Case Study Related Questions Flashcards
(53 cards)
What building services are being upgraded?
HVAC systems to BREEAM Excellent standards
LED lighting with smart controls (CIBSE Code)
Fire safety systems (BS 5839/9999)
Electrical distribution (18th Edition)
Building management systems
Accessibility upgrades (BS 8300)
What is shell and refurbished floor?
Shell: Basic envelope with core services, no fit-out
Refurbished floor: Stripped back with new services distribution, ceilings, basic M&E ready for tenant fit-out
What should you be doing during design progression?
Monthly cost monitoring and reporting
Track design changes and cost impacts
Maintain risk registers
Regular design team liaison
Continuous benchmarking
Client briefings on cost implications
What is an agreement-for-lease?
Legally binding contract where tenant commits to take lease once conditions met, landlord commits to grant lease on completion. Made project cancellation impossible - had to find cost solutions.
What is an appraisal?
Financial feasibility study comparing costs vs projected income/value to determine viability and return on investment.
How did you rationalize steel beam interventions?
Reduced from 63nr to 12 locations per floor by:
Optimizing services routes with M&E team
Using surface-mounted services where possible
Re-examining actual vs assumed loading
Combining multiple small interventions
Saved £1.25m
What plant did you retain?
Air handling units: £180k saving
Chiller components: £220k saving
Electrical switchgear: £150k saving
Lift systems: £100k saving
BMS infrastructure: £80k saving
Total: £730k of £1.25m saving
How did you identify service charge items?
Worked with Building Manager on:
Planned maintenance items (BMU scheduled for replacement)
Common area improvements benefiting all tenants
Compliance works required regardless
Reviewed lease responsibilities and service charge budgets
What is a cost plan?
Detailed construction cost estimate aligned with design stage, providing elemental breakdown, cost targets, risk assessment, and cash flow projections.
How do you prepare a cost plan?
Gather information (drawings, specs, site data)
Measure using NRM1 rules
Price using databases and market rates
Assess risks and contingencies
Report in standard format
Information requirements source?
RICS NRM1 Appendix A, RIBA Plan of Work, RICS guidance notes, client EIR for BIM projects.
Two design efficiency ratios:
Wall to Floor Ratio: External wall area ÷ GFA (target 0.35-0.45)
Net to Gross Ratio: Net area ÷ GIA (target 80-85%)
Calculate inflation:
Tender: Base Cost × (1 + rate)^years to tender
Construction: Cost × (1 + rate)^(0.5 × construction period)
What is TPI?
Tender Price Index - BCIS measure of tender price changes over time, reflecting market conditions and cost trends.
Design development risk:
Cost increases from design refinement, specification enhancement, coordination issues. Typically 5-10%, reducing as design matures.
NEC stands for
New Engineering Contract
Contract suites:
JCT, NEC, FIDIC
Office estimate requirements:
Brief, site information, program, market conditions, benchmarking data, statutory requirements.
JCT standard forms
standard d and b intermediate trad minor
D&B key principles
Single point responsibility, Employer’s Requirements, Contractor’s Proposals, design warranty, risk transfer, lump sum pricing.
QS role in JCT D&B
not named however apointed to do Cost ER, evaluate proposals, advise on terms
Post-contract: Valuations, variations, financial monitoring, final account
D&B valuation process:
Contractor applies for payment
Assess work done
Value including variations
Deduct previous payments/retention
Issue certificate within 5 days
Payment due 14 days later
Assess variations
Hierarchy: Contract rates → analogous rates → daywork
Extension of time:
Additional time for Relevant Events beyond contractor’s control. Maintains liquidated damages entitlement.