Design - Mill tolerance of seamless pipe

A
  • 12.5%

574: 4.1.1.3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

NDE - Limits of RT film density of weld as compared to IQI

A

-15 to 30 %

V: T-282.2.a.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Pipe Class - % of H2S in process to classify as Class 1 pipe

A

<,- (less than or equal to) 3%

570: 6.3.4.2.c

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

NDE - % of welds RT when fabricating normal service pipe

A

5%

b31.3: 341.4.1.b.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

NDE- % of welds to VT when fabricating normal service pipe

A

5%

b31.3: 341.4.1.a.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

NDE- % of welds to Brinnell after PWHT in furnace (if BHN are required)

A

10%

b31.3: 331.1.7.a

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

NDE - overlap with a UT scan, % of transducer diameter

A

10%

574: 10.2.1.4.3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

AI- Amount of time inspector must be involved in inspection activities - required to maintain API-570 certification

A

20%

570: A.3.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Metals- amount of nickel required for a material to be considered a nickel alloy

A

> 30%

571: 3.1.15

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

NDE - % of welds to Brinnell after local PWHT (if BHN is reqd)

A

100%

b31.3: 331.1.7.a

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

NDE - % of visual & RT required when fabricating severe cyclic pipe

A

100 %

b31.3: 341.4.3.a.1/b

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Testing - Pneumatic test pressure , % of design pressure

A

110%

b31.3: 345.5.4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Testing - leak test pressure of underground pipe, % of operating pressure

A

110%

570: 9.3.7

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

PRV- Maximum set pressure for thermal relief valves, % of design pressure

A

120%

b31.3 : 322.6.3.b.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Document Owner/User must have that is following API-570

A

QA/Repair Manual

570: 4.3.1.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Document required for each piping system

A

Inspection Plan

570: 4.3.1.2

16
Q

Document required when changes are made to hardware or process

A

MOC

570: 4.3.1.2

17
Q

Document required when Owner audits inspection program

A

Tracking system

570: 5.13

18
Q

Document required of examiners employer

A

Certification Records

570: 4.3.5.3

19
Q

Document required for each PRD Repair Organization

A

QC Manual

570: 6.7.2

20
Q

Document required concerning personnel at PRD Repair Organization

A

Training Program

570: 6.7.2

21
Q

Records maintain by Repair Organization and available to the Inspector

A

WPS’s & WPQ’s

570: 8.2.2

22
Q

Another record that the Owner/User must maintain

A

Inspection ISO’s

23
Q

Another record that the Owner/User must maintain

A

Track repairs Recommendations

570: 7.8

24
Q

Another record that the Owner/User must maintain

A

External Inspections

570: 7.8

25
Q

Another record that the Owner/User must maintain

A

Track Temporary Repairs

570: 7.9

26
Q

Another Record that the Owner/User must maintain

A

Deferrals