1
Q

What is the NRSWA?

A

New Roads and Street Works Act 1991 - Covers Utility Diversions in the C1-C9 process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

You state you used a decision making matrix to evaluate options for resolving the issue in you case study, which methodology used?

A

MCDA - Multi-Criteria Decision Analysis

e.g. considering Time, Cost, Quality, Risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

In your recommended solution in your case study, what procurement risks were introduced by using client’s contractor?

A

Risks include scope creep, failure to meet utility operator standards, and interface delays.

There’s also potential for unclear liability in case of failure.

Mitigations include a detailed interface schedule, formal agreement on specifications, and utility engineer sign-off procedures.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly