1
Q

What are the cheapest type of poles

A

Wood

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are some non wood poles / structures

A

Aluminum concrete fiberglass and steel

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How do you determine the whole depth used for poles

A

Is determined by the pole type and soil

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Four classes of insulators for poles

A

Pin post suspension and strain

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are conductors for overhead lines made out of

A

Stranded or solid aluminum copper steel

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What’s another name for a down guy

A

Anchor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What do grounds protect

A

Equipment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When would you use underground electrical distribution systems

A

When ordinance codes require its use or overhead is unsightly

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Two types of underground electrical distribution systems

A

Direct buried and conduit encased in concrete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Where are underground electrical distribution systems used

A

Industrial areas residential and airfields

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Another name for a manhole

A

Splice chamber or cable vault

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a riser and what must it go into

A

Underground connection to overhead via riser goes into pothead

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

All Ferris hardware used in Pole line construction must be what

A

Standard line galvanized steel

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the pitch in a duct system underground

A

3 in per 100 ft for draining

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How to lay ducks

A

Is began midway between manholes and when ducks May flare out

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

When does interior wiring begin

A

Begins where distribution system service connects to building and extends throughout known as service entrance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

How often is the NEC published and who publishes it

A

Every three years by the NFPA

18
Q

What sub part houses electrical in the 29 CFR

19
Q

What should portable tools always be plugged into and should have what

A

Should have a third prong for a ground and should always be plugged into a GFCI

20
Q

What is the simplest wiring system

A

Two wire single phase 50 amps or less usually for lighting

21
Q

What is the most common wiring system

A

Three wire single phase
110/220 lighting and power
Heating and air conditioning

22
Q

What are the four types of wiring systems

A

2 wire single phase
3 wire single phase
3 wire 3 phase
4 wire 4 phase

23
Q

What are three types of service disconnects

A

Knife blade
fuse block
breaker which is the most common

24
Q

Are three types of nmsc

A

NM insulated conductor non-metallic jacket
Nmc insulated conductor non corrosive jacket
Nms signaling and data non-metallic

25
What's another name for Romex
Nmsc
26
How often should data be stamped on Romex
Every 24 in
27
What are octagonal boxes used for
Lighting outlets
28
What are round boxes used for
Overhead for lighting
29
What's the mounting height for wall switches
48 in
30
What's the mounting height for receptacle outlets
18 in
31
What's the mounting height for bed lights
72 in
32
What are the types of electrical tests
D Energizer operational test Operational test Continuity test High potential Resistance testing
33
Grounds to metallic water pipe system should be made on what side of meter
Streetside
34
The system neutral equipment grounds should be grounded on what side of the service disconnect
Should be grounded on the supply side
35
How is an electrical continuity test verified by QC
Visually
36
Which type of conduit is used for service entrance raceways
RMC
37
Are running threads allowed at couplings
No
38
Runs in wet areas should have at least how much space between conduit and wall
1/4 in
39
What color is the grounded conductor
White or gray
40
What color is the grounding conductor
Green or bear
41
Branch circuit conductors within 3 in of ballast shall be for use at what temperatures
No lower than 90° c
42
Panel boards must have what filled out
Directory