4: Critical Path Analysis Flashcards

(4 cards)

1
Q

Precedence Table

A

A table, which shows which activities must be completed before others are started (a.k.a., dependence table)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Activity on Arc Network

A

The activities are represented by arcs and the completion of those activities, known as events, are shown as nodes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Dummy Activity

A

A dummy activity has no time or cost. Its sole purpose is to show dependencies between activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Every activity must be ____ in terms of its events. This requires that there can be ____ between any two events

A

Uniquely represented, at most one activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly