NDE - Maximum Length of crack or incomplete fusion allowed on a new weld

A

0”

B31.3 Tbl 341.3.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

Design -Mill Tolerance For rolled and welded pipe

A
  • 0.010”

574: 4.1.13

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Flanges - Typical flange face finish

A

125 - 250 micro inch

B16.5: 6.4.5.3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Flanges - When mating flanges, the maximum amount of un parallel allowed (per diameter of flange in feet)

A

1/16” per foot

B31.3: 335.1.c.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Flanges - Max offset four bolt-holes for mating flanges

A

1/8”

B31.1: 335.1.c.3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Welding - Maximum allowed size of open discontinuity in a bend test

A

1/8”

Sect IX: QW-163

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Preheat Zone - Distance from toe of weld

A

1”

B31.3: 330.1.4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

PWHT Zone - Distance from toe of weld

A

1”

B31.3: 331.2.6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

NDE- Minimum distance beyond the area to be examined to clean a part when performing a MT examination

A

1”

Sect V: T-741.1.b

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

NDE- Minimum distance beyond the area to be examined to clean a part when performing a PT examination

A

1”

Sect V: T-642.b

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Repairs - Minimum radius of insert patch

A

1”

570: 8.1.4.2.c

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

NDE- Max diameter of CML exam point for lines less than 10 NPS

A

2”

570: 3.1.20

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

NDE- Max diameter of CML exam point for lines greater than 10 NPS

A

3”

570: 3.1.20

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

NDE- Minimum length of spot RT

A

6”

B31.3: 344.5.2.c

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Welding - Minimum length to RT/UT when qualifying a welder with test coupon or 1st production weld

A

6”

IX: QW- 302.2/ 304.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Welding- Minimum length of RT when qualifying a welding operator with RT RT/UT a test coupon.

A

6”

IX: QW-302.2

16
Q

Corrosion- soil-to air area - Distance from Interface

A

6”

570: 3.1.87

17
Q

Corrosion- Distance to dig when inspecting for soil - to - air corrosion

A

6”-12”

574: 7.4.5

18
Q

NDE- Distance Of eye to part to count as a visual exam

A

6”-24”

577: 9.3.1.e

19
Q

Corrosion- soil-to-air area distance and soil from interface

A

12”

570: 3.1.87

20
Q

NDE - Minimum upstream limit of intensive examination of injection point circuit

A

12”

570: 5.5.9

21
Q

PWHT-Minimum overlap for a PWHT when using multiple heats

A

12”

B31.3: 331.2.5

22
Q

Welding- Minimum length RT/UT when Qualifying a welding operator on first production weld

A

3”

IX: QW-305.1

23
Q

Underground - Minimum length of Buried pipe to expose when excavating for inspection

A

6-8’

570: 9.3.6

24
Q

Repairs- Maximum size of fillet weld patch on pipe

A

1/2” diameter

570: fig c.2

25
Q

Circuits- Minimum upstream limit of injection point circuit

A

Greater of 12” or 3 “ inch diameter

570: 5.5.9

26
Q

NDE- Minimum downstream limit intensive examination of injection point circuit

A

10 diameters

570: 5.5.9

27
Q

Circuits- Minimum downstream limit of injection point circuit

A

Lesser of:

1st direction change +/- 25’ OR 2nd direction change