Advanced Flashcards

(76 cards)

1
Q

What legislation covers working at height?

A

Work at Height Regulations 2005 (WAH 2005)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which document states the safe way to work on a scaffold contract?

A

Method Statement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the safe working load of a Class B right-angle coupler?

A

6.1 kN

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the minimum recommended loading on a slung scaffold?

A

1.5 kN/m²

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the safety factor for a right-angle coupler?

A

1.65

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the Safe Working Load (SWL) of a class B sleeve?

A

5.5 kN

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the maximum distance a tie tube can be positioned from the node point?

A

300 mm

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the minimum recommended loading on a stair tower?

A

1.5 kN over 200 mm²

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the minimum size for a sole board?

A

220 × 450 × 35 mm

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the current technical guidance for tube and fitting scaffolds?

A

TG20

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A box tie can be considered to provide a pull capacity of?

A

12.2 kN

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How often should ledger bracing occur in an independent scaffold?

A

Each end and every other bay

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How often should sway bracing occur in a TG20 scaffold?

A

Every 6th bay

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the maximum width of a TG20 light duty fan?

A

6 boards (1350 mm)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the industry guidelines for the use of safety harnesses?

A

When there is a risk of falling and collective protection is not in place

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Which document must you have when erecting a prefabricated (aluminium) mobile tower?

A

Instruction Manual

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

At what height should guardrails and toe boards be introduced on a scaffold?

A

Every lift (when risk of fall)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Who is responsible for fixing the concrete pads & wall plates on raking shores?

A

Principal Contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is the minimum height for the top guard-rail?

A

950 mm

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

The distance between the toe board and guard-rail should not exceed?

A

470 mm

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is the minimum height for a toe board?

A

150 mm

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Above what slope should an engineer be consulted to check sloping foundations?

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is the recommended maximum spacing of structural transoms on the top chord of a TG20 bridge?

A

1.2 m

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What is the minimum recommended loading for a pedestrian ramp?

A

4.0 kN/m²

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
What is the general rule for tie positioning on basic scaffolds?
Every 4 m vertically and horizontally (16 m² pattern)
26
What is the maximum angle for spurs on a truss-out scaffold?
35°
27
How far should ladders project above the working platform?
1 m
28
What is the minimum length of a sole board for double standards?
900 mm (450mm per standard)
29
How should sole boards on roof scaffolds be positioned?
90° to rafters
30
Minimum opening size for internal ladder access?
450 mm × 600 mm
31
How should hanging tubes on drop scaffolds be supported?
Check doubles
32
Who is responsible for foundations when erecting falsework scaffolds?
Principal Contractor
33
At what rate should the tension chord of a beam be tied?
2.4 m
34
How many supplementary couplers for a swivel?
2
35
Minimum slope of a fan?
20°
36
Safety factor for a cantilever scaffold?
3:1
37
Max slope of a ramp?
1:4
38
Where should check fittings be placed on a hanger?
Above the top and below the bottom connection
39
What is the smallest base dimension for a tower scaffold?
1.2 m × 1.2 m
40
Scaffold towers erected externally should not exceed their smallest base dimension by more than?
3 times
41
First option when planning scaffold access?
Stairs or existing structures
42
Minimum depth of beams for TG20 3-bay bridge?
305 mm
43
Max transom spacing for standard scaffold board?
1.2 m
44
How to secure ring-type gin wheels?
Check fittings either side
45
Min number of working boards for 5-board scaffold?
3
46
Safe working load of a Class B swivel coupler?
6.1 kN
47
Percentage of ties that must be proof tested?
5%
48
Ideal raking shore chord location?
500 mm above floor
49
Legislation for hazardous materials?
COSHH
50
How many working platforms on general-purpose scaffold?
2
51
Max vertical load for a pair of girder clamps?
30 kN
52
Max service gap without guardrail?
225 mm
53
Max standard spacing on class 3 birdcage scaffold?
2.5 m
54
Top fall protection method in WAH hierarchy?
Guardrail
55
Min head clearance under pavement gantry?
2.44 m
56
How often should scaffolds be inspected?
Every 7 days or after bad weather
57
Ideal angle for rakers?
45°
58
Where is the node point on scaffold?
Where standard and ledger meet
59
Should the single guardrail stay in place?
Yes
60
Where should plan braces be placed on beamed bridge?
Top third
61
Who is responsible for safety on site?
Everyone
62
Standard spacing for light duty scaffold?
2 m
63
Standard spacing for general-purpose scaffold?
2 m
64
Max load on general-purpose scaffold?
2.0 kN/m²
65
Standard spacing for heavy-duty scaffold?
1.8 m
66
Max first lift height for independent scaffold?
2.7 m
67
Does a scaffolder need to be clipped on when installing ledgers & transoms within a single guardrail on a fully boarded lift?
No – unless kneeling below guardrail
68
How often to check safety harness?
Before each use and every 6 months by competent person
69
Max transom spacing for class 4 scaffold?
0.9 m
70
Ideal angle for staircase stringers?
30–35°
71
Clip-on required when raising boards?
Yes
72
Scaffold towers erected internally should not exceed their smallest base dimension by more than?
3.5 times
73
Expansion anchor ties only into?
Concrete
74
Max extension on adjustable jacks (dead shore)?
300 mm
75
What percentage of ties to ledger-braced standards?
50%
76
Current standard for scaffolds with tube & fittings?
BS EN 12811