Scheduling 2 Flashcards

0
Q
  1. For each of these LOWEST LEVEL tasks:
A

A. A specific crew can be assigned to achieve its objectives.
B. The crew and quantity of work determine its duration.
C. Each task has a natural sequence relative to other tasks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q
  1. As each lower level of the WBS is developed, a more detailed schedule can be made with the larger number of tasks.
A

When individual tasks are simple enough for their duration to be estimated, we do not subdivide tasks any further.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. When the FINAL plan is accepted just prior to start of construction, the FINAL schedule provides:
A

A. A solid timeline for ordering all resources.
B. The best start times for all tasks.
C. A forecast of cash flow for the life of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. The PYRAMID OF TASKS areas in the WBS that expands downward defines:
A

a TOP TO BOTTOM pattern for delegating RESPONSIBILITY and AUTHORITY.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. Note that any COMPLETE level of the WBS represents:
A

A COMPLETE DESCRIPTION OF THE PROJECT.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. The PYRAMID OF RESPONSIBILITY not only defines the downward flow of authority, it also defines:
A

the REVERSE BOTTOM TO TOP direction for reporting.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly