processes Flashcards

1
Q

What are the 7 processes?

A
Controlled start:
1. Starting up a project
2. Initiating a project
3. Directing a project
Controlled middle
4. Managing a stage boundary
5. Controlling a stage
6. Managing product delivery
Controlled end
7. Closing a product
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What actions are taken in the plan the initiation stage?

A
Set management controls
Review lessons log
Identify constraints
Review risk
Request Authorisation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the purpose of the directing a project stage?

A

To ensure that there is the authority to initiate the project, deliver project product and close the project
Ensure that direction and control are managed throughout the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What actions do the project board take to authorise the initiation of a project?

A

Review project brief
Confirm project definition, project approach and project management team
Review and approve the project product description- agreeing quality criteria and acceptance criteria
Verify business case
Review and approve stage plan
Inform stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What actions do the project board take to authorise the project?

A

Review and approve PID
- confirm project definition is accurate
- ensure lessons learned included
- Ensure sufficiency of quality management, risk management and change control
- approve membership of project management team
-ensure that project controls are adequate
- confirm achievability/viability of project plan review and approve product description
-review tolerances for the project obtain and commit resources necessary
- confirm the proposal to tailor
- verify the business case for viability
-

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What does the project board to before a project can progress to new stage?

A

Review and approve end stage report- to ascertain performance
Review the stage plan or exception plan to confirm validity and achievability
Make a decision by setting tolerances

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What must a project board to authorise to close a plan?

A

Review PID
Review end of project report
Review lessons learned
Verify handover of products
|Ensure that the post project benefits review covers performance of the products
Confirm the updated business case- comparing old with new
Review and issue project closure notification in accordance with comms plan

How well did you know this?