ADMIN Flashcards
(101 cards)
Who orders start-up or shutdown the reactor for planned maintenance or refueling?
“10AC-MGR-001-0
Vice-President”
Who may order a shutdown during an emergency or when continued operation would jeopardize the plant or personnel safety?
10AC-MGR-001-0
Anyone with an operator license
What actions are required for a RAS?
“31GO-OPS-006-0
-A RAS DOES NOT have to be initiated for a REQUIRED ACTION (Except For Corrective Maintenance) that WILL NOT be in effect at the end of the shift.
• SM must be notified of inoperability
• Entry and exit as well as actions taken logged in MCR log
• SM notified when the Condition/Required Action is terminated
- SS signs SS SIGN/TSA ACTIVE block of Section 2 of the RAS, signifying the sheet is active.
- SM reviews and signs SM SIGN block of Section 2 indicating concurrence with the RAS
- Alternating between LCO Conditions, in order to allow indefinite continued operation while not meeting the LCO, is NOT allowed.”
What are the conditions for normal entry into the drywell?
“31GO-OPS-005-0
Any containment entry after the initial entry where reactor power is less than or equal to 20% RTP and containment atmospheric conditions are acceptable as per subsection 6.3.”
What are the conditions for abnormal entry into the drywell?
“31GO-OPS-005-0
Any containment entry made with reactor power greater than 20% RTP OR the containment atmospheric conditions unknown or NOT acceptable as per subsection 6.3.”
What are the pre-entry conditions for entry into the drywell?
31GO-OPS-005-0 6.3 Entry Conditions:
The following conditions must be met before an initial containment entry is permitted:
- Oxygen ≥ 19.5% AND < 23.5% by volume
- Hydrogen ≤ 0.57% by volume
- Carbon Monoxide ≤ 50 ppm
- Airborne Radioactivity ≤ Hi-Hi Alarm setpoint on Fission Product Monitors OR Samples by RP, Indicate Entry Into the Drywell is Permitted
- Reactor Power ≤ 20 percent RTP
- Drywell Pressure > 0.0 PSIG and < 0.65 PSIG
What are the conditions for initial entry into the drywell?
“31GO-OPS-005-0
The first containment entry made subsequent to containment being de-inerted or drywell pneumatics on nitrogen supply, when reactor power is less than or equal to 20% RTP.
4.1.1 At least two persons are required when initial or abnormal primary containment entries are made; one of whom must be a qualified Radiation Protection Technician. A Radiation Protection Technician may NOT be required IF Radiation Protection Technicians are posted in primary containment as during a refueling outage.
4.1.2 A two-person backup team must be available for an Initial OR Abnormal Entry. This team will be equipped as specified in this procedure.
4.3.1 Approval must be obtained from the Shift Supervisor before an initial entry is made into the primary containment.
4.3.2 IF the conditions of 6.3 cannot be met, the entry will be considered abnormal AND approval for the abnormal entry must be obtained from the Plant Manager.
6.6 IF performing Initial OR Abnormal entry, THEN perform NMP-AD-006, Infrequently Performed Test and Evolutions.
7.1.1.3 After the Shift Supervisor has been notified by Radiation Protection AND Chemistry, that two successive samples of the containment atmosphere meet pre-entry conditions, the Shift Supervisor may approve initial containment entry.”
Who has the responsibility to manually align, start, or initiate any auto-start system that failed to auto-start?
NMP-OS-007-001
Nuclear Plant Operators (NPOs) have the responsibility to manually align, start, or initiate any automatically actuated system, equipment, signal, or function that has indication of a start failure or incomplete initiation so that it will perform its intended function unless operation would create a condition that would not mitigate a transient.
NMP-OS-007-001
WHEN a system or component has been placed in manual due to a transient caused by an automatic control malfunction, SM permission is required prior to returning the system or component to automatic control following stabilization from the transient and correction of the malfunction.”
Who can operate controls at the remote shutdown panel?
NMP-OS-007-001
4. During normal operation (generally non-emergency) controls at the Remote Shutdown Panel (RSDP) or Hot Shutdown Panels (HSP) which cause actual equipment operations shall be operated under the direct supervision or direction of a Licensed Operator currently assigned to the crew; the below exceptions apply:
-Controls which operate oil pumps may be operated by unlicensed personnel with SS approval.
-Controls which relate only to indication may be operated by unlicensed personnel with SS approval.
-Tags may be placed on equipment in the RSDP/HSP by unlicensed personnel
provided no manipulation of controls which can cause equipment operation will occur.
When is two-handed operation allowed?
NMP-OS-007-001
Control switches are operated single handed, except as specified below, or as specified in Attachment 2
Control switches are operated single handed (i.e., simultaneous manipulation) of two separate switches or controls will be avoided. This is to support use of STAR and focusing on the single piece of equipment being manipulated, except as specified below:
1. The Shift Supervisor may allow specific instances of Two-Handed Operation. This is appropriate WHEN specifically directed/permitted by procedure or required by design.
a. Two handed operation allowance is generally limited to conditions:
(1) where two switches must be operated to initiate a response, and do not require sequential operation.
(2) where two switches have similar function with a need or desire for close coordination between the two operations to mitigate the
significance/consequence of a transient or potential transient
b. Unless specified in Attachment 2, the use of Two-Handed Operation should be specifically requested, and granted on a case by case bases, such allowance should not be routine.
Hatch Specific Attachment 2 list
- Energizing emergency 4KV bus while holding the 86 lockout closed
- Control Rod withdrawal using rod movement and RONOR switches
- Operation of RHR injection valves emergency operating procedures
- Tripping of HPCI
What actions are required for lockout relays or electrical issues?
NMP-OS-007-001
Response to a Breaker that has Tripped or Malfunctioned
The SS may waive the following requirements based on plant conditions or specific event circumstances.
• Components that have tripped due to potential overload or failure condition should not be restarted until the cause is investigated
• Do not reset trip flags, thermal overloads or hand switch amber lights until directed by appropriate personnel after investigation has started.
• An investigation shall be performed by qualified personnel to determine the cause of the trip prior to further attempts to close the breaker or start associated equipment.
a. Mechanical relay flags (for example, on 4160V breaker cubicle doors) occasionally drop out due to vibrations. IF a breaker is clearly not tripped and no associated alarms have occurred, the system operator may attempt to reset the flag. The relay flag provides indication only. IF a relay has actuated it should have resulted in an alarm or breaker trip
What are the outage safety assessment risk colors and how often should attachment 1 be completed?
“31GO-OPS-024-0
- Attachment 1 is performed once per shift, (to be completed as early in the shift as possible) AND when a system status change occurs.
- Yellow (low risk) - This condition represents reduced but adequate safety function redundancy. This condition requires Shift Outage Manager approval. The operating shift shall be notified of the reduction in redundancy, no other contingency actions or plans are required.
- Orange (moderate risk) - This condition represents a reduction in the capability to perform the safety function with little or no redundancy remaining. Steps shall be taken to minimize time spent in this condition. Planned entry into this condition requires detailed compensatory actions and contingency plans, and approval by the Outages and Scheduling Manager and the Plant Manager. If unplanned entry into orange condition occurs immediate actions will be taken to restore Yellow status.
- Red (high risk) - This condition represents a potential loss of one or more Key Safety Functions. Planned entry into this condition is NOT allowed. If unplanned entry into Red condition occurs immediate actions will be taken to restore Yellow status.
- The respective Unit Operator at the Controls (OATC) is responsible for completing the Outage Safety Assessment.”
What are important details of SUV-019?
“34GO-SUV-019-2
-P: Corrected Level = indicated level -15 IF the reactor is < 212F, AND indicator is on scale.
-Surveillances required once / 12 hr shift must be taken between 0800 and 1100 Eastern Time on day shift AND between 2000 and 2300 night shift.
-Surveillances required once/8 hours must be taken WITHIN 1.0 hours of the designated time.
-The paper copy of the procedure will be used:
oIF the computer will NOT perform required calculations.
oIF the output from the computer is obviously incorrect AND represents a serious degradation of the computer system operation.
oIF the version number specified in the computerized round for the procedure is incorrect AND the Software Support Personnel can NOT resolve the problem.
oIF a pre-planned Mode change for the Unit will take place during the shift
AND ‘U1/U2 MODE CHANGE SUV-019 12 hour’ tour is unavailable. “
When do you notify chemistry during startup?
“34GO-OPS-001-2
4.4.9 - Obtain confirmation from the on-shift Lab Foreman that reactor water,
condensate AND feedwater are acceptable for power operation
per the ‘Sampling AND Analysis During Power Operation’, subsection,
of 64CH-SAM-023-0.
4.12.19.d Notify the on shift Lab Foreman of reactor criticality.
34GO-OPS-005-2
2.2.14 Anytime reactor thermal power is increased OR decreased by > 15% RTP in one hour, the Chemistry lab shall be notified to perform the sampling requirements of Unit 2 Tech Specs.
34GO-OPS-013-2
4. Notify the Shift Manager and Shift Supervisor any time Reactor power is increased OR decreased by greater than 15% of rated thermal power in one hour. This is to ensure Chemistry Lab is notified to perform sampling requirements of Hatch ODCM Table 3-3, note C.”
During startup what SRM readings are needed for TS SR 3.3.1.2.4?
“34GO-OPS-001-2
4.1.13 Record the readings on all operable SRM channels below, confirming counts are >3 cps per TS SR 3.3.1.2.4.”
What signatures are required prior to going to START & HOT STBY?
“34GO-OPS-001-2
4.2.2 Obtain Shift Supervisor’s AND Shift Manager’s signatures confirming all prerequisites necessary to put the Reactor Mode switch in START & HOT STBY for the purpose of plant startup have been met.”
What are the steps to place the reactor mode switch in Run?
“34GO-OPS-001-2
- 2.15 Perform Rod Drift Alarm Test while withdrawing a Group 1 (RWM Step 1) control rod
- 2.19.4 Notify the on shift Lab Foreman of reactor criticality.
4.2.21 Continue to pull rods to establish a heatup rate < 100°F/hr.
(Control rod withdrawal must be performed in a manner that will avoid steady periods of ≤50 seconds on the SRM period meters.)
4.2.22 WHEN SRM/IRM overlap has been confirmed, withdraw SRM detectors as required to maintain an indicated level between 200 CPS AND 7 x 10^4 CPS.
- 2.23 As reactor power goes up, range up the IRM Range Switches to maintain IRM indication on recorders between 10 AND 80 on the 0-125 scale.
- 2.24 WHEN all operable IRM channels are above range 3 AND PRIOR to reaching range 7, fully withdraw all operable SRM detectors.
- 2.25 Confirm there is overlap between IRM ranges 6 AND 7, by completing Attachment 9.
- 2.26 To continue power ascension with any inoperable IRMs, obtain Shift Supervisor approval.
- 4.3 Perform alternate power level check by confirming that one main turbine bypass valve, is between 50% AND 100% OPEN.
- 4.5 Place the Reactor Mode switch in RUN
- 4.2 Initiate a Required Action Sheet to confirm the containment oxygen concentration is < 4% by volume WITHIN 72 hours after entering Mode 2 per TS 3.6.3.2.
- 4.30 At approximately 15% reactor power, adjust the APRMs per 34SV-SUV-021-0, APRM Adjustment To Core Thermal Power, such that each APRM reading is between 0% AND 2% greater than the power value calculated by a reactor heat balance.”
When is a rod drift test performed?
“34GO-OPS-001-2
ROD DRIFT ALARM TEST
1.0 During withdrawal of a Group 1 control rod while the Rod Movement Control switch is in the OUT NOTCH position, perform the following:
1.1 Take Rod Drift Alarm Test Switch to TEST AND confirm the following:
1.1.1 Full Core Display red ROD DRIFT light for the control rod being tested ILLUMINATES.
1.1.2 Annunciator ROD DRIFT, ALARMS.”
How often do you perform heatup AND pressurization checks?
34GO-OPS-001-2
HEAT-UP PRESSURIZATION CHECK
1.0 During heatup AND pressurization, perform the following at least once every 15 minutes
How do you perform IRM 6/7 overlap check?
34GO-OPS-001-2
IRM OVERLAP CHECK
1.4 Confirm that Column 3 (RANGE 7 READING) = Column 4 (RANGE 6 READING / 10) + 2 (on the 0-40 scale).
How do you perform IRM alternate power Check?
34GO-OPS-001-2
RM ALTERNATE POWER CHECK
Record the IRM readings below AND estimate reactor power using one of the following formulas:
For IRM Ranges 7 AND 8: % Power = (IRM Reading) x (.0212)
For IRM Ranges 9 AND 10: % Power = (IRM Reading) x (.212)
What are the indications of criticality?
“34GO-OPS-001-2
The following are indications of criticality:
oSRM period meters indicate a stable, positive period AND
oSRM levels are going up WITHOUT requiring additional control rod withdrawal.
When below the Point of Adding Heat, SUBCRITICAL is defined as - Multiple SRM/IRM readings continuously lowering without rod insertions”
During Startup, when do you start CBP or CP pumps?
34GO-OPS-001-2 (1)
- Start condensate pumps as necessary to maintain booster pump suction pressure above the trip setpoint of 34(15) PSIG.
- The third Condensate Pump should be started between 70 - 80% RTP, to prevent the pumps from experiencing pump cavitation AND damaging the pumps impeller AND seals.
- Start condensate booster pumps as necessary to maintain Reactor Feed Pump suction pressure above the trip setpoint of 207 (145) psig.
34GO-OPS-005-2
-Prior to exceeding 2558 MWth evaluate the condensate system operation, AND start the third CBP.
What actions are required if rod movement is suspended for an extended period of time?
“34GO-OPS-001-2
- IF ROD MOVEMENT IS TO BE SUSPENDED FOR AN EXTENDED PERIOD OF TIME, THE CONTROL RODS WILL NORMALLY BE INSERTED TO THE SUBCRITICAL HOLD POINT. THE SUBCRITICAL HOLD POINT IS INSERTING ALL RODS TO NOTCH 00 EXCEPT FOR GROUP 1 (RWM STEP 1) WHICH WILL BE LEFT AT NOTCH 48.
- IF SRM/IRM OVERLAP IS NOT CONFIRMED, ROD WITHDRAWAL WILL BE HALTED. TECH SPECS WILL BE ADDRESSED TO DETERMINE IF ANY IRMS DECLARED INOPERABLE DUE TO FAILURE TO DEMONSTRATE OVERLAP WILL ALLOW STARTUP TO CONTINUE.”