7 Themes Flashcards

1
Q

Areas of project management that must be addresses continuously throughout the project

A

Themes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the 7 Themes

A

Business Case, Organization, Quality, Plans, Risk, Change, Progress

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Covers the work to be done by a team. Can have multiple work packages.

A

Team Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Facilitates communication and control by defining the means of delivering the products

A

Plans

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Updated at the end of each stage to reflect actual progress and revised forecasts. Used by the Project Board.

A

Project Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Define how, when, for how much, by whom, and where the project will deliver its product

A

Plans

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Used for day-to-day management of the project. Used by the Project Manager.

A

Stage Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

New plan created to replace a Stage Plan or Project Plan to overcome an issue

A

Exception Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

To identify, assess, and control uncertainty and improve the ability of the project to be successful

A

Risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

An uncertain event which will have an effect on the project’s objectives

A

Risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

An event which has happened but wasn’t planned

A

Project Issue

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Risk realized with negative impact

A

Threat

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Risk realized with positive impact

A

Opportunity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Money that is used to fund any risk responses

A

Risk Budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Documentation of all risks in a project.

A

Risk Register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Used by the Project Manager to capture all risks

A

Risk Register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Threats and Opportunities are identified and described in terms of the…

A

cause, event, effect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Risk Management Procedure

A

Identify, Assess, Plan, Implement, Communicate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

To identify, assess, and control any potential and approved changes to the project baseline

A

Change

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Only for products that have been approved by those in authority and deemed fit for purpose

A

Baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Product has been given a version number

21
Q

resolution of project issue where Project Issue is logged in the issue register

22
Q

3 Types of Issues

A

Request for Change, Off-Specification, Problems/Concerns

23
Q

resolution of project issue where Issue Report is written by the Project Manager

24
resolution of project issue where Issue is recorded in the Daily Log
Informal
25
Documentation of how a project will manage issues and changes
Change Control Approach
26
Issue And Change Control Procedures
Capture, Examine, Propose, Decide, Implement
27
The project needs to be able to identify different versions of its product or products
Configuration Management
28
To establish mechanisms to monitor and compare actual achievements against those planned, provide a forecast for the project objectives and the project’s continued viability, and to control any unacceptable deviations
Progress
29
Two Types Of Progress Controls
Time-Driven, Event-driven
30
Progress Theme Documents
Work Package, Lessons log, Lessons report, End stage report, End project report
31
Documents/Controls to create baselines
project plan, stage plan, exception plan, work package
32
Documents/Controls to review the progress
issue register, risk register, daily log, quality register, project status account
33
Documents/Controls to capture and report lessons
lessons log, lessons report
34
Documents/Controls to report progress
checkpoint report, highlight report, end stage report, end project report
35
Define and implement the mechanisms in the project to determine if the products are “fit for purpose”
Quality
35
Measurable definitions of the attributes of a set of products that makes them acceptable to key stakeholders
Acceptance Criteria
36
contains a set of quality policies, procedures, and standards expected within the organization
Quality Management System (QMS)
37
Describes in measurable terms what the product must deliver to be satisfactory
Acceptance Criteria
38
Documents the method of quality control that will be used in the project
Quality Management Approach
39
Focused on how the processes work
Quality Assurance
40
Focused on verifying if a product is fit for purpose
Quality Control
41
Contain the details of the results of a test
Quality Record
42
Product is judged fit for purpose based on these
Quality Record
43
Printed form with a signature
Formal
44
Email stating approval
Informal
45
Record the formal acceptance of the final product by different stakeholders
Acceptance record
46
Acceptance methods should be determined before the project begins and be documented inside of the Quality Management Approach
Acceptance record
47
only for products that have been approved by those in authority and deemed fit for purpose
Baseline
48
Define the sequence of events in which products be developed
Project Flow Diagram
49
This change is called an outcome and the measurable improvements are called ___
Benefits