Asphalt Spread Rate Flashcards

1
Q

_ x Gmm x __

What is the formula for TARGET/THEORETICAL spread rate?

A

t x Gmm x 43.3

t = thickness

Gmm = from mix design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

lb & sq yd

How do you calculate the ACTUAL spread rate?

A

Asphalt Weight Used (lb)

____________________________

Area Covered (sq yd)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How do you change LF to SY?

A

LF x Width of Lane = sq ft

sq ft / 9 = SY

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the target % difference between the TARGET spread rate and the ACTUAL spread rate?

A

5%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly