Steps of Developing a PMP

A

a. Develop PMP
b. Plan scope management
c. Plan schedule management
d. Plan cost management
e. Plan risk management
f. Plan stakeholder management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Step 1a - Develop PMP

A

 Project management plan will be progressively elaborated until project closure
 Make sure to control all changes via the Perform Integrated Change Control Process
 Use the project charter to define the high-level project boundaries.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Perform Integrated Change Control

A

process of reviewing all change requests, approving changes and managing changes to deliverables, organizational process assets, project documents, and project management plan; and communicating decisions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Step 1b - Plan Scope Mangement

A

documents how the project scope will be defined, validated, and controlled. Includes to parts
 Product scope – features and functions that characterize a product, service, or result
 Project scope – sub of products, services, and results that will be provided by the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Step 1a - Develop PMP - Outputs

A

PMP - includes project BLs and subsidiary plans

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Project Baselines

A

include scope, schedule, and cost baselines

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Subsidiary Plans

A

include management plans for change, communications, configuration, cost, resource, process improvement, procurement, quality, requirements, risk, schedule, scope, and stakeholder

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Step 1b - Plan Scope Management - Outcomes

A

Scope MP and requirements MP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Scope MP

A

o Covers both product and project scope
o Provides guidance and direction on how the scope will be managed
o Documents how the project scope will be defined, monitored, controlled, and verified

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Requirements Management Plan

A

o Establishes the project’s product metrics
o Defines the requirements prioritization process
o Describes how requirements will be analyzed, documented, and managed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Step 1c - Plan Schedule Management

A

establishes the policies, procedures, and documentation of the project schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Project Schedule

A

Project schedule – presents linked activities with planned dates, durations, milestones, and resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Step 1c - Plan Schedule Management - Outputs

A

Schedule Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Schedule Management Plan

A

o Establishes the policies, procedures, and documentation for managing the schedule
o Provides guidance and direction on how the schedule will be managed
o Includes appropriate thresholds and management of schedule contingencies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Step 1d - Project Cost Management

A

establishes the policies, procedures, and documentation of the project costs. Output, cost management plan, provides guidance and direction on how project costs will be managed throughout the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Step 1d - Project Cost Management - Outputs

A

Cost Management Plan

17
Q

Cost Management Plan

A

o Establishes the policies, procedures, and documentation for managing project costs
o Provides guidance and direction on how project costs will be managed
o Addresses stakeholder requirements for managing costs (when and how to track them)

18
Q

Step 1e - Plan Risk Management

A

defines how to conduct risks management activities in the project

19
Q

Step 1e - Plan Risk Management - Outputs

A

Risk Management Plan

20
Q

Risk Management Plan

A

o Defines how to conduct risk management activities for a project
o Requires alignment of risk management activities to importance of the project
o Obtains agreement and support from stakeholders on how to deal with unforeseen events

21
Q

Step 1f - Plan Stakeholder Engagement

A

develops strategies for effectively engaging the stakeholders throughout the project.

22
Q

Step 1f - Plan Stakeholder Engagement - Outputs

A

Stakeholder engagement plan

23
Q

Stakeholder Engagement Plan

A

o Identifies people, groups, or organizations that could impact or be impacted by the project
o Analyzes and documents relevant information about each project stakeholder
o Highlights the importance of engaging stakeholders early in the project

24
Q

Five Levels of Stakeholder Engagement

A

o Unaware – unaware or project and potential impacts
o Resistant - aware and resistant to change
o Neutral – aware and neither supportive nor resistant
o Supportive – aware and supportive to change
o Leading – aware and actively engage in ensuring the project is a success