Scheduling 2 Flashcards
0
Q
- For each of these LOWEST LEVEL tasks:
A
A. A specific crew can be assigned to achieve its objectives.
B. The crew and quantity of work determine its duration.
C. Each task has a natural sequence relative to other tasks.
1
Q
- As each lower level of the WBS is developed, a more detailed schedule can be made with the larger number of tasks.
A
When individual tasks are simple enough for their duration to be estimated, we do not subdivide tasks any further.
2
Q
- When the FINAL plan is accepted just prior to start of construction, the FINAL schedule provides:
A
A. A solid timeline for ordering all resources.
B. The best start times for all tasks.
C. A forecast of cash flow for the life of the project.
3
Q
- The PYRAMID OF TASKS areas in the WBS that expands downward defines:
A
a TOP TO BOTTOM pattern for delegating RESPONSIBILITY and AUTHORITY.
4
Q
- Note that any COMPLETE level of the WBS represents:
A
A COMPLETE DESCRIPTION OF THE PROJECT.
5
Q
- The PYRAMID OF RESPONSIBILITY not only defines the downward flow of authority, it also defines:
A
the REVERSE BOTTOM TO TOP direction for reporting.