3.3.4 Critical path analysis Flashcards

(3 cards)

1
Q

What is the critical path?

1

A
  • Series of activities which take the longest to complete
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is float time?

1

A
  • Any slack time available attached to an activity
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How do you calculate float time?

1

A
  • LFT (of activity) - duration (of activity) - EST (of activity)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly