Admin Flashcards

(139 cards)

1
Q
  • 0POP01-ZQ-0022 Plant OPS Shift Routine*
    • *

Who approves the use of temporary logs?

A

Unit Supervisor
OR
Shift Manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  • 0PSP03-XC-0002 Initial Containment Inspection*
    • *

What is the purpose of 0PSP03-XC-0002 Initial Containment Inspection to Establish Integrity?

A
  • *Visual Inspection to ensure no loose debris present**
  • Could clog emergency sump strainers during LOCA*

Verify 48” containment purge valves closed

Verify 18” Supplementary purge valves open/closed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  • 0POP01-ZO-0006 Risk Management Actions*
    • *

What does front stop completion time and the back stop completion time mean?

A
  • Front Stop Completion Time:*
  • *LCO action times in conventional Tech Specs**
  • Back Stop Completion Time:*
  • *Ultimate LCO Action Times permitted by Risk Management Tech Specs (RMTS)**
  • Takes precedence over any Risk-Informed Completion Time calculated to be greater than 30 days*

Note:
Risk-Management Technical Specifications (RMTS): Plant-specific set of configuration-based Technical Specifications, based on a formally approved configuration risk management program and associated probabilistic risk assessment, designed to supplement previous conventional plant Technical Specifications.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  • 0PGP03-ZO-0041 Primary to Secondary Leakage*
    • *

What puts you in action level 3 for primary to secondary leakage?

A

Leakage from 1 S/G:

  • Condition 1:*
  • *≥ 75 gpd and ↑ 30 gpd/hr**
  • Not required be entered for spikes*
  • Condition 2:*
  • *≥ 75 gpd w/ loss of radiation monitors**
  • May terminate S/D if Rad monitors restored and < 75 gpd*
  • Condition 3:*
  • *> 150 gpd**
  • Must be entered for spikes*
  • Go to POP04-RC-0004 (SG Tube Leakage)
  • Condition 1 OR 2: ↓50% [1 hr] and Be in MODE 3 [Following 2 hrs]
  • Condition 3: Be in MODE 3 [6 hrs]
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  • 0POP03-ZG-0007 Plant Cooldown*
    • *

What must CV-0198 RMW Isolation be throttled to in MODE 5?

A

< 110 GPM

Note:
Limited to < 125 gpm per LCO 3.4.1.4.1 Cold S/D Loops Filled

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  • 0PGP03-ZA-0090 Work Process Program*
    • *

What is a high risk work activity?

A

Cause / Would Cause:

Unit loses all power generation capability

Reduce power ≥ 20%

Entry into LCO that requires S/D in ≤ 24 hrs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  • Conduct of Operations*
    • *

According to 10CFR50.72, Immediate Notification Requirements for Operating Nuclear Power Reactors, what situations require the NRC to be notified within 1 hour?

A

Emergency Class Declared

Deviation from Tech Specs

Safety Limit / T.S. Section 2.0 Exceeded

Unplanned Criticality

Radiological, Security, Environmental Events

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  • 0PGP03-ZF-0018 FPS Functional Requirements*
    • *

How often is it required to flush the Fire Protection Header?

A

Once per year

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  • 0PGP03-ZO-0046 RCS Leakage Monitoring*
    • *

What are the action levels for identified leakage?

A
  • Action Level 1:*
  • *≥ 3.0 gpm - < 5.0 gpm**
  • Action Level 2:*
  • *≥ 5.0 gpm**
  • Action Level 3:*
  • *Expected to exceed 10 gpm within 24 hrs**
  • LCO 3.4.6.2:*
  • *> 10.0 gpm**
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  • 0POP01-ZA-0001 Admin Guidelines*
    • *

When are valves in the AFWST pit required to be checked?

A

If security barrier is breached

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  • 0PGPO3-ZG-RMTS Risk-Managed Tech Spec Program*
    • *

When can risk management tech specs (CRMP) be applied?

A

MODES 1 - 2

Applies to extended LCO times.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  • 0PGP03-ZR-0051 Radiological Access / Work Controls*
    • *

What is the maximum yearly dose that a visitor that is not qualified for unescorted access to the RCA can obtain?

A
  • *75 mrem TEDE**
  • Working Visitor*
  • *10 mrem TEDE**
  • Non-Working Visitor*
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
  • 0PGP03-ZO-0012 Plant Systems Chemistry Control*
    • *

What actions shall be performed for a secondary chemistry action level 1?

A

Generate CR

Return parameter < Action Level 1 Value

Have 21 days until it becomes action Level 2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
  • 0PGP03-ZF-0001 Fire Protection Program*
    • *

While performing a hourly fire watch, what does 0PGP03-ZF-0001 (Fire Protection Program) specifically say is not allowed?

A

Using a cell phone / mp3 / gaming devices

  • Hourly fire watches may have other duties.
  • Continuous fire watches may have NO other duties.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
  • 0POP01-ZA-0014 License Operator Maintenance*
    • *

What is required to maintain an active license each quarter?

A

Seven (7) 8 hr shifts

Five (5) 12 hr shifts

Physicals are valid

  • *Enrolled in License Operator Requal Training**
  • License Operator Upgrade Training does NOT count*
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
  • 0PGP03-ZA-0514 Barrier Impairment*
    • *

Who must be specifically notified if a fire suppression system is OOS for > 48 hours?

A

STP’s Insurer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q
  • 0PGP03-ZO-0039 Configuration Management*
    • *

How often is the operator aid review performed?

A

Quarterly

Performed by issuing authority.

Note:
The continuing need for each Operator Aid does not need to be verified. (kinda strange)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q
  • 0PSP03-ZQ-0028 Operator Logs*
    • *

If AFD alarm has been inoperable for > 24 hrs, how often must AFD be logged?

A

Every 30 mins

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q
  • Conduct of Operations*
    • *

When can the STA stand watch as the Unit Supervisor, Primary RO, or Secondary RO?

A

US / RO must be available to re-relieve the STA if STA becomes activated

US / RO must be in same unit as STA

US / RO must perform shift turnover on same unit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q
  • 0PSP03-XC-0002A Containment Entry (Integrity Established)*
    • *

Who can perform all sections of this surveillance with exception of closing out the surveillance?

A

Non-Licensed work control SRO

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q
  • 0PSP03-XC-0002A Containment Entry (Integrity Established)*
    • *

If a Øa occurs while personnel are in containment, where should personnel evacuate?

A

Aux Air Lock

If Aux Air Lock unavailable, must reset Øa and open the PAL OCIV. Personnel can then exit via the PAL.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q
  • 0POP01-ZA-0001 Admin Guidelines*
    • *

When are the emergency operations lockers audited?

A

Quarterly

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q
  • 0POP08-FH-0009 Core Refueling*
    • *

Which radiation detectors should be functional for moving irradiated fuel?

A

RT-8010B

OR

RT-8050 OR RT-8051

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q
  • 0PGP03-ZO-0046 RCS Leakage Monitoring*
    • *

What must be done for each of the action levels?

A

Action Level 1:
Monitoring
Notifications

Action Level 2:
MAB Walkdowns
Monitoring
Notifications

Off Hours notification for Duty Ops Manager

Action Level 3:
MAB / RCB Walkdowns
Monitoring
HP Surveys / SG Samples
Notifications

Off Hours notification for everyone

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
* 0PGP03-ZO-0012 Plant Systems Chemistry Control* * * * What is the objective of **_secondary_** chemistry action level 1?
**Identify and correct the cause of an out-of-normal value without a power reduction**
26
* 0PSP03-XC-0002 Initial Containment Inspection* * * * What is the max occupancy of containment during normal operations?
* *72 people** * PAL _and_ AAL must be OPERABLE* ## Footnote * * * Normal Operations is MODE 1 - 4 (Doors normally closed) or MODE 5 with the doors closed
27
* 0PGP03-ZO-0046 RCS Leakage Monitoring* * * * What should be done if a RCS leakage calculation was performed the test results are suspect?
**Redo the Test** ## Footnote * * * If the 2nd test confirms the 1st test's results, then the action level entry time shall be the time of the **1st test's results.**
28
* 0PGP03-ZO-0046 RCS Leakage Monitoring* * * * Who performs the necessary notifications for 0PGP-ZO-0046 RCS Leakage Monitoring?
**Shift Manager**
29
* Probabilistic Risk Assessment* * * * What are the risk important operator actions?
**Manually start idle CRE HVAC train** **Start RHR train** **Start standby trains after loss of SSPS due to fire.** **Perform bleed and feed for loss of heat sink general transient event.** **Start PDP after LOOP**
30
* Probabilistic Risk Assessment* * * * What are the levels of PRA?
* _Level 1:_* * *Core Damage** * CDF / year* * _Level 2:_* * *Large Early Release of Radiation** * LERF / year* * _Level 3:_* * *Public Health Consequences** * Early and Late Casualties / year* * * * *Note: STP does not have level 3 b/c industry standards do not require it.*
31
* 0PSP03-XC-0002 Initial Containment Inspection* * * * Who can perform the initial containment inspection to establish integrity?
**SRO**
32
* Probabilistic Risk Assessment* * * * What is the level 1 PRA (Likely to cause core damage) top vulnerability?
**LOOP**
33
* WCG-0001 Work Screening and Processing* * * * Who approves high risk plans?
**Duty Plant Manager**
34
* 0PGP03-ZO-ECO1A ECO Instructions* * * * What requires double valve isolation?
* *Fluid systems \> 150 psig or \> 200 ˚F** * Hazardous System* ## Footnote **SFP Discharge Piping** **Systems containing radioactive fluids** **Systems containing chemically hazardous fluids**
35
* 0PGP03-ZO-0012 Plant Systems Chemistry Control* * * * What are your actions for **_primary_** chemistry action level 2?
**Generate CR** **Fix within 24 hrs** **If cannot be fixed within 24 hrs, S/D plant to cold S/D.** * * * If heating up plant and \> 250 ˚F and Cl, SO4, Fl \> 150 ppb for 24 hrs or O2 \> 100 ppb for 24 hrs then lower temperature \< 250 ˚F.
36
* 0PGP03-ZI-0007 Confined Space Entry Program* * * * What O2 % would be considered safe in regards to Confined Spaces?
**19.5% - 23.5%**
37
* 0PGP03-ZR-0050 Radiation Protection Program* * * * What must be done if a woman declares herself pregnant?
**Restrict RCA Access** **Issue new TLD** **Figure out dose since conception** **Woman, HR, and RP manager agree on new limit** **Limit is _\< 450 mrem/pregnancy_** **If _≥ 450 mrem_ since conception, then limit is _50 mrem for the rest of the pregnancy._** * * * *Note: NRC limit is 500 mrem/pregnancy*
38
* 0PGP03-ZO-ECO1A ECO Instructions* * * * Whose permission is required to use a check valve, relief valve, or a fail open valve as a tagout boundary?
**Unit Operations Manager** **Maintenance Division Manager / General Maintenance Supervisor** * * * Also need their approval if: * Working on system \> 140 ˚F without a system vent/drain. * Using a freeze seal * Working on flange adjacent to boundary valve * Any backseated valve used for single valve isolation
39
* 0PGP03-ZR-0051 Radiological Access / Work Controls* * * * When must an area be posted a radiation area, high radiation area, locked high radiation area, and a very high radiation area?
* _Radiation Area:_* * *≥ 5 mR/hr @ 30 cm → \< 100 mR/hr @ 30 cm** * _High Radiation Area:_* * *≥ 100 mR/hr @ 30 cm → \< 1000 mR/hr @ 30 cm** * _Locked High Radiation Area:_* * *≥ 1000 mR/hr @ 30 cm → \< 500 Rads/hr @ 1 m** * _Very High Radiation Area:_* * *≥ 500 Rads/hr @ 1 m**
40
* 0PGP03-ZO-0012 Plant Systems Chemistry Control* * * * What chemistry transients warrant a Rx trip?
**CP Fully bypassed _AND_ Condensate Pump Discharge cation conductivity verified \> 1.0 µS/cm** **SG Cation conductivity rising _AND_ SG Na, Cl, or SO4 \> 1000 ppb** **SG Cation conductivity \> 15 µS/cm _AND_ SG Na rising**
41
* 0PGP03-ZA-0010 Performing/Verifying Activities* * * * When is indirect IV used?
**ALARA (10 mRem)** **Safety Condition** **Emergency Conditions**
42
* 0PGP03-ZO-0012 Plant Systems Chemistry Control* * * * What are your actions for **_primary_** chemistry action level 1?
**Generate CR** **Bring back in spec within 7 days** **If cannot be fixed within 7 days, then more formal corrective actions will be performed.**
43
* 0POP01-ZQ-0022 Plant OPS Shift Routine* * * * How far back in the logs should the on-coming watchstanders review?
*_Whichever is less:_* **Since last watch _OR_ Prior 72 hrs**
44
* 0PGP03-ZR-0050 Radiation Protection Program* * * * What are the AAL radiation exposure limits?
* _TEDE:_* * *2 R/year** * _Shallow Dose:_* * *40 R/year** * _Lifetime:_* * *N Rem (N=Age)** * * * No AAL for eyes b/c TEDE covers your eyes.
45
* 0PGP03-ZO-0012 Plant Systems Chemistry Control* * * * What are your actions for **_primary_** chemistry action level 3?
**Generate a CR** **S/D immediately** **Lower temperature to \< 250 ˚F as rapidly as possible.**
46
* Conduct of Operations* * * * Who must be notified if a licensed operator fails a random breathalyzer test?
**Unit Operations Manager**
47
* 0PGP03-ZR-0050 Radiation Protection Program* * * * What are the NRC exposure limits?
* _TEDE:_* * *5 R/year** * _Eyes:_* * *15 R/year** * _Everything Else:_* * *50 R/year**
48
* 0PGP03-ZO-0041 Primary to Secondary Leakage* * * * What puts you in action level 1 for primary to secondary leakage?
* _Total Leak Rate (All 4 S/Gs):_* * *≥ 30 gpd** ## Footnote * * * Monitor CARS / BD / N-16 10 min trends every 15 mins
49
* 0PGP03-ZR-0051 Radiological Access / Work Controls* * * * What is a DAC (Derived Air Concentration)?
* *Person will exceed yearly limit (5 Rem) if he breathes in air 40 hrs a week for 50 weeks.** * (2.5 mrem/hr)*
50
* 0PGP03-ZO-ECO1A ECO Instructions* * * * What is a severity Level 1, Level 2, and Level 3 event?
* _Level 1:_* * *Discovered after work has started** * _Level 2:_* * *Discovered after ECO released** * _Level 3:_* * *Discovered before ECO released** * * * To classify for these events, the error discovered potentially or could potentially expose a worker to hazardous energy.
51
* 0PGP03-ZO-0003 Temporary Modifications* * * * Who is responsible for reviewing a temporary modification _PRIOR_ to the approving of work?
**SRO**
52
* 0PGP03-ZI-0007 Confined Space Entry Program* * * * How many controlled Entry and Exit points will be established for a Permit entry Space?
**1 Entry** **0 Exit**
53
* LCO 6.2.2 Shift Manning* * * * When must a RP technician be on site?
**When fuel is in the reactor**
54
* 0POP08-FH-0003 Fuel Transfer System* * * * Who authorizes the operation of the bypass switches on the RFM and FHM?
**Core Load Supervisor** ## Footnote * * * If Fuel is attached, he must have permission from reactor engineering and the SM.
55
* 0PGP03-ZA-0514 Barrier Impairment* * * * When does the requirements of 0PGP03-ZA-0514 not apply to a barrier impairment?
* _Fire/HVAC/Flooding/Security:\*\*_* * *Personnel stationed to immediately close the door** * _Flooding:\*\*_* * *Breached for \< 1 shift** * * * *Note: IVC Doors 002-005 are an exception due to HELBA*
56
* LOT 803.08 Respond to Off-Normal Conditions* * * * What is STP required to notify the owner QSE's of?
**Power reductions \> 25 MWe (Non-Peak)** **Power reductions \> 5 MWe (Peak)** **Unit / Plant Shutdowns** **Changes in scheduled power generation** * * * Notifications made by EMS website and then followed by a telephone call.
57
* 0PGP03-ZR-0051 Radiological Access / Work Controls* * * * How you determine the dose rate received from a point source and a line source?
* _Point Source:_* * *DR1(D1)2 = DR2(D2)2** * _Line Source:_* * *\< L/2 → DR1(D1) = DR2(D2)** * *\> L/2 → DR1(D1)2 = DR2(D2)**2 * (Point Source Equation)*
58
* 0PGP03-ZA-0114 Fatigue Rule* * * * What are the work hour limits?
**16 hrs in 24 hrs** **26 hrs in 48 hrs** **72 hrs in 7 days** * *10 hr break between days** * 8 hr break allowed for crew transition* **34 hr break in any 9 day calendar days** * * * These are rolling time periods * * * *Note: If a covered worker exceeds 54 hrs in 1 week, then a CR must be generated*
59
* 0PGP03-ZO-0039 Configuration Management* * * * Who coordinates the computer point off scan review?
**Engineering Duty Manager**
60
* 0POP01-ZA-0014 License Operator Maintenance* * * * What must be done in order to activate a license?
* *Stand 60 hrs of plant familiarization** * Only required for initial activation* **Stand 40 hrs of U/I** **Do a plant tour** * *Discussion with Plant Manager** * Command and Control* * * * *Note: If license was activated in the current quarter, then do not have to perform license maintenance for that quarter to stay active.*
61
* 0PSP03-ZQ-0028 Operator Logs* * * * If ECW supply temperature is \< 75 ˚F and temperature lowers by ≥ 4 ˚F between consecutive log readings, what must the operator do?
**Start all ECW pumps**
62
* 0PGP03-ZA-0101 Shutdown Risk Assessment* * * * Who performs the final approval of the shutdown risk assessment report?
**Plant General Manager**
63
* 0PGP03-ZO-0022 Post-Trip Review* * * * Who authorizes unit restart after a Category I, II, or III reactor trip?
**Plant Manager** ## Footnote * * * For a Category III Rx trip, he must review the post trip review report. * * * *Note: The STA prepares the report and the Plant Operations Review Committee (PORC) reviews the report.*
64
* 0POP01-ZO-0004 Extreme Cold Weather Guidelines* * * * When is cold weather guidelines implemented?
**≤ 40 ˚F for 24 hrs** **≤ 34 ˚F** * * * Also done if weather is expected to achieve these temperatures. * * * *Note: Extreme cold weather season is 10/31 - 3/31.*
65
* 0PGP03-ZF-0001 Fire Protection Program* * * * How often must a watch enter an area and still be considered a continuous fire watch?
**Every 15 minutes** * * * * Hourly fire watches may have other duties. * Continuous fire watches may have _NO_ other duties.
66
* 0POP01-ZA-0001 Admin Guidelines* * * * Following an outage, whose permission is needed to waive the initial valve lineup for a system?
**Unit's Operation Manager** * * * One of the following conditions must exist: * System has remained in service * No work performed on system and system not modified * If work performed, then process was controlled by ECO process * * * *Note: Valves in MAB pit rooms not required to be checked for initial valve lineups*
67
* LOT 802.34 Testing Req. Following Testing* * * * What are the equipment groupings per ASME Section XI?
* _Class 1:_* * *RCS Pressure Boundary** * _Class 2:_* * *Essential Safety Systems** * _Class 3:_* * *Essential Support Systems**
68
* 0PGP03-ZI-0007 Confined Space Entry Program* * * * What is the definition of a confined space?
**Large enough someone can enter** **Limited entry / exit points** **Not designed for continuous occupancy**
69
* 0PGP03-ZA-0112 Fatigue Rule Waivers* * * * When is a fatigue rule waiver authorized to be used?
**Mitigates or prevents condition adverse to nuclear safety** * * * * SM determines if waiver necessary * Plant General Manager approves waiver
70
* 0PGP03-ZO-0042 Reactivity Management* * * * A planned reactivity change must be reviewed by a SRO or Rx Engineering if the reactivity change exceeds what amount?
**± 100 pcm boron** **± 2% RTP** * * * Must also be approved by operations management
71
* 0PGP03-ZO-0012 Plant Systems Chemistry Control* * * * What is the objective of **_secondary_** chemistry action level 2?
**To minimize corrosion by operating at reduced power while corrective actions are taken.**
72
* 0PGP03-ZO-0041 Primary to Secondary Leakage* * * * What puts you in increased monitoring for primary to secondary leakage?
* _Total Leak Rate (All 4 S/Gs):_* * *≥ 5 gpd and \< 30 gpd** ## Footnote * * * Monitor CARS / BD / N-16 every 12 hrs * * * *Note: ≤ 10% rise in 24 hrs, return to normal monitoring.*
73
* 0PGP03-ZO-0003 Temporary Modifications* * * * What kind of temporary leak repairs are covered under 0POP03-ZO-0003 Temporary Modifications?
* _Requires:_* * *P&ID Change** * Valve kill / packing injection excluded* **Procedure Change** **CROE** **Training** * * * *Note: Normal temporary leak repairs are covered under 0PGP03-ZO-0009 Temporary Leak Repair*
74
* 0PGP03-ZA-0098 Station Housekeeping* * * * How many drains in the RCA may be taped up for your work area?
**≤ 1 drain at a time** ## Footnote * * * Do not leave unattended. * * * *Note: If done long term, do a T-MOD*
75
* 0PGP03-ZA-0090 Work Process Program* * * * Whose permission is required to start emergent work without an approved work package?
**Shift Manager** **Emergency Director**
76
* 0PGP03-ZO-0046 RCS Leakage Monitoring* * * * What are the action levels for unidentified leakage?
*_Absolute Leak Rate:_* * _Action Level 1:_* * *7 Day (Rolling Average) \> 0.1 gpm** * _Action Level 2:_* * *2 Days (Consecutive) \> 0.15 gpm** * _Action Level 3:_* * *1 Day \> 0.3 gpm** * _LCO 3.4.6.2:_* * *\> 1.0 gpm** * * * *_Baseline Deviation:_* * _Action Level 1:_* * *9 Days (Consecutive) \> Baseline Mean** * _Action Level 2:_* * *2 of last 3 Days \> Baseline Mean + 2 Standard Deviations** * _Action Level 3:_* * *1 Day \> Baseline Mean + 3 Standard Deviations**
77
* 0PGP03-ZO-0042 Reactivity Management* * * * What are the significant levels of Reactivity Management?
* _Level 1: (Highest)_* * *Significant Event** * Fundamental Organizational Breakdown* * _Level 2:_* * *Consequential Event** * Violation of Design Basis / License* * _Level 3:_* * *Unacceptable Event** * Violation of Process / Procedures* * _Level 4:_* * *Precursor** * _Level 5: (Lowest)_* * *Concern** * _Level 6:_* * *No Impact**
78
* 0PSP03-ZQ-0028 Operator Logs* * * * What must be done if the QPTR alarm is _NOT_ clear?
**Perform 0PSP10-NI-0002 every 12 hrs**
79
* WCG-0001 Work Screening and Processing* * * * Who approves medium risk plans?
**Duty Operations Manager**
80
* Conduct of Operations* * * * When performing a controlled shutdown for a LCO action statement, how long does it take to shutdown the plant?
* _100% - 20%:_* * *40%/hr (2 hrs)** * _20% - 3%:_* * *15%/hr (≈ 1 hr)** * _3% - MODE 3:_* * *Remaining time on LCO** * * * Should start shutting down as soon as you know you will not be able to fix the problem. * * * *Note: Adjusted to coincide with Tech Spec action times.*
81
* 0PGP03-ZO-0002 Conduct of Operators for Cranes* * * * When should outdoor cranes be secured?
* *Wind Speeds \> 30 mph** * Gust ≤ 35 mph allowed* ## Footnote * * * Personnel should not be hoisted in manbaskets if winds \> 15 mph.
82
* 0PGP03-ZO-0012 Plant Systems Chemistry Control* * * * What actions shall be performed for a **_secondary_** chemistry action level 2?
**Generate CR** **Take actions for safe and orderly reduction of power to ≤ 50% and achieve ≤ 50% power within 24 hours of entering Action Level 2.** **Have _300 hours_ until action becomes action level 3** * * * Power reduction may be terminated when no longer in action level 2 but may not raise power until out of action level 1.
83
* 0PGP03-ZA-0090 Work Process Program* * * * What classifies as emergency maintenance?
**Prevent / mitigate an accident** **Prevent unplanned release** **Protect human life** **Prevent significant plant damage** * * * * Authorized by SM * Does _NOT_ need a work package
84
* 0PGP03-ZO-0012 Plant Systems Chemistry Control* * * * What is the objective of **_secondary_** chemistry action level 3?
**To correct a condition that can result in rapid corrosion of a secondary side component during continued operation.** ## Footnote * * * Plant shutdown will minimize impurity ingress and limit exposure of steam generator, turbine, and other secondary materials to corrosive solutions.
85
* Conduct of Operations* * * * What is the minimum shift complement?
**SM (2)** **US (2)** **STA (1)** **RO (4)** **ENS Communicator (1)** **Safe S/D Plant Operators (4)** * *Fire Brigade Members (5)** * 1 Qualified Fire Brigade Leader* **State / County Communicator (1)**
86
* 0PAP01-ZA-0102 Plant Procedures* * * * Who's approval is required to perform a field change to a procedure?
**Any SRO**
87
* 0PGP03-ZA-0098 Station Housekeeping* * * * In order to eat or drink in a house keeping area, what must the area be zoned as?
**Zone V** ## Footnote * * * Zone IV is the same except no eating or drinking allowed in Zone IV. (MAB, FHB, ECW, etc.) * * * *Note: Zone I is the highest degree of cleanliness (Clean room)*
88
* 0PGP03-ZE-0004 Plant Surveillance Program* * * * What surveillances does the plant surveillance program procedure govern?
**Tech Specs** **TRM** **ODCM**
89
* 0PSP03-XC-0002A Containment Entry (Integrity Established)* * * * Who determines what tools, test equipment, or other material may be left inside the RCB once personnel exit containment with integrity established?
**SM / Unit Supervisor**
90
* LCO 6.2.2 Shift Manning* * * * How long can minimum crew staffing be violated?
**2 hrs**
91
* 0PGP03-ZA-0514 Barrier Impairment* * * * Who is responsible for verifying Form 1 of 0PGP03-ZA-0514 is completed accurately?
* *Fire Marshal** * FPS Section* * *Rapid Response Team Supervisor** * HVAC Section* * *Mechanical/Civil Supervisor** * Flood Barrier Section* * *Security Force Supervisor** * Security Section*
92
* 0POP08-FH-0009 Core Refueling* * * * When conducting refueling operations, who must be on communications?
**Refueling Machine** **Fuel Handling Machine** **FHB Console** **RCB Console** **Control Room Operator** **Rx Engineer**
93
* 0PGP03-ZO-0039 Configuration Management* * * * If a computer point was taken off scan, removed from alarm checking, or a substitute value entered, the computer point must be tracked in the points off scan log. When must the review be performed?
**36 hrs** ## Footnote * * * If another point is available, then review can be extended to **_72 hrs._**
94
* 0PGP03-ZI-0007 Confined Space Entry Program* * * * Who is responsible for maintaining respirator protection equipment for use in Permit Entry Spaces?
**Health Physics**
95
* 0PGP03-ZO-0012 Plant Systems Chemistry Control* * * * If a chemistry waiver is desired and the waiver is for a control parameter, whose concurrence must be obtained?
**Plant Manager** ## Footnote * * * Chemistry Manager is required for all waivers.
96
* Conduct of Operations* * * * When is the STA activated?
**Emergency Plan Entry** **EOPs entered** **SM / STA discretion**
97
* 0PGP03-ZA-0114 Fatigue Rule* * * * What is the minimum amount of time per week that operations personnel must have off?
* _Normally: (12 hr shifts)_* * *2.5 days/week** * _Outage:_* * *3 days / 15 day period** * * * Outage fatigue rules can only apply for 60 days.
98
* 0POP01-ZO-0006 Risk Management Actions* * * * What does the risk assessment calculator assess?
**Incremental Conditional Core Damage Probability** **Weekly Trip Risk Probability** * * * Used in MODES 1 and 2
99
* 0PGP03-ZF-0011 STPEGS Fire Brigade* * * * How often are Fire Brigade meetings conducted?
**4 per year**
100
* 0PGP03-ZR-0050 Radiation Protection Program* * * * If your AAL TEDE is extended past 2 R/year, whose approval is required?
*_2 R - 3 R:_* **RP Manager Individual's Manager** *_3 R - 4 R:_* **(Same as 2 R - 3 R) Plant Manager** *_4 R - 5 R:_* **(Same as 3 R - 4 R) Senior Management Team Member** * * * *Note: Powerpoint had 1.5 R/year as the limit but ZR-50 has 2R/year.*
101
* Conduct of Operations* * * * How long does the STA have to get to the control room once notified?
**10 mins**
102
* Probabilistic Risk Assessment* * * * What are the level 1 PRA external events (Likely to cause core damage)?
**Fire** **Flooding** **Tornado** **Seismic**
103
* 0POP01-ZO-0006 Risk Management Actions* * * * Who approves risk management actions?
**Plant General Manager** ## Footnote * * * Shift Manager in charge of implementing actions.
104
* 0PGP03-ZA-0098 Station Housekeeping* * * * Who approves exemptions for station housekeeping?
**Plant Manager**
105
* 0PSP03-ZQ-0028 Operator Logs* * * * What leakage rate would force the you to declare the containment sump level / flow monitoring system inoperable?
**\> 4.7 gpm**
106
* Survey Maps* * * * What do the following symbols mean on a survey map?
* _Circle:_* * *Smear** * _Triangle:_* * *Air Sample** * _Rhombus:_* * *Large area wipe** * * * * Number by itself is a general area reading (\<2.5) * \*120/3.5 means 120 on contact and 3.5 @ 30 cm
107
* 0PGP03-ZO-ECO1A ECO Instructions* * * * Who can waive the IV on an ECO restoration?
* *Issuing Authority** * Unit Operations Division Manager (Designee) must concur* ## Footnote * * * IV waived for significant radiation exposure, personnel safety reduction, or for emergency conditions. * * * *Note: IV on locked components cannot be waived*
108
* LCO 6.2.2 Shift Manning* * * * How many plant operators are required for shift manning to satisfy tech specs?
* _MODES 1 -4:_* * *2 / Unit** * _At all Times:_* * *3 Total** * At least 1 / Unit*
109
* 0POP01-ZO-0011 Operability, Functionality, and Reportability Guidance* * * * If a prompt determination is performed for a \< 72 hr S/D action statement, when should the prompt determination be completed by?
**≤ 24 hrs** ## Footnote * * * Normally prompt determinations are completed within 1 week. * * * *Note: For all CRs where the SM/US calls a component OPERABLE but degraded, a prompt determination shall be requested.*
110
* 0PGP03-ZO-0041 Primary to Secondary Leakage* * * * What puts you in action level 2 for primary to secondary leakage?
* _Leakage from 1 S/G:_* * *75 gpd - 150 gpd** * * * Monitor CARS / BD / N-16 10 min trends every 15 mins If \> 75 gpm for ≥ 1 hr: * Go to POP04-RC-0004 (SG Tube Leakage) * Be in MODE 3 [24 hrs] * Time starts when ≥ 75 gpd first indicated
111
* Probabilistic Risk Assessment* * * * What is most likely to cause an early large area release? (Level 2 PRA)
**Induced SGTR**
112
* 0POP01-ZO-0002 345 kV Switchyard* * * * Who can be designated as a STP designated qualified operators?
**Unit Supervisor** **SM** **Unit Operations Manager**
113
* 0PGP03-ZR-0050 Radiation Protection Program* * * * Who has the authority to lift a Health Physics Stop Work Order?
**Plant Manager** **RP Manager**
114
* 0POP01-ZA-0001 Admin Guidelines* * * * When is the locked component deviation log audited?
**Monthly** ## Footnote * * * * Note:* * Shift Manger/Unit Supervisor responsible for ensuring log updated when locked valve positioned.*
115
* 0PGP03-ZO-0012 Plant Systems Chemistry Control* * * * What do the different **_primary_** chemistry action levels mean?
* _Action Level 1:_* * *Long term reliability could be affected** * _Action Level 2:_* * *Significant damage could be done in a very short time** * _Action Level 3:_* * *Inadvisable to keep operating the plant**
116
* 0POP01-ZQ-0022 Plant OPS Shift Routine* * * * Who ensures appropriate entries are made in the control room logbook?
**Unit Supervisor**
117
* Conduct of Operations* * * * While checking the position of a normally locked closed valve, the valve operator cannot be moved due to the locking device. What is the proper method for checking the position of this valve?
**Remove the locking device** **Check valve in closed direction**
118
* Admin Procedures* * * * What are the Admin and Tech Spec / TRM Heatup and Cooldown limits for the RCS and PZR?
***_Heatup Rates:_*** *_RCS:_* **Admin: 50 ˚F/hr Tech Spec: 100 ˚F/hr** *_PZR:_* **Admin: 100 ˚F/hr TRM: 100 ˚F/hr** * * * ***_Cooldown Rates:_*** *_RCS:_* **Admin: 80 ˚F/hr Tech Spec: 100 ˚F/hr** *_PZR:_* **Admin: 160 ˚F/hr TRM: 200 ˚F/hr**
119
* 0PGP03-ZR-0044 Contamination Control Program* * * * What contamination levels are present in a contaminated area and a high contamination area?
* _Contaminated Area:_* * *≥ 1,000 dpm/100cm2 beta/gamma** **≥ 20 dpm/100cm2 alpha** * _High Contamination Area:_* * *≥ 100,000 dpm/100cm2 beta/gamma** **≥ 1,000 dpm/100cm2 alpha**
120
* 0PGP03-ZO-0041 Primary to Secondary Leakage* * * * When are the N-16 monitors available to detect primary-to-secondary leakage?
**\>25% power** * * * * Between 20% and 25% the N-16 monitors are unreliable. * \< 20% the N-16 monitors do not function.
121
* 0PGP03-ZO-0042 Reactivity Management* * * * What is the Plant manager, Operations Manager, Unit Operations Manager, and SM responsible for?
* _Plant Manager:_* * *Ensures reactivity management philosophy** * _Operations Manager:_* * *Implements reactivity management program** * _Unit Operations Manager:_* * *Determines event classification** * _Shift Manager:_* * *Daily application**
122
* 0PGPO3-ZG-RMTS Risk-Managed Tech Spec Program* * * * Can the CRMP be applied if all trains required by the LCO are inoperable?
**Yes** **≥ 1 train must be PRA Functional**
123
* 0PGP03-ZA-0010 Performing/Verifying Activities* * * * Who may authorize adding, omitting, or changing a step in a procedure?
**Shift Manager / Unit Supervisor** * * * Changes are allowed as long as: * Does _NOT_ affect personnel / equipment safety * Documented in log book / procedure * CR generated * * * *Note: Cannot be used to fix broken procedure.*
124
* 0PGP03-ZF-0011 STPEGS Fire Brigade* * * * Who is responsible for providing necessary keys for the Fire Brigade?
**Security Force Supervisor**
125
* 0POP01-ZO-0004 Extreme Cold Weather Guidelines* * * * Who is responsible for implementing the extreme cold weather program?
**Shift Manger**
126
* 0PGP03-ZF-0018 FPS Functional Requirements* * * * A fire door has a self-closing feature. Would the door be considered functional if the self-closing feature was broken but the door would still latch closed?
**No** ## Footnote * * * Both the self-closing feature and the latch must be working.
127
* 0PGP03-ZO-0012 Plant Systems Chemistry Control* * * * What actions shall be performed for a **_secondary_** chemistry action level 3?
**Generate a CR** * *Take Plant to ≤ 5% power as quickly as safe plant operation permits.** * Has to be done regardless of the duration into Action Level 3* * * * * Note:* * If due to Hydrazine / FW O2 \< 2, have 8 hrs to fix and then must go to cold shutdown.*
128
* 0ERP01-ZV-IN06 Radiological Exposure Guidelines* * * * While the E-Plan is activated, what situations allow personnel to exceed 5 REM TEDE?
* _5 REM to 10 REM:_* * *Protection of Property** **Lifesaving Activities** **Protecting Large Populations** * * * * _10 REM to 25 REM:_* * *Lifesaving Activities** **Protecting Large Populations** * * * * _\> 25 REM:_* * *Lifesaving Activities** **Protecting Large Populations** **PERSONNEL HAVE TO VOLUNTEER** * * * *Note: All personnel can receive 5 REM while in E-Plan without permission.*
129
* 0PGP03-ZO-0046 RCS Leakage Monitoring* * * * When can RCS Leakage action levels be exited?
**Enhanced Unidentified Leak Rate Program indicates exit from the Action Level** **_Entry into Mode 5_** **Directed the procedure.**
130
* 0PGP03-ZE-0004 Plant Surveillance Program* * * * What must be done if a SR is interrupted and that interruption extends past shift change?
**Suspend the SR**
131
* 0PGP03-ZR-0050 Radiation Protection Program* * * * If your total extended lifetime TEDE is extended past the limit, whose approval is required?
*_\< 1 R Past Limit:_* **RP Manager Dept Manager Plant Manager You** *_\> 1 R Past Limit:_* **(Same as \< 1 R Past Limit) Senior Management Team Member**
132
* 0PGP04-ZE-0313 Maintenance Rule Program* * * * What satisfies the maintenance rule program during different MODES of operation?
* _MODES 1 -4:_* * *CRMP** * _≤ MODE 5:_* * *Shutdown Risk Assessment**
133
* 0POP08-FH-0009 Core Refueling* * * * What is the only form of communication that meets the requirements 0POP08-FH-0009 when moving fuel?
**A dedicated headset** ## Footnote * * * If the dedicated headset were to fail, even if other forms of communication exist, movement of fuel must be stopped.
134
* Conduct of Operations* * * * When must you notify the FAA that the aviation lights are not working?
**Lights not working for \> 30 mins**
135
* 0PGP03-ZF-0011 STPEGS Fire Brigade* * * * How many Fire Drills must a Fire Brigade Member participate in?
**2 per year**
136
* 0PGP03-ZO-0022 Post-Trip Review* * * * What are the different categories of a reactor trip?
* _Category 1:_* * *Cause of Trip Identified** **Safety-Related Equipment functioned properly** * * * * _Category 2:_* * *Cause of Trip Identified** **Safety-Related Equipment did _NOT_ Function properly** **Cause of Malfunction identified** * * * * _Category 3:_* * *Cause of Trip unknown** **Safety-Related Equipment did _NOT_ Function properly** **Cause of Malfunction _NOT_ identified**
137
* 0PGP03-ZO-0046 RCS Leakage Monitoring* * * * When is Form 1 (Leakage Log) entered?
* *Any time unidentified leakage changes by 0.2 gpm** * Increasing or Decreasing*
138
* 0PGP03-ZA-0090 Work Process Program* * * * What is a work activity risk (WAR)?
**Impact on operations during MODES 1 - 4** **Primary focus is interruption of power generation** **Includes impact of removing / returning equipment.** * * * Work Control / Work week manager develops WAR.
139
* Conduct of Operations* * * * When can a SRO perform control board manipulations?
**When directed by SM during POP04s, POP05s, POP09s, or SAMGs** **Taking Action to save a life** **Designated as RO in logbook**