AOA and AON Flashcards

1
Q

In order to calculate the LST/LS and LFT/LF in an AON, you use the [x] pass.

A

Backward

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

In an AON, EFT stands for [x]

A

Earliest Finish Time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

In an AON, EST stands for [x]

A

Earliest Start Time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When sorting out a project by identifying all of the tasks, you should engage in a [x] planning process.

A

Hierarchical

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When sorting out a project by identifying all of the tasks, you should begin with the project’s [x].

A

Objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

[x] is a series of connected activities (or intermediate events) between any two events in a network.

A

Path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

In an AON, LFT stands for [x]

A

Latest Finish Time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

AON stands for [x]

A

Activity on Node

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

In order to calculate the EST/ES and EFT/EF in an AON, you use the [x] pass.

A

Forward

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

[x] is a task or set of tasks required by the project which use resources and time.

A

Activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Do you want there to be Negative Float?

A

No

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Free slack is the slack an activity has before it delays the [x]

A

Next Activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

[x] is the set of activities on a path from the project’s start event to its finish event that, if delayed, will delay the completion date of the project.

A

Critical Path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When sorting out a project by identifying all of the tasks, the lowest level task is typically [x] to [y] days in duration.

A

2, 14

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Do you want there to be more than one critical path?

A

No

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

[x] is a diagram of nodes connected by directional arcs that defines the project and illustrates the relationships of all activities.

17
Q

In an AON, LST stands for [x]

A

Latest Start time

18
Q

What is the Duration of a Milestone?

19
Q

When sorting out a project by identifying all of the tasks, you generally use [x] to [y] activities per level

20
Q

[x] are identifiable and noteworthy events marking significant progress on the project.

A

Milestones

21
Q

AOA stands for?

A

Activity on Arrow

22
Q

Can there be negative float

23
Q

Can a critical path run over a dummy task?

24
Q

Can a critical path change?

25
[x] is the time required to complete all activities on the critical path.
Critical Time
26
How much float does the critical path have?
0
27
Total slack is the slack an activity has before it delays the [x].
Project
28
[x] is an identifiable state resulting from the completion of one or more activities. Before it can be achieved or realized, all its predecessor activities must be completed.
Event
29
Can there be more than one critical path?
Yes