28: Uses of Capital Flashcards

1
Q

Capital allocation is the process planning _____ on assets where the _____ to the firm are expected to be greater than 1 years

A

planning expenditures based on cash flows

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Making good capital allocation decisions must be consistent with the manager’s primary goal of:

A

maximizing shareholder value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Are interest costs included in the estimate of the incremental cash flows from an investment?

A

No. Costs to finance the investment are taken into account when the cash flows are discounted at the appropriate cost of capital;
including interest costs in the cash flows would result in double-counting the cost of debt

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Sunk costs _____ be included in the analysis

A

Should not, these costs are not affected by the accept/reject decision because they cannot be avoided

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

the effects of acceptance of a project may have on other firm cash flows

A

externatilites

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A common example of a ____ externality is cannibalization, which occurs when:

A

negative externality because the new project takes sales from an existing one

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Cash flows are based on:

A

opportunity costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cash flows are analyzed on an ______ basis

A

after tax
the impacts of taxes must be considered when analyzing all capital allocation projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Financing costs, like interest payments, are reflected in the project’s:

A

required rate of return (discount rate) & therefore should not be included in the cash flows

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The net present value (NPV) of an investment is equal to the sum of the expected cash flows discounted at the:

A

opportunity cost of capital

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

IRR is the discount rate that makes the net present value equal to zero

A

IRR is the discount rate to make PV inflows = PV outflows

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

When comparing ROIC and cost of capital, if all projects have a positive NPV, ROIC is ____ cost of capital, and these projects are providing return that is greater than ______

A

Since all projects have a positive NPV, they are all providing a return that is greater than the opportunity cost of capital.
Therefore, the ROIC > cost of capital

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

____ is a direct measure of the expected change in firm value from undertaking a project

A

NPV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

____ is related to share value; and should cause a proportionate increase in a company’s stock price, of _____/shares outstanding, but other factors are related

A

NPV
NPV per shares outstanding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

IRR shows the return on _____

A

each dollar invested as a percentage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

When dealing with mutually exclusive projects, the most reliable decision rule is:

A

NPV

17
Q

The value of a company is the value of its _____ plus the ______ of all of its future investments

A

existing investments + net present values

18
Q

The internal rate of return method assumes that the cash flows from a project are reinvested at the project’s ____; the net present value (NPV) method assumes that cash flows are reinvested at _____.

A

IRR
the cost of capital

19
Q

used to identify systematic errors in the forecasting process and improve operations is which step of the capital allocation process?

A

conducting post audit (last step)

20
Q

For independent projects the NPV decision rule is to:
For mutually exclusive projects the NPV decision rule is to:

A

accept all projects with a positive NPV
accept the project with the highest NPV

21
Q

When the NPV = 0, this means the discount rate used is _____ IRR

A

cost of capital = IRR

22
Q

changing the inputs into a production process:
option to sell:
option to increase capacity:

A

flexibility option
abandonment
expansion

23
Q

IRR analysis will yield ____ accept/reject decision for a single project compared to NPV

A

the same

24
Q

NPV is the preferred method, but should be used especially when there are ____ IRR

A

multiple project IRRs

25
Q

Unconventional cash flows where the sign of the cash flows change more than once cause:

A

multiple IRR

Conventional cash flows= 1 IRR

26
Q

NPV will = IRR for projects:

A

for independent projects with conventional cash flows

27
Q

Conflict between the NPV and IRR decision rules can arise when evaluating mutually exclusive projects with conventional cash flows because:

A

1) the scale of investments may differ and/or 2) the timing of the cash flows may differ