4: Earned Value Analysis Flashcards

(23 cards)

1
Q

What does EVA use to measure project performance? (3)

A

Planned cost

Actual cost

Earned value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is planned cost sometimes referred to as?

A

Budgeted cost of work scheduled (BCWS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is actual cost sometimes referred to as?

A

Actual cost of work performed (ACWP)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is earned value sometimes referred to as?

A

Budgeted cost of work performed (BCWP)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the formula for cost variance?

A

Earned Value (EV) - Actual Cost (AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the formula for schedule variance?

A

Earned Value (EV) - Planned Cost (PC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the formula for Cost Performance Index (CPI)

A

CPI = Earned Value / Actual Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the formula for Schedule Performance Index (SPI)

A

SPI = Earned Value / Planned Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How do you interpret CPI & SPI?

A

If the index values are less than 1.0, then the project is lagging behind, if the values are greater than 1.0, then the project is outperforming the plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the formula for forecasting the final cost?

A

Final Cost = Budgeted Cost / CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the formula for forecasting the final duration?

A

Final Duration = Original Duration / SPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the limitations to EVA? (3)

A
  • Assumes money is spent linearly and prorated based on time (not the case).
  • Costs in terms of money spent is accurate, however, judgement of task or project progress are subjective and therefore so are costs associated with the schedule.
  • Predictions for the future are based on extrapolations of what has occurred so far. Often what has happened does not represent accurately what will happen in the future.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What should you comment on when asked to give your views on the health of a project at a certain point? (5)

A
  • Stage of the project
  • Whether delay is critical or not
  • Whether under/over cost or time is insurmountable or not
  • Any CE’s or loss in profit due to over spend/time
  • If more data should be captured at this stage
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Describe in greater detail what should be considered when talking about the health of a project if the project is at an early stage.

A

At an early stage any overspend or overrun may be due to weather or unexpected conditions. The existing trend may not be representative of the future trend.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Describe in greater detail what should be considered when talking about the health of a project if the project is delayed.

A

Whether delay is to critical tasks or not. The SPI being negative does not necessarily mean the total project duration will be extended, as non-critical tasks may be delayed.

This is a weakness of SPI tracking.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Describe in greater detail what should be considered when talking about the health of a project if the project is over in terms of cost or time.

A

Whether or not the cost/time overspend is insurmountable and whether further close tracking would be necessary to see if the current trend is short lived.

17
Q

Describe in greater detail what should be considered when talking about the health of a project if the project continues to overspend or overrun.

A

If the overspend/overrun is significant, CE’s could be triggered resulting in a loss of profits. Therefore interventions should be considered to bring the project back on track.

18
Q

Describe in greater detail what should be considered when talking about the health of a project if there is not much tracking information relating to a project.

A

Further information should be gathered from the site relating to the status of a project to better inform decisions.

19
Q

How should you compare the performance or health of a project between two points in time?

A

Comment on the trends in cost and time performance and whether or not they have improved or worsened.

Additionally, comment on the % completion of the project (related to original duration) and whether or not a trend should have settled.

20
Q

Discuss the need to consider individual tasks on a project when analysing Earned Value data (SPI).

A
  • Tasks can be critical or non critical.
  • Critical tasks need to be monitored for SPI values < 1.0 as these result in delay.
  • Non-critical tasks do not result in delay.
  • As a result, the overall SPI can be < 1.0 but not actually delayed due to non-critical tasks skewering the figures.
21
Q

Discuss the need to consider individual tasks on a project when analysing Earned Value data (CPI).

A
  • If a non-critical task has completed with a CPI <1.0 then this will affect the overall CPI even if other tasks are completed on budget, therefore a value fore CPI <1.0 can be put into context if previous tasks are known to be over budget.
22
Q

Discuss the need to consider individual tasks on a project when analysing Earned Value data (continued).

How should SPI & CPI values be compared?

A

They should be compared relatively to their equivalent values from previous reports to look for improvement or worsening in project performance.

Tracking information from individual tasks should also be considered to for a balanced view of the projects health.

23
Q

When plotting a graph of cumulative cost vs time, how do you draw the following?

  • Planned cost
  • Actual cost
  • Earned value
A

Planned cost is one straight line from zero to the total planned cost at the original duration.

Both actual cost and earned value are a straight line from zero to the calculated values at the time given, followed by a dotted line to the predicted cost and finish date. Second time period calculation is added as a full line.