4 - Project Integration Management Flashcards
(31 cards)
What are the 6 Project Integration Management processes?
- 1 Develop Project Charter
- 2 Develop Project Management Plan
- 3 Direct and Manage Project Work
- 4 Monitor and Control Project Work
- 5 Perform Integrated Change Control
- 6 Close Project or Phase
04.0 Project Integration Management
What is the major project document that provides the project manager with most of their authority?
The Project Charter
04.1 Develop Project Charter
What is the major project document that provides the project manager with most of their authority?
The Project Charter
04.1 Develop Project Charter
What is the process for developing a document that formally authorizes a project or a phase and documenting initial requirements that satisfy the stakeholder needs and expectations?
Develop Project Charter
04.1 Develop Project Charter
What is the the formal document that describes the process and management plans used to execute, monitor, and control the project?
The Project Management Plan
04.2 Develop Project Management Plan
What is the process for documenting the actions necessary to define, prepare, integrate and coordinate all subsidiary plans.The primary source of information for how the project will be planned, executed, monitored and controlled and closed?
Develop Project Management Plan
04.2 Develop Project Management Plan
What is the document that formally authorizes a project or a phase and documenting initial requirements that satisfy the stakeholder’s needs and expectation?
The project charter
04.2.1.1 Project Charter
From what process does work performance data come from?
Direct and Manage Project Work
04.3 Direct and Manage Project Work
What three kinds of change requests are implementable in the Direct and Manage Project Work process?
Corrective
Preventative action
Defect repair
04.3 Direct and Manage Project Work
What is the process of performing the work defined in the project management plan to scheme the project’s activities?
Direct and Manage Project Work
04.3 Direct and Manage Project Work
What process produces the project or phase deliverables?
Direct and Manage Project Work
04.3 Direct and Manage Project Work
What is required for a decision that involves procuring goods, services, or resources?
A change request
04.3.1.2 Approved Change Requests
What written document can modify project policies or procedure, project scope, cost, or budget, schedule or quality?
A change request
04.3.1.2 Approved Change Requests
What are anything that can modify project policies or procedure, project scope, cost or budget, schedule or quality?
Change Requests
04.3.3.3 Change Requests
What includes collecting, measuring and distributing performance information and assessing measurements and trends to effect process improvements?
Monitor project work
04.4 Monitor and Control Project Work
What gives the project management team insight into the health of the project and identifies any areas that may require special attention?
Continuous monitoring
04.4 Monitor and Control Project Work
What includes determining corrective or preventive actions or replanning and following up on action plans to determine whether the actions taken resolved the performance issue?
Control project work
04.4 Monitor and Control Project Work
What is the process of tracking, reviewing, and regulating the process to meet the performance objectives defined in the project management plan?
Monitor and Control Project Work
04.4 Monitor and Control Project Work
What is an EAC?
Estimate at completion
04.4.1.3 Cost Forecasts
What is an ETC?
Estimate to completion
04.4.1.3 Cost Forecasts
What is anything that can modify project policies or procedure, project scope, cost or budget, schedule or quality (including modifications to procurement documentation)?
Change request
04.4.3.1 Change Requests
What are the physical or electronic illustrations of work performance information compelled in project documents, intended to generate decisions, actions, or awareness?
Work performance reports
04.4.3.2 Work Performance Reports
What is the difference between change control and configuration control?
Configuration control is focused on the specification of both the deliverables and the processes. Change control is focused on identifying, documenting, and approving or rejecting changes to the project documents, deliverables, or baselines.
04.5 Perform Integrated Change Control
What is the process of reviewing all change requests, approving changes, and managing changes to deliverables, organizational process assets, project documents, and the project management plan?
Perform Integrated Change Control
04.5 Perform Integrated Change Control