8. Project Scheduling and Planning Flashcards

(20 cards)

1
Q

What two key factors shape project structure?

A

Parallelity and precedence of activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is parallelity in project planning?

A

When multiple tasks can occur at the same time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is precedence in project planning?

A

When certain tasks must occur before others can begin.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the Critical Path?

A

The sequence of tasks that determines the minimum project duration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Why is the Critical Path important?

A

Any delay in its tasks delays the entire project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a Work Breakdown Structure (WBS)?

A

A logical subdivision of work assigning responsibility to individuals or teams.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What does a Gantt chart show?

A

Task sequence, timing, and dependencies based on the logic network.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are events in network analysis?

A

Points between activities used to branch the project timeline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the Forward Pass?

A

Calculates the earliest start times for each activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the Backward Pass?

A

Calculates the latest finish times for each activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How is float defined in project planning?

A

The flexibility in scheduling a task without delaying the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What does it mean if an activity has zero float?

A

It lies on the Critical Path and cannot be delayed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is an Activity-on-Node (AoN) network?

A

A diagram where nodes represent activities and show timing data.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What information is shown in an AoN module?

A

EAS, EAF, LAS, LAF, Duration, Float, and Activity description.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How is Earliest Activity Finish (EAF) calculated?

A

EAF = EAS + Duration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How is Latest Activity Start (LAS) calculated?

A

LAS = LAF - Duration.

17
Q

How is Float calculated?

A

Float = LAF - EAS - Duration.

18
Q

Why must project plans be regularly updated?

A

Projects change—activities slip, new tasks added—requiring updates.

19
Q

What does project float allow managers to do?

A

Reschedule non-critical tasks without delaying the whole project.

20
Q

What are the three lecture summary points?

A

Understand parallelity and precedence, know different networks, and understand float.