Scheduling 10 Flashcards
- If the EST of a
task is 13 and the LST is 17, and the EFT is 15 and the LFT is 19, but the work is delayed, then the task can finish on:
17, 18, or 19.
- The difference
between a task’s EST and LST is:
TOTAL FLOAT
- What is the
definition of FREE FLOAT?
The amount of time available for rescheduling a task WITHOUT AFFECTING THE SCHEDULE OF ANY OTHER TASK.
- If a predecessor
task has a TOTAL FLOAT of 2 days but the follower task starts on the predecessor’s EFT, then:
the PREDECESSOR TASK has ZERO FREE FLOAT, even though it has a total float of 2 days.
- What is FLOAT?
A measure of the flexibility available for rescheduling a task or string of tasks making up a path through the network.
- Where do you
put the calculations for TF and FF?
TF’s outside the SSC, on the bottom left hand side. FF is on the bottom RHS.
- How do you
calculate TF for a task?
LST-EST=TF
- How do you
calculate FF for a task?
Task 2 EST -Task 1 EFT