Network Analysis, Critical Path & Gantt Chart Flashcards

1
Q

What is Network Analysis?

A

Network Analysis is a technique adopted in planning and controlling unique and complex projects. It is a system of planning a project outline by analyzing its associated activities. In network analysis, complex projects are broken down into smaller activities or tasks, which are then organized according to a sequence. Then, the order of tasks/activities is also decided according to a logical sequence.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a Network diagram / Gantt Chart / Programme? And why use it?

A

A network diagram is prepared whereby all project activities are represented visually. The diagram depicts the cost of various activities and establishes a relationship between various tasks. The process is helpful in different phases of project management from planning, controlling and coordinating to decision-making. It ensures that the project is successfully completed economically and much before the time while exploiting minimum resources. Hence, network analysis reduces operational cost, total time, wastage of resources and conflicts in projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What does CPM stand for?

A

Critical Path Method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

In essence, what is the purpose of the Critical Path Method

A

It’s a tool that provides a means of determining which jobs or activities, of the many that comprise a project, are “critical” in their effect on total project time, and how best to schedule all jobs in the project in order to meet a target date at minimum cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the 7 characteristics that form the Network Analysis?

A

EST - Earliest Start Time
D - Duration
EFT - Earliest Finish Time

Name of Activity

LST - Latest Start Time
F - Float
LFT - Latest Finish Time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the formula for EFT?

A

EST + D

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the Formula for LFT

A

LST + D

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How do we obtain the LFT?

A

Complete the earliest section (top half of the analysis) for all activities in order to obtain the finsih date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How do we obtain the LFT?

A

Complete the earliest section (top half of the analysis) for all activities in order to obtain the finish date. Then, use the acquired finish date as the LFT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How do we calculate the LST

A

LFT - D

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How do we calculate Float (F)?

A

LST - EST

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the purpose of Float (F)?

A

It is used to assess the scheduling flexibility of Programme activities (Also known as Slack). Determining the float can provide opportunities to formulate strategies to ensure project completion.
In simple terms, the float allows a specific activity to deviate from the programme’s critical path without affecting the overall project completion date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly