5 critical path method Flashcards

(13 cards)

1
Q

What are critical activities?

A

activities that must be completed on time if the entire project is to be completed on time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the float?

A

the amount of time that an activity can be delayed without delaying the project completion date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the critical path?

A

The sequence of activities which represent the longest total time required to complete the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a lag?

A

Delaying the following activity by an amount of time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a lead?

A

It means that an activity can be started earlier by a certain time period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the 3 steps of estimating activity duration?

A

1 find quantity of each item by doing a material take off from the drawings or from BoQ
2 find the resources required usually from experience
3 find the unit output of each resource- from
A experience or historical production records
B standards
C from work study - for repetitive processes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the earliest start/finish time?

A

The earliest time an activity can start/finish without affecting total project time or logic of the network

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the benefits of knowing the total float?

A

can move around non-critical activities and avoid over-allocation of people or equipment and can use resource levelling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Why might an activity be delayed?

A

1 the planning was incorrect and unrealistic- based on historical data no applicable or manufacturers outputs wrong
2 project not controlled - wrong resources or not enough or not motivated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

why might a non-critical activity become critical?

A
Many reasons might contribute to start times being affected:
• Previous activities late
• Resources not available or ready
• Site not ready
• Plans not complete
• Design not complete
• Permissions not ready
Reasons why the duration might be affected:
• Insufficient resources
• Inadequate resources
• Inadequate work areas
• Low supply of materials, designs, instructions etc
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

whats an issue when the full network is pretty critical?

A

1 need to sure each activity starts on time which needs the activity before to end on time and have done all prep work
2 risk to client to mitigate risk by changing project logic or ensuring adequate resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

how much of a lag is there usually between design and construction?

A

5 weeks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are issues with starting design and construction at the same time?

A

1 cost of design increase
2 final cost unknown before construction starts
3 design errors may not be checked before construction starts
4 construction sequence and timing to be altered leading to longer construction phase
5 contractor probs claim
6 risks for client
7 may have to re-negotiate contract
8 problems may result in project actually taking longer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly