monitor and Control Project Work
- C) Perform Integrated Change Control
- D) Control Scope
Correct Answer: C
‘Stakeholder Analysis’ is a technique used in:
- A) Develop Project Charter
- B) Identify Stakeholders
- C) Plan Stakeholder Engagement
- D) Manage Stakeholder Engagement
Correct Answer: B
The ‘To-Complete Performance Index’ (TCPI) is calculated to:
- A) Determine the cost performance required to complete the project within the original budget.
- B) Measure the cost efficiency of work performed to date.
- C) Forecast the project’s schedule performance.
- D) Assess the project team’s effectiveness.
Correct Answer: A
‘Qualitative Risk Analysis’ should:
- A) Assign a numerical value to both the probability of occurrence and the impact of project risks.
- B) Prioritize risks based on their probability of occurrence and potential impact on project objectives.
- C) Quantify the possible outcomes for the project and their probabilities.
- D) Develop responses for the highest priority risks.
Correct Answer: B
In the ‘Manage Communications’ process, what is a key activity?
- A) Creating a detailed project budget.
- B) Ensuring that project information is generated, collected, distributed, and understood.
- C) Performing a stakeholder analysis.
- D) Updating the project risk register.
Correct Answer: B
Which of the following best describes ‘Resource Leveling’?
- A) Enhancing project team members’ skills through additional training.
- B) Adjusting the project schedule to address resource over-allocation.
- C) Allocating the most skilled resources to high-priority tasks.
- D) Reducing the project scope to meet resource availability.
Correct Answer: B
The ‘Cost Management Plan’ is developed in which process?
- A) Plan Cost Management
- B) Estimate Costs
- C) Determine Budget
- D) Control Costs
Correct Answer: A
‘Procurement Statements of Work’ (SOW) are developed to:
- A) Describe the procurement item in sufficient detail to allow prospective sellers to determine if they are capable of providing the products, services, or results.
- B) Outline the project’s scope in detail.
- C) Provide vendors with a clear understanding of project timelines.
- D) Establish the project’s quality requirements.
Correct Answer: A
What does the ‘Project Schedule Network Diagram’ provide?
- A) An estimation of the project’s costs.
- B) A visual representation of the project’s activities and their interdependencies.
- C) The critical path of the project.
- D) Both B and C.
Correct Answer: D
During which process group is the ‘Project Charter’ developed?
- A) Initiating
- B) Planning
- C) Executing
- D) Monitoring and Controlling
Correct Answer: A
‘Risk Urgency Assessment’ is a tool used to:
- A) Measure the severity of potential project risks.
- B) Prioritize risks based on their urgency and potential impact on project objectives.
- C) Identify the risks that require immediate response.
- D) Determine the probability of risk occurrence.
Correct Answer: B
The main goal of ‘Plan Communications Management’ is to:
- A) Ensure that all project stakeholders are kept informed about the project status.
- B) Determine the information and communications needs of the project stakeholders.
- C) Develop an appropriate approach for project communications based on stakeholder needs and requirements.
- D) Implement the tools and techniques necessary to enhance project communication.
Correct Answer: C
The ‘Control Quality’ process is crucial because it:
- A) Defines the quality standards for the project.
- B) Identifies quality metrics for the project.
- C) Ensures that the project’s deliverables meet the defined quality standards.
- D) Develops the project management plan.
Correct Answer: C
‘Bottom-Up Estimating’ is a technique that:
- A) Estimates the project cost by aggregating the individual costs from the bottom up.
- B) Provides a quick and easy way to estimate project duration.
- C) Is used exclusively during the closing phase of the project.
- D) Relies solely on the expertise of top management for estimation.
Correct Answer: A
Which process involves establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule?
- A) Plan Schedule Management
- B) Develop Schedule
- C) Control Schedule
- D) Sequence Activities
Correct Answer: A
‘Configuration Management’ is primarily concerned with:
- A) Managing the project team’s configuration.
- B) Tracking changes to the product configuration and documenting them.
- C) Ensuring the compatibility of project hardware and software.
- D) Managing the project schedule configuration.
Correct Answer: B
‘Stakeholder Management Plan’ is developed to:
- A) Identify project stakeholders.
- B) Analyze the potential impact of project decisions on stakeholders.
- C) Outline strategies to engage stakeholders effectively.
- D) Track stakeholder satisfaction.
Correct Answer: C
The purpose of ‘Perform Integrated Change Control’ is to:
- A) Review all change requests, approve changes, and manage changes to the deliverables, organizational process assets, and project documents.
- B) Ensure that all changes are communicated to all stakeholders.
- C) Implement approved changes to the project scope, plans, and environment.
- D) Both A and C.
Correct Answer: D
What is the purpose of the ‘Monitor Stakeholder Engagement’ process?
- A) To identify all stakeholders at the beginning of the project.
- B) To plan how to engage stakeholders effectively.
- C) To track project performance and make necessary adjustments to the engagement strategies.
- D) To ensure all stakeholders are fully satisfied with the project outcomes.
Correct Answer: C