Planning a Project - Step 4 - Mod 102 Flashcards
Step 4: Schedule and Cost Baseline Steps
4a: Develop schedule
4b: Determine budget
Step 4a: Develop schedule
analyze sequences, durations, source requirements, and schedule constraints to create the project schedule model.
Schedule Network Analysis
Generates project schedule model. Uses analytical techniques to calculate early and late start and finish dates of uncompleted activities.
Analytical Techniques for Schedule Network Analysis
Critical path method
critical chain method
what-if analysis
resource optimization
Critical Path Method
Estimates minimum project duration and calculates scheduling flexibility on the logical network paths within the schedule model. Graphic of longest path through project.
Resource Optimization
- Resource leveling - adjusting start/end dates based on available resources. May impact original critical path.
- Resource smoothing - adjusting schedule w/i available free and total floats. Ensure completion date not impacted.
Schedule Compression Techniques
- Crashing - shorten schedule duration for least incremental cost by adding resources.
- Fast tracking - perform portions of sequential tasks in parallel.
Step 4a: Develop Schedule - Outputs
Schedule baseline, project schedule, schedule data, project calendars, change requests, PMP updates, project doc updates
Schedule Baseline
Docs approved version of schedule model that can be changed only through formal change control procedures. Serves as basis for comparison to actual results during variance calculations.
Project Schedule
Includes planned start and end dates for each activity. Presented in various formats.
Schedule Data
Contains schedule milestones, schedule activities, activity attributes, etc. Includes resource requirements by time period, alternative schedules, and scheduling contingency reserves.
Project Calendars
List working days and shifts for schedule activities.
Step 4b: Determine Budget
Aggregates estimated costs of activities into one authorized cost baseline. Performance can be monitored and controlled based on cost baseline.
Cost Aggregation
Aggregate work package estimates so they can be tracked, perhaps by mapping to control accounts, based on higher component levels of WBS. Rolled up for entire project.
Contingency Reserve
Budget to be included in cost baseline to cover known unknowns. Ex: rework - know needed but not how much.