SB Activities Flashcards

1
Q

Managing a Stage Boundary Process (5)

A
  1. Plan the Next Management Stage
  2. Update the Project Plan
  3. Update the Business Case
  4. Report Management Stage End
  5. Produce an Exception Plan
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

SB 1. Plan the Next Management Stage (6)

PSCRIQ

A
PID
Stage plan
Configuration item records
Risk Register
Issue Register
Quality Register
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

SB 2. Update the Project Plan (3)

PIR

A

Project Plan
Issue Register
Risk Register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. Update the Business Case (4)

BBRI

A

Business Case
BMA
Risk Register
Issue Register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. Report Management Stage End (3)

ELF

A

End Stage Report
Lessons Report
Follow-on Action Reccomendatiosn

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. Produce an Exception Plan (6)

PECRIQ

A
PID
Exception Plan
Configuration item records
Risk Register
Issue Register
Quality Register
How well did you know this?
1
Not at all
2
3
4
5
Perfectly