ASTM C 31 - STRENGTH SPECIMEN CASTING Flashcards

1
Q

_ inches greater — than _ times the depth of the beam in it’s tested position.

In beam molds -> what is the REQUIRED LENGTH?

A

Length at LEAST:

2 inches later — than 3 times the depth of the beam in its tested postion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

5/8 inch AND _/8 inch +- 1/_ inch

What are the 2 types (diameter measurement) of tamping rods when making strength specimens?

A

5/8 inch AND 3/8 inch

+-

1/16 inch

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What rod diameter do you use for a cylinder diameter that is 6 inches or greater?

A

5/8 inch

+-

1/16 inch

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What rod diameter do you use for a cylinder diameter that is less than 6 inches?

A

3/8 inch

+-

1/16 inch

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

2_ inches?

What is the MAXIMUM length for both tamping rods?

A

24 inches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

_ inches longer than the d…

What is the required length for BOTH tamping rods?

A

4 inches longer than the depth of the mold

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

9___ vibrations/minute

What is the minimum frequency (vibrations/minute) for an internal vibrator?

(150 Hz)

A

9000 vibrations/minute

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

1/_

“Internal vibrator with an outside diameter no more than __ the diameter or width of the specimen.”

A

1/4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

_ inches longer than the d…

How many inches longer must the vibrator be than the length of the specimen?

A

At least 3 inches longer than the depth of the container

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How often must the internal vibrator be checked by a tachometer for verification?

A

Every 2 years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

1.__ lbs +- 0.5 lbs

What is the required mallet weight for a 1/2 ft3 measure and smaller?

A

1.25 lbs

+-

0.5 lbs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

2.__ lbs +- 0.5 lbs

What is the required mallet weight for a larger than 1/2 ft3 measure?

A

2.25 lbs

+-

0.5 lbs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

6 x _ inches – _ x 8 inches

What are the 2 types of cylinder molds (_x_) used when casting strength specimens?

A

1) 6 x 12 inches
2) 4 x 8 inches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Nominal size of aggregate exceeds _ inches

When must you wet sieve a concrete sample when casting strength specimens?

A

Nominal max size of aggregate exceeds 2 inches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Do you cast beam molds in a horizontal position? (Y/N)

A

YES

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

“Beam length at least (1) _ inches greater than (2) _ times the depth of the beam in its tested position”

A

1) 2 inches
2) 3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

4 in x _ in

What is the minimum beam dimension for a nominal aggregate size of 1 inches or less?

A

4 in x 4 in

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

6 in x _ in

What is the minimum beam dimension for a nominal aggregate size of 1 inch - 2 inches?

A

6 in x 6 in

19
Q

ROD OR VIBRATE OR BOTH

SLUMP > 3 IN

20
Q

ROD OR VIBRATE OR BOTH

SLUMP BETWEEN 1-3 INCHES

21
Q

ROD OR VIBRATE OR BOTH

SLUMP <1 INCH

22
Q

How many lifts do you make with a cylinder diameter of 4 inches (4x8)?

METHOD OF CONSOLIDATION – RODDING ONLY

23
Q

How many lifts do you make with a cylinder diameter of 6 inches (6x12)?

METHOD OF CONSOLIDATION – RODDING ONLY

24
Q

How many lifts do you make with a cylinder diameter of 9 inches?

25
# \_5 Times How many rod strokes do you do for cylinders with a diameter of 4 inches (4x8) AND 6 inches (6x12)? **_METHOD OF CONSOLIDATION -- RODDING ONLY_**
25 Times
26
How many rod strokes do you complete with a cylinder diameter of 9 inches? **_METHOD OF CONSOLIDATION -- RODDING ONLY_**
50 rod strokes
27
How many lifts do you use with cylinders of **4, 6, AND 9 inch diameters**? **_METHOD OF CONSOLIDATION -- VIBRATING ONLY_**
2 Lifts
28
How many insertions of the internal vibrator do you preform with a **4 inch cylinder diameter**? ## Footnote **PER LAYER**
1 insertion per layer
29
How many insertions of the internal vibrator do you preform with a **6 inch cylinder diameter**? ## Footnote **PER LAYER**
2 insertions per layer
30
How many insertions of the internal vibrator do you preform with a **9 inch cylinder diameter**? ## Footnote **PER LAYER**
4 insertions per layer
31
# \_5 Minutes "Place cylinders in initial curing location within __ minutes of casting."
15 Minutes
32
# 1 time for each _ in^2 of surface area How many times do you rod **EACH** layer for a **BEAM MOLD**?
1 time for each 2 in2 of surface area
33
# A = L x \_ What is the formula for **AREA OF A BEAM MOLD**
Area = Length x Width
34
# Rods = Area / \_ What is the formula for the number of RODS to be preformed on a beam speciman?
Rods = Area / 2
35
How many layers do you do **WHEN CASTING A BEAM MOLD**? **_METHOD OF CONSOLIDATION -- VIBRATING_**
1 Layer
36
# Every _ inches How often do you insert the vibrator down the centerline of the **BEAM speciman**?
Every 6 inches
37
# Up to \_8 hours What is the **MAXIMUM** amount of time the **INITIAL** curing phase can last?
Up to 48 hours
38
# Within 1/\_ inch per foot What is the **leveling requirments** for the inital curing location?
Within 1/4 inch per foot
39
What are the initial curing TEMPERATURE REQUIRMENTS for specimans **less than 6,000 PSI**?
60-80 degrees F
40
What are the initial curing TEMPERATURE REQUIRMENTS for specimans **6,000 PSI and greater**?
68 degrees F - 78 degrees F
41
# \_ hours after final set What is the earliest amount of time a speciman can be moved in? (Hours)
8 hours after final set
42
What is the maximum allowable transport time for cylinders?
4 hours
43
# Within \_0 minutes How long does FINAL curing take AFTER MOLD REMOVAL?
Within 30 minutes
44
# 7\_.5 Degrees F +- \_.5 Degrees F What is the required TEMPERATURE for the CURING ROOMS AND SOAK TANKS at the lab?
73.5 Degrees F +- 3.5 Degrees F