4.2 Flashcards

(19 cards)

1
Q

extension of the building drain

carries wastewater to the community sewer main or on - site sewage treatment system

also called house or building connection, or _______________

A

building sewer, sanitary sewer lateral

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

SLOPE REQUIREMENT OF BUILDING SEWER

Slopes range from ________ to________ in per foot.

______ in per foot slope is used only in large buildings with hundreds of fixtures. Proper slope prevents blockages and allows smooth flow.

A

1/16, 1/2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Is the primary pipe that conveys waste water from buildings to a treatment plant.

Typically, at least ___ inches (200 mm) in diameter for gravity-based systems

A

Sanitary Main Sewer, 8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

These are screw type fittings with removable caps for accessing the drainage system

A

cleanouts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

There are two types of cleanout

A

floor cleanouts and wall cleanouts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Placement for cleanout is no higher than _____ inches in vertical stacks

A

48

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Requirement of Cleanouts

The ________ of soil and waste stacks

Direction changes over ____

Junction of building drain and sewer ( __________ ft from foundation)

A

base

60 degrees

2-4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

CLEANOUT SPACING

They should not be no more than _____ ft apart, including the developed length of the cleanout pipe, in horizontal drainage lines of ___ in or less size.

A

50, 4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

CLEANOUT SPACING

Cleanouts should be no more than _____ ft apart, including the developed length of cleanout pipe, in horizontal drainage lines of sized over ____ to ____ in.

A

100, 4, 10

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

CLEANOUT SPACING

Cleanouts should be no more than _____ ft apart, including the developed length of cleanout pipe, in horizontal drainage lines exceeding sizes of ______

A

150, 10

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

CLEANOUT SIZE BASED ON PIPE DIAMETER

1.5 to 2 inches: _______ cleanout

2.5 to 3 inches: _______ cleanout

4 inches or larger: _______ inch cleanout

A

1.5
2.5
3.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

_____ are pipes that introduce sufficient air into the drainage system to reduce air turbulence and to release sewer gases to the outside

A

Vents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The primary pupose of venting is to protect the ______________.

A

trap seal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Without a vent, as water drains from a fixture, the moving wastewater tends to ______ water from the trap of another ficture as it falls through the drain pipes

A

siphon

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

TYPES OF VENTING MODELS

the ______________ method serves two fixtures located on the same floor; it is essentially an individual vent that serves no more than two traps or trapped fixtures

A

common vents, common venting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

TYPES OF VENTING MODELS

the _______________ method uses a single vent pipe to provide venting for all of the fixtures of one or two bathroom groups that are located on the same floor

the vent pipe for the ___________ typically serves as the vent for the other fixtures in the bathroom

A

wet vents, wet venting, lavatory

17
Q

TYPES OF VENTING MODELS

The ___________________ technique is defined as the installation of a vent pipe for every trapped fixture. It is the easiest method of ensuring the preservaion of a trap seal but the most costly because of the number of vent pipes requried in the venting system

A

individual vents

18
Q

A ______________ system is a horizontal venting pipe serving up to eight fixtures

Each fixture must be connected to a single horizontal drain in this technique

The vent connection is made between two upstream fixtures that is, those fixtures connected to the horizontal drain pipe that are the farthest awat from the vent stack

A

Circuit Vents

circuit venting

19
Q

TYPES OF VENTING METHODS